All stakeholders, including citizens, NGOs, etc. have an important role in the law making process. But for many stakeholders, the process is not obvious or easily explained. In PRS, we often receive a number of requests from NGOs about how it is that they can get Parliament to make changes in legislation and what would be productive ways in which citizens can make a difference in the law making process. To address this, PRS has developed a short Primer on "Engaging with Policy Makers: Ideas on Contributing to the Law Making Process", in which we have tried to explain the process of how a Bill becomes an Act and some of the opportunities for citizen groups to become part of the process. Sometimes, large parts of a Bill that is introduced in Parliament may not be agreeable to some groups. In such cases there is a tendency among NGOs to sometimes decide to redraft the Bill. To the extent that NGOs think of redrafting a Bill as a tactical negotiating position, they may have a point in trying to redraft legislation. To the extent that NGOs think of such redrafting as a way to keep the discourse alive on the most important issues in any legislation, such efforts are welcome and useful. But if there is a belief that the Bill introduced in Parliiament will be withdrawn to introduce another Bill on the same subject as drafted by NGOs, then history suggests that the probability of that happening is close to zero. This is not a comment on the quality of the Bill that may be drafted by the group of NGOs, but rather a result of a complex set of issues about lawmaking in India. Despite the odds, there are some recent examples in which NGOs were able to bring about significant changes to Bills in Parliament. The Right to Information Act stands out as one of the best examples in recent times. On the recently passed Right to Education Bill, NGOs were able to exert sufficient pressure to bring about changes in the Bill, and also get the government to bring in an amendment Bill to make further changes. In the Seeds Bill which was introduced in 2004, the Government appears to have agreed to bring about important changes thanks to the efforts of a number of farmer groups approaching the government directly, and through their local MPs and political parties. It would be useful if we can get more examples/ comments/ suggestions about how some NGOs were able to bring about these changes in Bills. This will help more people understand how their voices can be heard in the corridors of power.

There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,