Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified when applications open.

In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.

The increasing Non-Performing Assets (NPAs) in the Indian banking sector has recently been the subject of much discussion and scrutiny.  Yesterday, the Supreme Court struck down a circular dated February 12, 2018 issued by the Reserve Bank of India (RBI).  The RBI circular laid down a revised framework for the resolution of stressed assets.  In this blog, we examine the extent of NPAs in India, and recent events leading up to the Supreme Court judgement.

What is the extent and effect of the NPA problem in India?

Banks give loans and advances to borrowers. Based on the performance of the loan, it may be categorised as: (i) a standard asset (a loan where the borrower is making regular repayments), or (ii) a non-performing asset. NPAs are loans and advances where the borrower has stopped making interest or principal repayments for over 90 days.

As of 2018, the total NPAs in the economy stand at Rs 9.6 lakh crore.  About 88% of these NPAs are from loans and advances of public sector banks.  Banks are required to lend a certain percentage of their loans to priority sectors.  These sectors are identified by the RBI and include agriculture, housing, education and small scale industries.[1]  In 2018, of the total NPAs, 22% were from priority sector loans, and 78% were from non-priority sector loans. 

In the last few years, gross NPAs of banks (as a percentage of total loans) have increased from 2.3% of total loans in 2008 to 9.3% in 2017 (see Figure 1). This indicates that an increasing proportion of a bank’s assets have ceased to generate income for the bank, lowering the bank’s profitability and its ability to grant further credit.

Figure 1: Gross NPAs (% of total loans)

Source: Reserve Bank of India; PRS

What has been done to address the problem of growing NPAs?

The measures taken to resolve and prevent NPAs can broadly be classified into two kinds – first, remedial measures for banks prescribed by the RBI for internal restructuring of stressed assets, and second, legislative means of resolving NPAs under various laws (like the Insolvency and Bankruptcy Code, 2016).

Remedial Measures

Over the years, the RBI has issued various guidelines for banks aimed at the resolution of stressed assets in the economy. These included introduction of certain schemes such as: (i) Strategic Debt Restructuring (which allowed banks to change the management of the defaulting company), and (ii) Joint Lenders’ Forum (where lenders evolved a resolution plan and voted on its implementation).   A summary of the various schemes implemented by the RBI is provided in Table 1. 

Table 1: Non-legislative loan recovery framework

Loan restructuring

  • Banks internally undertake restructuring of loans, if the borrower is unable to repay the amount.  This involves changing the terms of repayment, which includes altering the payment schedule of loans or interest rates.

Corporate Debt Restructuring

  • Allows for restructuring of a borrower’s outstanding loans from more than one bank.  This mechanism is available if the borrower’s outstanding loans are more than Rs 10 crore.[2]

Joint Lender's Forum

  • Lenders evolve an action plan to resolve the NPA of a defaulter.[3]  If 60% of the creditors by value, and 50% of the creditors by number agree, a recovery plan will be implemented.[4]

5:25 Scheme

  • Banks can extend loan term to 25 years based on cash flow of projects for which the loan was given.  Interest rates and other terms of the loans may be readjusted every five years.[5]

Strategic Debt Restructuring

  • Banks convert their debt into equity to hold a majority of shares in a company.  This allows banks to change the management of the defaulting company.[6]

Sustainable Structuring of Stressed Assets

  • Allows for conversion of a part of the outstanding debt to equity or preference shares if: (i) project for which loan was taken has commenced operations, and (ii) borrower can repay over 50% of the loan.[7]

Sources: RBI scheme guidelines; Economic Survey 2016-17; PRS.

Legislative Measures

  • The Insolvency and Bankruptcy Code (IBC) was enacted in May 2016 to provide a time-bound 180-day recovery process for insolvent accounts. When a default occurs, the creditors or debtor may apply to the National Company Law Tribunal for initiating the resolution process. Once the application is approved, the resolution process will have to be completed within 180 days (extendable by 90 days) from the date of approval.  The resolution process will be presided over by an insolvency professional to decide whether to restructure the loan, or to sell the defaulter’s assets to recover the outstanding amount.  If a timely decision is not arrived at, the defaulter’s assets are liquidated.
  • The Banking Regulation (Amendment) Act, 2017: The amendment allows RBI to direct banks to initiate recovery proceedings against defaulting accounts under the IBC.  Further, under Section 35AA of the Act, RBI may also issue directions to banks for resolution of specific stressed assets. 

In June 2017, an internal advisory committee of RBI identified 500 defaulters with the highest value of NPAs.[8]  The committee recommended that 12 largest non-performing accounts, each with outstanding amounts greater than Rs 5,000 crore and totalling 25% of the NPAs of the economy, be referred for resolution under the IBC immediately.  Proceedings against the 12 largest defaulters have been initiated under the IBC. 

What was the February 12 circular issued by the RBI?

Subsequent to the enactment of the IBC, the RBI put in place a framework for restructuring of stressed assets of over Rs 2,000 crore on or after March 1, 2018.  The resolution plan for such restructuring must be unanimously approved by all lenders and implemented within 180 days from the date of the first default.  If the plan is not implemented within the stipulated time period, the stressed assets are required to be referred to the NCLT under IBC within 15 days.  Further, the framework introduced a provision for early identification and categorisation of stressed assets before they are classified as NPAs.

On what grounds was the RBI circular challenged?

Borrowers whose loans were tagged as NPAs before the release of the circular recently crossed the 180-day deadline for internal resolution by banks. Some of these borrowers, including various power producers and sugar mills, had appealed against the RBI circular in various High Courts. A two-judge bench of the Allahabad High Court ruled in favour of the RBI’s powers to issue these guidelines, and refused to grant interim relief to power producers from being taken to the NCLT for bankruptcy. These batch of petitions against the circular were transferred to the Supreme Court, which issued an order in September 2018 to maintain status quo on the same.

What did the Supreme Court order?

The Court held the circular issued by RBI was outside the scope of the power given to it under Article 35AA of the Banking Regulation (Amendment) Act, 2017.  The Court reasoned that Section 35AA was proposed by the 2017 Act to authorise the RBI to issues directions only in relation to specific cases of default by specific debtors.  It held that the RBI circular issued directions in relation to debtors in general and this was outside their scope of power.  The court also held that consequently all IBC proceedings initiated under the RBI circular are quashed. 

During the proceedings, various companies argued that the RBI circular applies to all corporate debtors alike, without looking into each individual’s sectors problems and attempting to solve them.  For instance, several power companies provided sector specific reasons for delay in payment of bank dues.  The reasons included: (i) cancellation of coal blocks by the SC leading to non-availability of fuel, (ii) lack of enough power purchase agreements by states, (iii) non-payment of dues by DISCOMs, and (iv) delays in project implementation leading to cost overruns.  Note that, in its 40th report, the Parliamentary Standing Committee on Energy analysed the impact of the RBI circular on the power sector and noted that the ‘one size fits all’ approach of the RBI is erroneous. 

 

 

[1] ‘Priority Sector Lending – Targets and Classification’ Reserve Bank of India, July 2012, https://rbi.org.in/scripts/NotificationUser.aspx?Id=7460&Mode=0

[2] Revised Guidelines on Corporate Debt Restructuring Mechanism, Reserve Bank of India, https://www.rbi.org.in/upload/notification/pdfs/67158.pdf

[3] ‘Framework for Revitalising Distressed Assets in the Economy – Guidelines on Joint Lenders’ Forum (JLF) and Corrective Action Plan (CAP)’, Reserve Bank of India, February 26, 2016, https://www.rbi.org.in/scripts/NotificationUser.aspx?Id=8754&Mode=0

[4] Timelines for Stressed Assets, Press Release, Reserve Bank of India, May 5, 2017, https://www.rbi.org.in/Scripts/NotificationUser.aspx?Id=10957&Mode=0

[5] Flexible Structuring of Long Term Project Loans to Infrastructure and Core Industries, RBI, July 15, 2014, https://www.rbi.org.in/scripts/NotificationUser.aspx?Id=9101&Mode=0

[6] Chapter 4, The Economic Survey 2016-17, http://unionbudget.nic.in/es2016-17/echap04.pdf

[7] ‘RBI introduces a ‘Scheme for Sustainable Structuring of Stressed Assets’’ Press Release, Reserve Bank of India, June 13, 2016, https://www.rbi.org.in/Scripts/BS_PressReleaseDisplay.aspx?prid=37210

[8] RBI identifies Accounts for Reference by Banks under the Insolvency and Bankruptcy Code (IBC), Reserve Bank of India, June 13, 2017, https://www.rbi.org.in/scripts/BS_PressReleaseDisplay.aspx?prid=40743