In the last decade, the government has implemented several schemes to address issues related to urbanisation and aid the process of urban development.  One of the schemes is the Smart Cities Mission, which intends to take advantage of the developments in information technology in developing the urban development strategy, across 100 cities.  Last week the government announced the list of 9 new Smart Cities, taking the total to 99.  In light of this, we look at the Smart Cities Mission and a few issues with it.

What is a Smart City?

The primary objective of the Mission is to develop cities that provide core infrastructure and give a decent quality of life to its citizens, a clean and sustainable environment, and apply ‘smart’ solutions.

However, the Mission document does not provide one definition of a Smart City.  Instead it allows cities to come up with their own solutions of what they identify as a Smart City.  The guidelines suggest that the core infrastructure elements in a Smart City will include: (i) adequate water supply, (ii) assured electricity supply, (iii) sanitation, including solid waste management, (iv) efficient urban mobility and public transport, (v) affordable housing, (vi) robust IT connectivity, and (vii) good governance.  ‘Smart’ solutions may include (i) energy efficient buildings, (ii) electronic service delivery, (iii) intelligent traffic management, (iv) smart metering, (v) citizen engagement, etc.

How were the Smart Cities selected?

The Mission was introduced in the form of a competition, called the Smart City challenge.  The first stage was in July 2015 when states nominated their cities for the competition.  In August 2015, the Ministry of Urban Development selected 100 of those cities to participate in the competition.  These cities were required to develop their smart city plans (SCPs) and compete against each other.  The SCPs were evaluated on the basis of the solutions, the processes followed, the feasibility and cost effectiveness of the plans, and citizen engagement.  Over the last 2 years, the Ministry has announced winner cities in batches.  So far, 99 cities have been selected under the Mission.

What information do these SCPs contain?

The cities had to prepare their SCPs with two primary strategic components: (i) area-based development, and (ii) pan-city development.  The area-based development would cover a particular area of the city, and could have either a redevelopment model, or be a completely new development.  Pan-city development would envisage application of certain smart solutions across the city to the existing infrastructure.

Each city had to formulate its own concept, vision, mission and plan for a Smart City that was appropriate to its local context and resources.  The Ministry of Urban Development provided technical assistance, through consultancy firms, to cities for helping them prepare these strategic documents.

How will the Mission be implemented?

The Mission will be implemented at the city level by a Special Purpose Vehicle (SPV).  The SPV will plan, approve, release funds, implement, manage, monitor, and evaluate the Smart City development projects.

The SPV will be a limited company incorporated under the Companies Act, 2013 at the city-level.  It will be chaired by the Collector/ Municipal Commissioner of the Urban Development Authority.  The respective state and the Urban Local Body (ULB or municipality) will be the promoters in this company having 50:50 equity shareholding.

How are the Plans getting financed?

The Mission will be operated as a Centrally Sponsored Scheme.  The central government will provide financial support of up to Rs 48,000 crore over five years, that is, an average of Rs 500 crore per city.  The states and ULBs will have to contribute an equal amount.  The central government allocated Rs 4,000 crore towards the Mission in the 2017-18 budget.

Since funding from the government will meet only a part of the funding required, the rest will have to be raised from other sources including: (i) states/ ULBs own resources from collection of user fees, land monetization, etc., (ii) innovative finance mechanisms such as municipal bonds, (iii) leverage borrowings from financial institutions (such as banks), and (iv) the private sector through Public Private Partnerships (PPPs).

The total cost of projects proposed under the various SCPs of the 90 winner cities is Rs 1.9 lakh crore.  About 42% of this amount will come from central and state funding, 23% through private investments and PPPs, and 19% through convergence with other schemes (such as HRIDAY, AMRUT, Swachh Bharat-Urban).  The remaining will be generated by the cities through the levy of local taxes, and user fees.

What are some of the issues to consider?

Financial capacity of cities:  Under the Mission, cities have to generate additional revenue through various sources including market borrowings, PPPs, and land monetization.  The High Powered Expert Committee on Indian Urban Infrastructure and Services (HPEC) had observed that ULBs in India are among the weakest in the world, both in terms of capacity to raise resources and financial autonomy.  Even though ULBs have been getting higher allocations from the centre and states, and tax devolution to them has increased, their own tax bases are narrow.  Further, owing to their poor governance and financial situation, ULBs find it difficult to access external financing.

Such a situation may pose problems when implementing the Mission, where the ULBs have to raise a significant share of the revenue through external sources (PPPs, market borrowings).  For example, the Bhubaneswar Smart City Plan has a total project cost of Rs 4,537 crore (over five years), while the city’s annual budget for 2014-15 was Rs 469 crore.

In order to improve the finances of the ULBs, committees have made various recommendations, which include:

  • State governments make legislative changes to give more taxation powers and autonomy to ULBs for improving their revenue collections.
  • ULBs could raise their own revenue by tapping into land-based financing sources, and introducing reforms to strengthen non-tax revenues (such as water and sewerage charges, parking fees, etc.).
  • Municipal bonds may also be used as a source of revenue for ULBs.

The government has recently introduced a few policies and mechanisms to address municipal financing.  Examples include value capture financing through public investments in infrastructure projects, and a credit rating system for cities.  In June 2017, the Pune Municipal Corporation raised Rs 200 crore by issuing municipal bonds.

Technical capacity of the ULBs:  The Smart Cities Mission seeks to empower ULBs to raise their own revenue, and also lays emphasis on the capacity building of ULBs.  The HPEC had observed that municipal administration has suffered due to: (i) presence of untrained and unskilled manpower, and (ii) shortage of qualified technical staff and managerial supervisors.  It had recommended improving the technical capacity of ULBs by providing technical assistance to state governments, and ULBs in planning, financing, monitoring, and operation of urban programmes.  The central government had allocated Rs 10.5 crore towards the capacity building component of the Mission in 2017-18.

The Ministry of Urban Development has been running several programmes to improve capacity of ULBs.  This includes MoUs with 18 states to conduct training programmes for their ULB staff.

Coverage of the Mission:  The Mission covers 100 cities, of which 99 have been announced as winners so far.   The urban population that will be impacted through the Mission is around 96 million (data for 90 cities excluding the recently announced 9 cities).

As per Census 2011, India’s urban population was 377 million.  The Mission impacts about 25% of this population.  Further, most of the SCPs approved so far focus on area-based development, thus affecting a particular area of the cities.  About 80% of the total project cost proposed is towards this model of development.  In each city, this area-based development will cover up to 50 acres of area.  The remaining 20% of the project cost is towards pan-city development proposals, which provide smart planning solutions for the entire city.  It may be argued that even within the selected cities, the Mission will only impact few selected areas, and not necessarily help with development of the entire city.

In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.