There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Earlier today, a Bill to raise maternity benefits was introduced and passed in Rajya Sabha.  The Bill amends the Maternity Benefit Act, 1961.  The Act regulates the employment of women during the period of child birth, and provides maternity benefits.  The Act applies to factory, mines, plantations, shops and other establishments.

Duration of maternity leave: The Act states that every woman will be entitled to maternity benefit of 12 weeks.  The Bill increases this to 26 weeks.  Further, under the Act, this maternity benefit should not be availed before six weeks from the date of expected delivery.  The Bill changes this to eight weeks. In case of a woman who has two or more children, the maternity benefit will continue to be 12 weeks, which cannot be availed before six weeks from the date of the expected delivery.

Maternity leave for adoptive and commissioning mothers: Further, the Bill introduces a provision to grant 12 weeks of maternity leave to: (i) a woman who legally adopts a child below three months of age; and (ii) a commissioning mother.  A commissioning mother is defined as a biological mother who uses her egg to create an embryo implanted in another woman.  The 12-week period of maternity benefit will be calculated from the date the child is handed over to the adoptive or commissioning mother.

Informing women employees of the right to maternity leave: The Bill introduces a provision which requires every establishment to intimate a woman at the time of her appointment of the maternity benefits available to her.  Such communication must be in writing and electronically.

Option to work from home: The Bill introduces a provision that states that an employer may permit a woman to work from home.  This would apply if the nature of work assigned to the woman permits her to work from home.  This option can be availed of, after the period of maternity leave, for a duration that is mutually decided by the employer and the woman.

Crèche facilities: The Bill introduces a provision which requires every establishment with 50 or more employees to provide crèche facilities within a prescribed distance.  The woman will be allowed four visits to the crèche in a day.  This will include her interval for rest. Various countries provide maternity leave.  However, the duration of leave varies across different countries.[i]  We present a comparison of maternity leave available in different countries, as on 2014, below.

Sources: International Labour Organisation Report (2014); PRS.   [i]. “Maternity and Paternity at work: Legislation across countries”, International Labour Organisation Report (2014), http://www.ilo.org/wcmsp5/groups/public/---dgreports/---dcomm/---publ/documents/publication/wcms_242615.pdf.