In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.

As of May 29, 2020, there are 1,65,799 confirmed cases of COVID-19 in India.  47,352 new cases have been registered in the last week (since May 22).  Out of the confirmed cases so far, 71,106 patients have been cured/discharged and 4,706 have died.  Most cases are in the state of Maharashtra (59,546) followed by the states of Tamil Nadu (19,372), Delhi (16,281) and Gujarat (15,562).  

With the spread of COVID-19, the central government initially undertook many measures to contain the spread of the pandemic, including restrictions on travel and movement through national lockdown.  With gradual resumption of activities, the central government has recently announced measures to ease restrictions on travel and movement.   Further, the government has continued to announce policy decisions to ease the financial stress caused by the pandemic, and to contain further spread of the pandemic.  In this blog post, we summarise some of the key measures taken by the central government in this regard between May 23 and May 29, 2020.

Figure 1: Day wise number of COVID-19 cases in the country

image

Source: Ministry of Health and Family Welfare; PRS.

Finance

RBI announces additional measures to ease financial stress caused by COVID-19

On May 22, the Reserve Bank of India (RBI) issued a statement with various development and regulatory policies to ease the financial stress caused by COVID-19.   These measures include: (i) improving liquidity in the market; (ii) support to exports and imports; and (iii) easing capital financing.  Subsequently, following measures have been notified by the RBI: 

  • In March 2020, the RBI had permitted all lending institutions to grant a moratorium of three months on payment of all term loans outstanding as of March 1, 2020.   This has been extended by another three months (till August 31, 2020).  Such deferment will not result in downgrade in asset classification.
     
  • For working capital such as cash credit or overdraft as well, lending institutions are permitted to allow a deferment of another three months on recovery of interest (till August 31, 2020). 
     
  • Currently, the exposure limit of a bank to a group of connected counterparties is 25% of the eligible capital base of the bank.  As a one-time measure to ease difficulty in raising funds, this limit has been relaxed to 30% of capital base of bank. 

Travel and Movement 

Domestic Air travel resumes; fare limits set by government

Domestic passenger air travel has been resumed in a phased manned (with one-third capacity of operations) from May 25, 2020 based on the announcement of the Ministry of Civil Aviation on May 21.  To ensure that airlines do not charge excessive fare and to ensure that journey is only for essential purposes, the Ministry of Civil Aviation issued an order to limit the minimum and maximum fare that airlines can charge from the passenger.   The routes have been divided in seven sectors based on the approximate duration of the flight.  For routes with shortest duration (for example, Delhi to Chandigarh), the minimum and maximum fare will be Rs 2,000 and Rs 6,000, respectively.  For routes with the longest duration (for example, Delhi to Thiruvananthapuram), the minimum and maximum fare will be Rs 6,500 and Rs 18,600, respectively. 

Further, the Ministry announced that all operational routes under the Regional Connectivity (UDAN) Scheme with up to 500 km of length or operational routes in priority areas (North East region, hilly states or islands) are permitted to resume operations.  This is in addition to the one-third capacity of operations announced earlier. 

Health

Guidelines for international arrivals issued

The Ministry of Health and Family Welfare issued guidelines for international arrivals.  All travellers are required to give an undertaking that they will undergo a 14-day mandatory institutional quarantine at their own cost (7 days in institutional quarantine followed by a 7-day isolation at home).  In emergency cases (such as pregnancy or death in the family), home quarantine will be permitted.  Use of Aarogya Setu app will be mandatory in such cases.  Only asymptomatic passengers will be allowed to board (flight/ship) after thermal screening.  On arrival, thermal screening will be carried out for all passengers.  The passengers found to be symptomatic will be isolated and taken to a medical facility. 

Movement of migrant labourers

Supreme Court gives an interim order regarding problems of migrant labourers

The Supreme Court of India took cognisance of the problems of migrant labourers who have been stranded in different parts of the country.  In its order, the Court observed that there are lapses being noticed in the process of registration, transportation and in providing food and shelter to the migrant workers.  In view of these difficulties, the Court issued the following interim directions:  

  • Free of cost food should be provided to the migrant workers who are stranded at different places in the country by the concerned state governments.  This information should be publicised and also notified to workers when they are waiting for their turn to board the train or bus.
     
  • The states should speed up the process of registration of migrant workers and provide help desk for registration.  Complete information regarding the modes of transport must be publicised to the workers.  
     
  • Fare should not be charged from migrant workers for travel by train or bus. The railway fare shall be shared by the states as per their arrangement.  The originating state of travel must provide water and meal during transportation.   In case of a train journey, Railways must provide water and meal during the journey. 
     
  • After the migrant workers reach their native place, the receiving state must provide health screening, transport and other facilities free of cost. 
     
  • Migrant workers found walking on highways or roads must be provided transportation to their destination and all facilities including food and water.

The Court directed the central and state governments to produce record of all necessary details such as the number of migrant workers, the plan to transport them to their destination, and the mechanism of registration. 

Other measures

PM CARES Fund included in the list of CSR eligible activities

The Ministry of Corporate Affairs notified the inclusion of PM CARES fund in the list of activities eligible for Corporate Social Responsibility (CSR) under the Companies Act, 2013.  Under the Act, companies with net worth, turnover or profits above a specified amount are required to spend 2% of their average net profits in the last three financial years towards CSR activities. This measure will come into effect retrospectively from March 28, 2020, when the fund was setup

For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.