There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Today, some Members of Parliament initiated proceedings for the removal of the current Chief Justice of India by submitting a notice to the Chairman of Rajya Sabha.  A judge may be removed from office through a motion adopted by Parliament on grounds of ‘proven misbehaviour or incapacity’.  While the Constitution does not use the word ‘impeachment’, it is colloquially used to refer to the proceedings under Article 124 (for the removal of a Supreme Court judge) and Article 218 (for the removal of a High Court judge).

The Constitution provides that a judge can be removed only by an order of the President, based on a motion passed by both Houses of Parliament.  The procedure for removal of judges is elaborated in the Judges Inquiry Act, 1968.  The Act sets out the following steps for removal from office:

  • Under the Act, an impeachment motion may originate in either House of Parliament. To initiate proceedings: (i) at least 100 members of Lok Sabha may give a signed notice to the Speaker, or (ii) at least 50 members of Rajya Sabha may give a signed notice to the Chairman.  The Speaker or Chairman may consult individuals and examine relevant material related to the notice.  Based on this, he or she may decide to either admit the motion or refuse to admit it.
  • If the motion is admitted, the Speaker or Chairman (who receives it) will constitute a three-member committee to investigate the complaint. It will comprise: (i) a Supreme Court judge; (ii) Chief Justice of a High Court; and (iii) a distinguished jurist.  The committee will frame charges based on which the investigation will be conducted.  A copy of the charges will be forwarded to the judge who can present a written defence.
  • After concluding its investigation, the Committee will submit its report to the Speaker or Chairman, who will then lay the report before the relevant House of Parliament. If the report records a finding of misbehaviour or incapacity, the motion for removal will be taken up for consideration and debated.
  • The motion for removal is required to be adopted by each House of Parliament by: (i) a majority of the total membership of that House; and (ii) a majority of at least two-thirds of the members of that House present and voting. If the motion is adopted by this majority, the motion will be sent to the other House for adoption.
  • Once the motion is adopted in both Houses, it is sent to the President, who will issue an order for the removal of the judge.