There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Recently there have been news reports about the NITI Aayog submitting its recommendations on improving the financial health of Air India to the Ministry of Finance.[1],[2]  The Civil Aviation Ministers have also mentioned that the Ministry will soon propose a roadmap for the rejuvenation of the national airline.  While the NITI Aayog report is not out in the public domain yet, we present a few details on the financial health of the airline.

Finances of Air India

In 2015-16, Air India earned a revenue of Rs 20,526 crore and registered losses of Rs 3,837 crore.  As of March 31, 2015, the total debt of Air India was at Rs 51,367 crore.[3]  This includes Rs 22,574 crore outstanding on account of aircraft loans.  The figure below shows the losses incurred by Air India in the last few years (2007-16).

image(1)

According to the Ministry of Civil Aviation, reasons for Air India’s losses include: (i) the adverse impact of exchange rate variation due to the weakening of Indian Rupee, (ii) high interest burden, (iii) increase in competition, especially from low cost carriers, and (iv) high fuel prices.[4]  The National Transport Development Policy Committee (NTDPC), in its report in 2013, had observed that with the increase in the number of airlines in the market, Air India has been struggling to make a transition from a monopoly market to a competitive one.[5]  These struggles have been primarily regarding improving its efficiency, and competing with the private airlines.

Turnaround Plan and Financial Restructuring

In order to bail out the company, the government had approved the Turnaround Plan (TAP) and Financial Restructuring Plan (FRP) of Air India in April 2012.[6]  Under the plans, the government would infuse equity into Air India subject to meeting certain milestones such as Pay Load Factor (measures capacity utilisation), on time performance, fleet utilisation, yield factor (average fare paid per mile, per passenger), and rationalisation of the emolument structure of employees.7  The equity infusion included financial support towards the repayment of the principal, as well as the interest payments on the government loans for aircraft acquisition.  Under the TAP/FRP, the central government was to infuse Rs 30,231 crore till 2020-21.  As of 2016-17, the Ministry has infused an equity amount of Rs 24,745 crore.[7]

In 2017-18, the Ministry has allocated Rs 1,800 crore towards Air India which is 67% of the Ministry’s total budget for the year.[8]  However, this amount is 30% lower than the TAP commitment of Rs 2,587 crore.3  In 2016-17, while Air India had sought and equity infusion of Rs 3,901 crore, the government approved Rs 2,465 crore as the equity infusion.[9]  The Standing Committee on Transport, Tourism, and Culture examining the 2017-18 budget estimates noted that reducing the equity infusion in Air India might adversely affect the financial situation of the company.[10]  It recommended that the government must allocate the amount committed under TAP.  The Ministry had also observed that due to reduction of equity infusion, Air India has to arrange funds through borrowing which costs additional amount of interest to be paid by the government.[11]

As per the Ministry, Air India has achieved most of the targets set out in TAP.[12]  Despite running into losses, it achieved an operating profit of Rs 105 crore in FY 2015-16.[13]  Air India’s performance in some of the segments are provided in the table below.

Table 1: Air India’s performance

  2011-12 2014-15
Overall Network On Time Performance (measures adherence to time schedule) 68.2% 72.7%
Passenger Load Factor (measures capacity utilisation of the airline) 67.9% 73.7%
Network Yield achieved (in Rs/ RPKM)* 3.74 4.35
Number of Revenue Passengers (in million) 13.4 16.9
Operating Loss (in Rs crore) 5,139 2,171

* Note: RPKM or Revenue Passenger Kilometre performed refers to number of seats for which the carrier has earned revenue.

Sources: Lok Sabha Questions; PRS.

The NTDPC had observed that with its excessive and unproductive manpower, failure to invest in the technology required to keep it competitive, and poor operations, Air India’s future looks risky.  It had also questioned the rationale for a national airline.  It had suggested that the government must frame a decisive policy with regard to Air India, and clarify its future accordingly.5  It had recommended that Air India’s liabilities should be written off and be dealt with separately, and the airline should be run on complete operational and financial autonomy.5

Need for competitive framework in the sector

With the entrance of several private players in the market, the domestic aviation market has grown significantly in the last decade.  The market share of an airline is directly related to its capacity share in the market.  While private carriers have added capacity in the domestic market, the capacity induction (adding more aircrafts) of Air India has not kept up with the private carriers.  This has resulted in decrease in market share of Air India from 17% in 2008-09 to 14% in 2016-17.[14]

The Committee looking at the competitive framework of the civil aviation sector had observed that the national carrier gets preferential treatment through access to government funding, and flying rights.[15]  It had recommended that competitive neutrality should be ensured between private carriers and the national carrier, which could be achieved by removing the regulations that provide such preferential treatment to Air India.  The NTDPC had also noted that the presence of a state-owned enterprise should not distort the market for other private players.6  It had recommended that the Ministry should consider developing regulations that improve the overall financial health of the airline sector.

While Air India’s performance has improved following the TAP, along with the equity infusion from government, its debt still remains high and has been gradually increasing.  In light of this, it remains to be seen what the government will propose with regard to the rejuvenation of the national airline, and ensure a competitive and fair market for all the players in the airline market.

[1] “Govt to prepare Air India revival plan within 3 months, amid calls for privatization”, Livemint, May 31, 2017, http://www.livemint.com/Politics/0koi5Hyidj1gVD3wOWTruM/Govt-says-all-options-open-for-Air-India-revival.html.

[2] “Air India selloff: Fixing airline’s future is more important than past”, Financial Express, May 31, 2017, http://www.financialexpress.com/opinion/why-fixing-air-indias-future-more-important-than-past/693777/.

[3] Lok Sabha Questions, Unstarred question no 382, Ministry of Civil Aviation, February 25, 2016, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=28931&lsno=16.

[4] Lok Sabha Questions, Unstarred question no 353, Ministry of Civil Aviation, November 17, 2016, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=40733&lsno=16.

[5] “Volume 3, Chapter 3: Civil Aviation”, India Transport Report: Moving India to 2032, National Transport Development Policy Committee, June 17, 2014, http://planningcommission.nic.in/sectors/NTDPC/volume3_p1/civil_v3_p1.pdf.

[6] “Government Approves Financial Restructuring and Turn Around Plan of Air India”, Press Information Bureau, Cabinet Committee on Economic Affairs (CCEA), April 12, 2012, http://pib.nic.in/newsite/PrintRelease.aspx?relid=82231.

[7] Lok Sabha Questions, Unstarred question no 472, Ministry of Civil Aviation, April 6, 2017, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=51752&lsno=16.

[8] Notes on Demands for Grants 2017-18, Demand no 9, Ministry of Civil Aviation, http://indiabudget.nic.in/ub2017-18/eb/sbe9.pdf.

[9] Lok Sabha Questions, Unstarred question no 4809, Ministry of Civil Aviation, March 30, 2017, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=51108&lsno=16.

[10] “244th report: Demand for Grants (2017-18) of Ministry of Civil Aviation”, Standing Committee on Transport, Tourism and Culture, March 17, 2017, http://164.100.47.5/newcommittee/reports/EnglishCommittees/Committee%20on%20Transport,%20Tourism%20and%20Culture/244.pdf.

[11] “218th report: Demand for Grants (2015-16) of Ministry of Civil Aviation”, Standing Committee on Transport, Tourism and Culture, April 28, 2015.

[12] Lok Sabha Questions, Unstarred question no 307, Ministry of Civil Aviation, February 25, 2016, http://164.100.47.190/loksabhaquestions/annex/7/AU307.pdf.

[13] Lok Sabha Questions, Unstarred question no 1566, Ministry of Civil Aviation, March 9, 2017, http://www.loksabha.nic.in/Members/QResult16.aspx?qref=47532.

[14] Lok Sabha Questions, Unstarred question no 312, Ministry of Civil Aviation, March 23, 2017, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=49742&lsno=16.

[15] Report of the Committee Constituted for examination of the recommendations made in the Study Report on Competitive Framework of Civil Aviation Sector in India, Ministry of Civil Aviation, June 2012, http://civilaviation.gov.in/sites/default/files/moca_001870_0.pdf.