In the last decade, the government has implemented several schemes to address issues related to urbanisation and aid the process of urban development.  One of the schemes is the Smart Cities Mission, which intends to take advantage of the developments in information technology in developing the urban development strategy, across 100 cities.  Last week the government announced the list of 9 new Smart Cities, taking the total to 99.  In light of this, we look at the Smart Cities Mission and a few issues with it.

What is a Smart City?

The primary objective of the Mission is to develop cities that provide core infrastructure and give a decent quality of life to its citizens, a clean and sustainable environment, and apply ‘smart’ solutions.

However, the Mission document does not provide one definition of a Smart City.  Instead it allows cities to come up with their own solutions of what they identify as a Smart City.  The guidelines suggest that the core infrastructure elements in a Smart City will include: (i) adequate water supply, (ii) assured electricity supply, (iii) sanitation, including solid waste management, (iv) efficient urban mobility and public transport, (v) affordable housing, (vi) robust IT connectivity, and (vii) good governance.  ‘Smart’ solutions may include (i) energy efficient buildings, (ii) electronic service delivery, (iii) intelligent traffic management, (iv) smart metering, (v) citizen engagement, etc.

How were the Smart Cities selected?

The Mission was introduced in the form of a competition, called the Smart City challenge.  The first stage was in July 2015 when states nominated their cities for the competition.  In August 2015, the Ministry of Urban Development selected 100 of those cities to participate in the competition.  These cities were required to develop their smart city plans (SCPs) and compete against each other.  The SCPs were evaluated on the basis of the solutions, the processes followed, the feasibility and cost effectiveness of the plans, and citizen engagement.  Over the last 2 years, the Ministry has announced winner cities in batches.  So far, 99 cities have been selected under the Mission.

What information do these SCPs contain?

The cities had to prepare their SCPs with two primary strategic components: (i) area-based development, and (ii) pan-city development.  The area-based development would cover a particular area of the city, and could have either a redevelopment model, or be a completely new development.  Pan-city development would envisage application of certain smart solutions across the city to the existing infrastructure.

Each city had to formulate its own concept, vision, mission and plan for a Smart City that was appropriate to its local context and resources.  The Ministry of Urban Development provided technical assistance, through consultancy firms, to cities for helping them prepare these strategic documents.

How will the Mission be implemented?

The Mission will be implemented at the city level by a Special Purpose Vehicle (SPV).  The SPV will plan, approve, release funds, implement, manage, monitor, and evaluate the Smart City development projects.

The SPV will be a limited company incorporated under the Companies Act, 2013 at the city-level.  It will be chaired by the Collector/ Municipal Commissioner of the Urban Development Authority.  The respective state and the Urban Local Body (ULB or municipality) will be the promoters in this company having 50:50 equity shareholding.

How are the Plans getting financed?

The Mission will be operated as a Centrally Sponsored Scheme.  The central government will provide financial support of up to Rs 48,000 crore over five years, that is, an average of Rs 500 crore per city.  The states and ULBs will have to contribute an equal amount.  The central government allocated Rs 4,000 crore towards the Mission in the 2017-18 budget.

Since funding from the government will meet only a part of the funding required, the rest will have to be raised from other sources including: (i) states/ ULBs own resources from collection of user fees, land monetization, etc., (ii) innovative finance mechanisms such as municipal bonds, (iii) leverage borrowings from financial institutions (such as banks), and (iv) the private sector through Public Private Partnerships (PPPs).

The total cost of projects proposed under the various SCPs of the 90 winner cities is Rs 1.9 lakh crore.  About 42% of this amount will come from central and state funding, 23% through private investments and PPPs, and 19% through convergence with other schemes (such as HRIDAY, AMRUT, Swachh Bharat-Urban).  The remaining will be generated by the cities through the levy of local taxes, and user fees.

What are some of the issues to consider?

Financial capacity of cities:  Under the Mission, cities have to generate additional revenue through various sources including market borrowings, PPPs, and land monetization.  The High Powered Expert Committee on Indian Urban Infrastructure and Services (HPEC) had observed that ULBs in India are among the weakest in the world, both in terms of capacity to raise resources and financial autonomy.  Even though ULBs have been getting higher allocations from the centre and states, and tax devolution to them has increased, their own tax bases are narrow.  Further, owing to their poor governance and financial situation, ULBs find it difficult to access external financing.

Such a situation may pose problems when implementing the Mission, where the ULBs have to raise a significant share of the revenue through external sources (PPPs, market borrowings).  For example, the Bhubaneswar Smart City Plan has a total project cost of Rs 4,537 crore (over five years), while the city’s annual budget for 2014-15 was Rs 469 crore.

In order to improve the finances of the ULBs, committees have made various recommendations, which include:

  • State governments make legislative changes to give more taxation powers and autonomy to ULBs for improving their revenue collections.
  • ULBs could raise their own revenue by tapping into land-based financing sources, and introducing reforms to strengthen non-tax revenues (such as water and sewerage charges, parking fees, etc.).
  • Municipal bonds may also be used as a source of revenue for ULBs.

The government has recently introduced a few policies and mechanisms to address municipal financing.  Examples include value capture financing through public investments in infrastructure projects, and a credit rating system for cities.  In June 2017, the Pune Municipal Corporation raised Rs 200 crore by issuing municipal bonds.

Technical capacity of the ULBs:  The Smart Cities Mission seeks to empower ULBs to raise their own revenue, and also lays emphasis on the capacity building of ULBs.  The HPEC had observed that municipal administration has suffered due to: (i) presence of untrained and unskilled manpower, and (ii) shortage of qualified technical staff and managerial supervisors.  It had recommended improving the technical capacity of ULBs by providing technical assistance to state governments, and ULBs in planning, financing, monitoring, and operation of urban programmes.  The central government had allocated Rs 10.5 crore towards the capacity building component of the Mission in 2017-18.

The Ministry of Urban Development has been running several programmes to improve capacity of ULBs.  This includes MoUs with 18 states to conduct training programmes for their ULB staff.

Coverage of the Mission:  The Mission covers 100 cities, of which 99 have been announced as winners so far.   The urban population that will be impacted through the Mission is around 96 million (data for 90 cities excluding the recently announced 9 cities).

As per Census 2011, India’s urban population was 377 million.  The Mission impacts about 25% of this population.  Further, most of the SCPs approved so far focus on area-based development, thus affecting a particular area of the cities.  About 80% of the total project cost proposed is towards this model of development.  In each city, this area-based development will cover up to 50 acres of area.  The remaining 20% of the project cost is towards pan-city development proposals, which provide smart planning solutions for the entire city.  It may be argued that even within the selected cities, the Mission will only impact few selected areas, and not necessarily help with development of the entire city.

On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.