In the last decade, the government has implemented several schemes to address issues related to urbanisation and aid the process of urban development.  One of the schemes is the Smart Cities Mission, which intends to take advantage of the developments in information technology in developing the urban development strategy, across 100 cities.  Last week the government announced the list of 9 new Smart Cities, taking the total to 99.  In light of this, we look at the Smart Cities Mission and a few issues with it.

What is a Smart City?

The primary objective of the Mission is to develop cities that provide core infrastructure and give a decent quality of life to its citizens, a clean and sustainable environment, and apply ‘smart’ solutions.

However, the Mission document does not provide one definition of a Smart City.  Instead it allows cities to come up with their own solutions of what they identify as a Smart City.  The guidelines suggest that the core infrastructure elements in a Smart City will include: (i) adequate water supply, (ii) assured electricity supply, (iii) sanitation, including solid waste management, (iv) efficient urban mobility and public transport, (v) affordable housing, (vi) robust IT connectivity, and (vii) good governance.  ‘Smart’ solutions may include (i) energy efficient buildings, (ii) electronic service delivery, (iii) intelligent traffic management, (iv) smart metering, (v) citizen engagement, etc.

How were the Smart Cities selected?

The Mission was introduced in the form of a competition, called the Smart City challenge.  The first stage was in July 2015 when states nominated their cities for the competition.  In August 2015, the Ministry of Urban Development selected 100 of those cities to participate in the competition.  These cities were required to develop their smart city plans (SCPs) and compete against each other.  The SCPs were evaluated on the basis of the solutions, the processes followed, the feasibility and cost effectiveness of the plans, and citizen engagement.  Over the last 2 years, the Ministry has announced winner cities in batches.  So far, 99 cities have been selected under the Mission.

What information do these SCPs contain?

The cities had to prepare their SCPs with two primary strategic components: (i) area-based development, and (ii) pan-city development.  The area-based development would cover a particular area of the city, and could have either a redevelopment model, or be a completely new development.  Pan-city development would envisage application of certain smart solutions across the city to the existing infrastructure.

Each city had to formulate its own concept, vision, mission and plan for a Smart City that was appropriate to its local context and resources.  The Ministry of Urban Development provided technical assistance, through consultancy firms, to cities for helping them prepare these strategic documents.

How will the Mission be implemented?

The Mission will be implemented at the city level by a Special Purpose Vehicle (SPV).  The SPV will plan, approve, release funds, implement, manage, monitor, and evaluate the Smart City development projects.

The SPV will be a limited company incorporated under the Companies Act, 2013 at the city-level.  It will be chaired by the Collector/ Municipal Commissioner of the Urban Development Authority.  The respective state and the Urban Local Body (ULB or municipality) will be the promoters in this company having 50:50 equity shareholding.

How are the Plans getting financed?

The Mission will be operated as a Centrally Sponsored Scheme.  The central government will provide financial support of up to Rs 48,000 crore over five years, that is, an average of Rs 500 crore per city.  The states and ULBs will have to contribute an equal amount.  The central government allocated Rs 4,000 crore towards the Mission in the 2017-18 budget.

Since funding from the government will meet only a part of the funding required, the rest will have to be raised from other sources including: (i) states/ ULBs own resources from collection of user fees, land monetization, etc., (ii) innovative finance mechanisms such as municipal bonds, (iii) leverage borrowings from financial institutions (such as banks), and (iv) the private sector through Public Private Partnerships (PPPs).

The total cost of projects proposed under the various SCPs of the 90 winner cities is Rs 1.9 lakh crore.  About 42% of this amount will come from central and state funding, 23% through private investments and PPPs, and 19% through convergence with other schemes (such as HRIDAY, AMRUT, Swachh Bharat-Urban).  The remaining will be generated by the cities through the levy of local taxes, and user fees.

What are some of the issues to consider?

Financial capacity of cities:  Under the Mission, cities have to generate additional revenue through various sources including market borrowings, PPPs, and land monetization.  The High Powered Expert Committee on Indian Urban Infrastructure and Services (HPEC) had observed that ULBs in India are among the weakest in the world, both in terms of capacity to raise resources and financial autonomy.  Even though ULBs have been getting higher allocations from the centre and states, and tax devolution to them has increased, their own tax bases are narrow.  Further, owing to their poor governance and financial situation, ULBs find it difficult to access external financing.

Such a situation may pose problems when implementing the Mission, where the ULBs have to raise a significant share of the revenue through external sources (PPPs, market borrowings).  For example, the Bhubaneswar Smart City Plan has a total project cost of Rs 4,537 crore (over five years), while the city’s annual budget for 2014-15 was Rs 469 crore.

In order to improve the finances of the ULBs, committees have made various recommendations, which include:

  • State governments make legislative changes to give more taxation powers and autonomy to ULBs for improving their revenue collections.
  • ULBs could raise their own revenue by tapping into land-based financing sources, and introducing reforms to strengthen non-tax revenues (such as water and sewerage charges, parking fees, etc.).
  • Municipal bonds may also be used as a source of revenue for ULBs.

The government has recently introduced a few policies and mechanisms to address municipal financing.  Examples include value capture financing through public investments in infrastructure projects, and a credit rating system for cities.  In June 2017, the Pune Municipal Corporation raised Rs 200 crore by issuing municipal bonds.

Technical capacity of the ULBs:  The Smart Cities Mission seeks to empower ULBs to raise their own revenue, and also lays emphasis on the capacity building of ULBs.  The HPEC had observed that municipal administration has suffered due to: (i) presence of untrained and unskilled manpower, and (ii) shortage of qualified technical staff and managerial supervisors.  It had recommended improving the technical capacity of ULBs by providing technical assistance to state governments, and ULBs in planning, financing, monitoring, and operation of urban programmes.  The central government had allocated Rs 10.5 crore towards the capacity building component of the Mission in 2017-18.

The Ministry of Urban Development has been running several programmes to improve capacity of ULBs.  This includes MoUs with 18 states to conduct training programmes for their ULB staff.

Coverage of the Mission:  The Mission covers 100 cities, of which 99 have been announced as winners so far.   The urban population that will be impacted through the Mission is around 96 million (data for 90 cities excluding the recently announced 9 cities).

As per Census 2011, India’s urban population was 377 million.  The Mission impacts about 25% of this population.  Further, most of the SCPs approved so far focus on area-based development, thus affecting a particular area of the cities.  About 80% of the total project cost proposed is towards this model of development.  In each city, this area-based development will cover up to 50 acres of area.  The remaining 20% of the project cost is towards pan-city development proposals, which provide smart planning solutions for the entire city.  It may be argued that even within the selected cities, the Mission will only impact few selected areas, and not necessarily help with development of the entire city.

Recently, there have been multiple Naxal attacks on CRPF personnel in Chhattisgarh.  Parliamentary Committees have previously examined the working of the Central Armed Police Forces (CAPFs).  In this context, we examine issues related to functioning of these Forces and recommendations made to address them.

What is the role of the Central Armed Police Forces (CAPFs)?

Under the Constitution, police and public order are state subjects.  However, the Ministry of Home Affairs (MHA) assists state governments by providing them support of the Central Armed Police Forces.  The Ministry maintains seven CAPFs: (i) the Central Reserve Police Force, which assists in internal security and counterinsurgency, (ii) the Central Industrial Security Force, which protects vital installations (like airports) and public sector undertakings, (iii) the National Security Guards, which is a special counterterrorism force, and (iv) four border guarding forces, which are the Border Security Force, Indo-Tibetan Border Police, Sashastra Seema Bal, and Assam Rifles.

What is the sanctioned strength of CAPFs personnel compared to the actual strength?

As of January 2017, the sanctioned strength of the seven CAPFs was 10,78,514 personnel.  However, 15% of these posts (1,58,591 posts) were lying vacant.  Data from the Bureau of Police Research and Development shows that vacancies in the CAPFs have remained over the years.  Table 1 shows the level of vacancies in the seven CAPFs between 2012 and 2017. Nov 2The level of vacancies is different for various police forces.  For example, in 2017, the Sashastra Seema Bal had the highest level of vacancies at 57%.  On the other hand, the Border Security Force had 2% vacancies.  The Central Reserve Police Force, which account for 30% of the sanctioned strength of the seven CAPFs, had a vacancy of 8%.

How often are CAPFs deployed?

According to the Estimates Committee of Parliament, the number of deployment of CAPFs battalions has increased from 91 in 2012-13 to 119 in 2016-17.  The Committee has noted that there has been heavy dependence by states on central police forces even for day-to-day law and order issues.  This is likely to affect anti-insurgency and border-guarding operations of the Forces, as well as curtail their time for training.  The continuous deployment also leaves less time for rest and recuperation.

The Estimates Committee recommended that states must develop their own systems, and augment their police forces by providing adequate training and equipment.  It further recommended that the central government should supplement the efforts of state governments by providing financial assistance and other help for capacity building of their forces.

What is the financial allocation to CAPFs?

Under the Union Budget 2018-19, an allocation of Rs 62,741 crore was made to the seven CAPFs.  Of this, 32% (Rs 20,268 crore) has been allocated to the Central Reserve Police Forces.  The Estimates Committee has pointed out that most of the expenditure of the CAPFs was on salaries.  According to the Committee, the financial performance in case of outlays allocated for capacity augmentation has been very poor.  For example, under the Modernization Plan-II, Rs 11,009 crore was approved for the period 2012-17.  However, the allocation during the period 2013-16 was Rs 251 crore and the reported expenditure was Rs 198 crore.

What are the working conditions for CAPFs personnel?

The Standing Committee on Home Affairs in the year 2017 had expressed concern over the working conditions of personnel of the border guarding forces (Border Security Force, Assam Rifles, Indo-Tibetan Border Police, and Sashastra Seema Bal).  The Committee observed that they had to work 16-18 hours a day, with little time for rest or sleep.  The personnel were also not satisfied with medical facilities that had been provided at border locations.

In addition, the Standing Committee observed that personnel of the CAPFs have not been treated at par with the Armed Forces, in terms of pay and allowances.  The demand for Paramilitary Service Pay, similar to Military Service Pay, had not been agreed to by the Seventh Central Pay Commission.  Further, the Committee observed that the hard-area allowance for personnel of the border guarding forces was much lower as compared to members of the Armed Forces, despite being posted in areas with difficult terrain and harsh weather.

What is the status of training facilities and infrastructure available to CAPFs?

The Estimates Committee has noted that all CAPFs have set up training institutions to meet their training requirements and impart professional skills on specialised topics.  However, the Committee noted that there is an urgent need to upgrade the curriculum and infrastructure in these training institutes.  It recommended that while purchasing the latest equipment, training needs should also be taken care of, and if required, should be included in the purchase agreement itself.  Further, it recommended that the contents of training should be a mix of conventional matters as well as latest technologies such as IT, and cyber security.

According to the Estimates Committee, the MHA has been making efforts to provide modern arms, ammunition, and vehicles to the CAPFs.  In this regard, the Modernization Plan-II, for the period 2012-17, was approved by the Cabinet Committee on Security.  The Plan aims to provide financial support to CAPFs for modernisation in areas of arms, clothing, and equipment.

However, the Committee observed that the procurement process under the Plan was cumbersome and time consuming.  It recommended that the bottlenecks in procurement should be identified and corrective action should be taken.  It further suggested that the MHA and CAPFs should hold negotiations with ordnance factories and manufacturers in the public or private sector, to ensure an uninterrupted supply of equipment and other infrastructure.