In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA). This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.
I. MGNREGA: A brief introduction
A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households. Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development. Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.
B. Key features:
MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population. The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works. Table 1 provides information regarding employment generation and expenditure under MGNREGA.
Table 1: MGNREGA: Key indicators
Year |
Number of households provided employment (in crore) |
Average number of person days of work per household |
Total Expenditure (in lakh) |
2006-07 |
2.10 |
43 |
8823.35 |
2007-08 |
3.39 |
42 |
15856.88 |
2008-09 |
4.51 |
48 |
27250.10 |
2009-10 |
5.25 |
54 |
37905.23 |
2010-11 |
5.49 |
47 |
39377.27 |
2011-12* |
4.99 |
43 |
38034.69 |
2012-13** |
4.25 |
36 |
28073.51 |
Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013
II. Findings and Recommendations of the Standing Committee on Rural Development
A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:
B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include
Table 2: Work completion rate
Year |
Work completion rate (%) |
2006-07 |
46.34 |
2007-08 |
45.99 |
2008-09 |
43.76 |
2009-10 |
48.94 |
2010-11 |
50.86 |
2011-12* |
20.25 |
2012-13* |
15.02 |
Total | 33.22 |
Source: Standing Committee on Rural Development. Note: * As on 30.01.2013
C. Recommendations: The Committee made the following recommendations, based on its findings:
Over the last couple of weeks, MNREGA is back in the spotlight. The Union Minister for Rural Development wrote to certain states regarding potential misuse of funds, and it was announced that rural development schemes are open to CAG audit. In large schemes like MNREGA, officials at all levels of government - central, state, district, block, panchayat - have roles to play. This can make it difficult to locate the responsible authority in case implementation issues arise. We list the responsibilities of different government agencies involved in implementation of MNREGA in the Table below.
Stakeholder | Responsibilities | |
Gram Sabha | (a) recommending works; (b) conducting social audits on implementation every six months; and (c) functioning as a forum for sharing information. | |
Gram Panchayat | (a) planning works; (b) receiving applications for registration; (c) verifying applications; (d) registering households; (e) issuing job cards, (f) receiving applications for employment; (g) issuing detailed receipts; (h) allotting employment within 15 days of application; (i) executing works; (j) maintaining records; (k) convening Gram Sabha for social audit; and (l) monitoring implementation at the village level. | |
Intermediate Panchayat | (a) consolidating Gram Panchayat plans into a Block plan and (b) monitoring and supervision at the block level. | |
Programme Officer (PO) | (a) ensuring work to applicants within 15 days; (b) scrutinising Gram Panchayat annual development plans; (c) consolidating proposals into a Block plan and submitting to intermediate panchayat; (d) matching employment opportunities with demand for work at the Block level; (e) monitoring and supervising implementation; (f) disposing of complaints; (g) ensuring that Gram Sabha conducts social audits; and (h) payment of unemployment allowance. | |
District Panchayat | (a) finalizing district plans and labour budget; and (b) monitoring and supervising at district level. | |
District Programme Coordinator (DPC) | (a) ensuring that the scheme is implemented according to the Act at the district level; (b) information dissemination; (c) training; (d) consolidating block plans into a district plan; (e) ensuring that administrative and technical approval for projects are obtained on time; (f) release and utilisation of funds; (g) ensuring monitoring of works; (h) muster roll verifications; and (i) submitting monthly progress reports. | |
State Employment Guarantee Council (SEGC) | (a) advising the state government on implementation; (b) evaluate and monitor implementation; (c) determining the "preferred works" to be taken up; (d) recommending the proposal of works to be submitted to the state government; and (e) prepare an annual report to the state legislature. | |
State Government | (a) wide communication of the scheme; (b) setting up the SEGC; (c) setting up a State Employment Guarantee Fund; (d) ensuring that dedicated personnel are in place for implementation, including Gram Rozgar Sahayak, Programme Officer, and technical staff; (e) ensuring state share of the scheme budget is released on time; (f) delegation of financial and administrative powers to the DPC and Programme Officer if necessary; (g) training; (h) establishing a network of professional agencies for technical support and quality control; (i) regular review, monitoring, and evaluation of processes and outcomes; and (j) ensuring accountability and transparency. | |
Central Employment Guarantee Council | (a) advising the central government on MNREGA matters; (b) monitoring and evaluating implementation of the Act; and (c) preparing annual reports on implementation and submitting them to Parliament. | |
Ministry of Rural Development | (a) ensuring resource support to states and the CEGC; (b) regular review, monitoring, and evaluation of processes and outcomes; (c) maintaining and operating the MIS to capture and track data on critical aspects of implementation; (d) assessing the utilization of resources through a set of performance indicators; (e) supporting innovations that help in improving processes towards the achievement of the objectives of the Act; (f) support the use of Information Technology (IT) to increase the efficiency and transparency of the processes as well as improve interface with the public; and (g) ensuring that the implementation of NREGA at all levels is sought to be made transparent and accountable to the public.. | |
Source: Operational Guidelines, National Rural Employment Guarantee Scheme, Ministry of Rural Development. |