There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The term of the 12th Haryana Legislative Assembly ends in October this year.  We look at the work done by the 12th Haryana Assembly during its term from 2009 to 2014 to assess its performance on metrics such as the number of sittings, members’ attendance, and legislative business. Performance of the Assembly Since the beginning of its tenure, which commenced in October 2009, the Assembly has held ten sessions. Till March 2014, the Assembly had met for a total of 54 days – an average of 11 days per year.  In comparison, the Lok Sabha sat for an average of 69 days each year from 2009 to 2014.  Among state assemblies, only Nagaland and Arunachal Pradesh sat for fewer days than Haryana. In the same period the Kerala Assembly sat for an average of 50 days per year , while Tamil Nadu Assembly sat for 44 days. sitting days haryana The average attendance among Haryana MLAs stood at 89% for the whole term, with six members registering 100% attendance.  

 Attendance haryana

  From the beginning of its term in 2009 till March 2014, the Assembly passed 129 Bills.  All Bills were discussed and passed on the same day as they were introduced. None of the Bills were referred to any Committee. Participation in the general discussion on the Budget has recovered since 2012, when the Budget was discussed for around three hours with eight Members participating.. In 2013, discussion took place for eight hours and forty minutes with 31 members participating. In 2014, the Assembly discussed the Budget for four hours and fifty minutes with 21 Members participating.

 Budget discussion

Key laws passed by the 12th Assembly include the Haryana State Commission for Women Bill, the Haryana Prohibition of Ragging in Educational Institution Bill and the Punjab Agricultural Produces Markets (Haryana Amendment) Bill.