In the last decade, the government has implemented several schemes to address issues related to urbanisation and aid the process of urban development.  One of the schemes is the Smart Cities Mission, which intends to take advantage of the developments in information technology in developing the urban development strategy, across 100 cities.  Last week the government announced the list of 9 new Smart Cities, taking the total to 99.  In light of this, we look at the Smart Cities Mission and a few issues with it.

What is a Smart City?

The primary objective of the Mission is to develop cities that provide core infrastructure and give a decent quality of life to its citizens, a clean and sustainable environment, and apply ‘smart’ solutions.

However, the Mission document does not provide one definition of a Smart City.  Instead it allows cities to come up with their own solutions of what they identify as a Smart City.  The guidelines suggest that the core infrastructure elements in a Smart City will include: (i) adequate water supply, (ii) assured electricity supply, (iii) sanitation, including solid waste management, (iv) efficient urban mobility and public transport, (v) affordable housing, (vi) robust IT connectivity, and (vii) good governance.  ‘Smart’ solutions may include (i) energy efficient buildings, (ii) electronic service delivery, (iii) intelligent traffic management, (iv) smart metering, (v) citizen engagement, etc.

How were the Smart Cities selected?

The Mission was introduced in the form of a competition, called the Smart City challenge.  The first stage was in July 2015 when states nominated their cities for the competition.  In August 2015, the Ministry of Urban Development selected 100 of those cities to participate in the competition.  These cities were required to develop their smart city plans (SCPs) and compete against each other.  The SCPs were evaluated on the basis of the solutions, the processes followed, the feasibility and cost effectiveness of the plans, and citizen engagement.  Over the last 2 years, the Ministry has announced winner cities in batches.  So far, 99 cities have been selected under the Mission.

What information do these SCPs contain?

The cities had to prepare their SCPs with two primary strategic components: (i) area-based development, and (ii) pan-city development.  The area-based development would cover a particular area of the city, and could have either a redevelopment model, or be a completely new development.  Pan-city development would envisage application of certain smart solutions across the city to the existing infrastructure.

Each city had to formulate its own concept, vision, mission and plan for a Smart City that was appropriate to its local context and resources.  The Ministry of Urban Development provided technical assistance, through consultancy firms, to cities for helping them prepare these strategic documents.

How will the Mission be implemented?

The Mission will be implemented at the city level by a Special Purpose Vehicle (SPV).  The SPV will plan, approve, release funds, implement, manage, monitor, and evaluate the Smart City development projects.

The SPV will be a limited company incorporated under the Companies Act, 2013 at the city-level.  It will be chaired by the Collector/ Municipal Commissioner of the Urban Development Authority.  The respective state and the Urban Local Body (ULB or municipality) will be the promoters in this company having 50:50 equity shareholding.

How are the Plans getting financed?

The Mission will be operated as a Centrally Sponsored Scheme.  The central government will provide financial support of up to Rs 48,000 crore over five years, that is, an average of Rs 500 crore per city.  The states and ULBs will have to contribute an equal amount.  The central government allocated Rs 4,000 crore towards the Mission in the 2017-18 budget.

Since funding from the government will meet only a part of the funding required, the rest will have to be raised from other sources including: (i) states/ ULBs own resources from collection of user fees, land monetization, etc., (ii) innovative finance mechanisms such as municipal bonds, (iii) leverage borrowings from financial institutions (such as banks), and (iv) the private sector through Public Private Partnerships (PPPs).

The total cost of projects proposed under the various SCPs of the 90 winner cities is Rs 1.9 lakh crore.  About 42% of this amount will come from central and state funding, 23% through private investments and PPPs, and 19% through convergence with other schemes (such as HRIDAY, AMRUT, Swachh Bharat-Urban).  The remaining will be generated by the cities through the levy of local taxes, and user fees.

What are some of the issues to consider?

Financial capacity of cities:  Under the Mission, cities have to generate additional revenue through various sources including market borrowings, PPPs, and land monetization.  The High Powered Expert Committee on Indian Urban Infrastructure and Services (HPEC) had observed that ULBs in India are among the weakest in the world, both in terms of capacity to raise resources and financial autonomy.  Even though ULBs have been getting higher allocations from the centre and states, and tax devolution to them has increased, their own tax bases are narrow.  Further, owing to their poor governance and financial situation, ULBs find it difficult to access external financing.

Such a situation may pose problems when implementing the Mission, where the ULBs have to raise a significant share of the revenue through external sources (PPPs, market borrowings).  For example, the Bhubaneswar Smart City Plan has a total project cost of Rs 4,537 crore (over five years), while the city’s annual budget for 2014-15 was Rs 469 crore.

In order to improve the finances of the ULBs, committees have made various recommendations, which include:

  • State governments make legislative changes to give more taxation powers and autonomy to ULBs for improving their revenue collections.
  • ULBs could raise their own revenue by tapping into land-based financing sources, and introducing reforms to strengthen non-tax revenues (such as water and sewerage charges, parking fees, etc.).
  • Municipal bonds may also be used as a source of revenue for ULBs.

The government has recently introduced a few policies and mechanisms to address municipal financing.  Examples include value capture financing through public investments in infrastructure projects, and a credit rating system for cities.  In June 2017, the Pune Municipal Corporation raised Rs 200 crore by issuing municipal bonds.

Technical capacity of the ULBs:  The Smart Cities Mission seeks to empower ULBs to raise their own revenue, and also lays emphasis on the capacity building of ULBs.  The HPEC had observed that municipal administration has suffered due to: (i) presence of untrained and unskilled manpower, and (ii) shortage of qualified technical staff and managerial supervisors.  It had recommended improving the technical capacity of ULBs by providing technical assistance to state governments, and ULBs in planning, financing, monitoring, and operation of urban programmes.  The central government had allocated Rs 10.5 crore towards the capacity building component of the Mission in 2017-18.

The Ministry of Urban Development has been running several programmes to improve capacity of ULBs.  This includes MoUs with 18 states to conduct training programmes for their ULB staff.

Coverage of the Mission:  The Mission covers 100 cities, of which 99 have been announced as winners so far.   The urban population that will be impacted through the Mission is around 96 million (data for 90 cities excluding the recently announced 9 cities).

As per Census 2011, India’s urban population was 377 million.  The Mission impacts about 25% of this population.  Further, most of the SCPs approved so far focus on area-based development, thus affecting a particular area of the cities.  About 80% of the total project cost proposed is towards this model of development.  In each city, this area-based development will cover up to 50 acres of area.  The remaining 20% of the project cost is towards pan-city development proposals, which provide smart planning solutions for the entire city.  It may be argued that even within the selected cities, the Mission will only impact few selected areas, and not necessarily help with development of the entire city.

Recently, the Cabinet Committee on Economic Affairs approved an increase in the Minimum Support Prices (MSPs) for Kharif crops for the 2018-19 marketing season.  Subsequently, the Commission for Agricultural Costs and Prices (CACP) released its price policy report for Kharif crops for the marketing season 2018-19.

The central government notifies MSPs based on the recommendations of the CACP.  These recommendations are made separately for the Kharif marketing season (KMS) and the Rabi marketing season (RMS).  Post harvesting, the government procures crops from farmers at the MSP notified for that season, in order to ensure remunerative prices to farmers for their produce.

In this blog post, we look at how MSPs are determined, changes brought in them over time, and their effectiveness for farmers across different states.

How are Minimum Support Prices determined?

The CACP considers various factors such as the cost of cultivation and production, productivity of crops, and market prices for the determination of MSPs.  The National Commission on Farmers(Chair: Prof. M. S. Swaminathan) in 2006 had recommended that MSPs must be at least 50% more than the cost of production.  In this year’s budget speech, the Finance Minister said that MSPs would be fixed at least at 50% more than the cost of production.

The CACP calculates cost of production at three levels: (i) A2, which includes cost of inputs such as seeds, fertilizer, labour; (ii) A2+FL, which includes the implied cost of family labour (FL); and (iii) C2, which includes the implied rent on land and interest on capital assets over and above A2+FL.

Table 1 shows the cost of production as calculated by the CACP and the approved MSPs for KMS 2018-19.  For paddy (common), the MSP was increased from Rs 1,550/quintal in 2017-18 to Rs 1,750/quintal in 2018-19.  This price would give a farmer a profit of 50.1% on the cost of production A2+FL.  However, the profit calculated on the cost of production C2 would be 12.2%.  It has been argued that the cost of production should be taken as C2 for calculating MSPs.  In such a scenario, this would have increased the MSP to Rs 2,340/quintal, much above the current MSP of Rs 1,750/quintal.

Figure 1

Which are the major crops that are procured at MSPs?

Every year, MSPs are announced for 23 crops.  However, public procurement is limited to a few crops such as paddy, wheat and, to a limited extent, pulses as shown in Figure 1.

Figure 2

The procurement is also limited to a few states.  Three states which produce 49% of the national wheat output account for 93% of procurement.  For paddy, six states with 40% production share have 77% share of the procurement.  As a result, in these states, farmers focus on cultivating these crops over other crops such as pulses, oilseeds, and coarse grains.

Due to limitations on the procurement side (both crop-wise and state-wise), all farmers do not receive benefits of increase in MSPs.  The CACP has noted in its 2018-19 price policy report that the inability of farmers to sell at MSPs is one of the key areas of concern.  Farmers who are unable to sell their produce at MSPs have to sell it at market prices, which may be much lower than the MSPs.

How have MSPs for major crops changed over time?

Higher procurement of paddy and wheat, as compared to other crops at MSPs tilts the production cycle towards these crops.  In order to balance this and encourage the production of pulses, there is a larger proportional increase in the MSPs of pulses over the years as seen in Figure 2.  In addition to this, it is also used as a measure to encourage farmers to shift from water-intensive crops such as paddy and wheat to pulses, which relatively require less water for irrigation.

Figure 3

What is the effectiveness of MSPs across states?

The MSP fixed for each crop is uniform for the entire country.  However, the production cost of crops vary across states.  Figure 3 highlights the MSP of paddy and the variation in its cost of production across states in 2018-19.

Figure 4

For example, production cost for paddy at the A2+FL level is Rs 702/quintal in Punjab and Rs 2,102/quintal in Maharashtra.  Due to this differentiation, while the MSP of Rs 1,750/quintal of paddy will result in a profit of 149% to a farmer in Punjab, it will result in a loss of 17% to a farmer in Maharashtra.  Similarly, at the C2 level, the production cost for paddy is Rs 1,174/quintal in Punjab and Rs 2,481/quintal in Maharashtra.  In this scenario, a farmer in Punjab may get 49% return, while his counterpart in Maharashtra may make a loss of 29%.

Figure 5

Figure 4 highlights the MSP of wheat and the variation in its cost of production across states in 2017-18. In the case of wheat, the cost of production in Maharashtra and West Bengal is much more than the cost in rest of the states.  At the A2+FL level, the cost of production in West Bengal is Rs 1,777/quintal.  This is significantly higher than in states like Haryana and Punjab, where the cost is Rs 736/quintal and Rs 642/quintal, respectively.  In this case, while a wheat growing farmer suffers a loss of 2% in West Bengal, a farmer in Haryana makes a profit of 136%.  The return in Punjab is even higher at 1.5 times or more the cost of production.