There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Parliament is considering a proposal to change the process of appointment of judges to the Supreme Court and High Courts.  A Constitutional Amendment Bill has been introduced in Rajya Sabha that enables the formation of a Judicial Appointments Committee (JAC), and states that the composition and functions of the JAC will be detailed in a law enacted by Parliament.  The appointments will be made according to the recommendations of the JAC.  This body replaces the current process of “consultation” with the Chief Justice of India (CJI) and other senior judges. An ordinary Bill has also been introduced in Rajya Sabha which seeks to establish the JAC.  The composition of the JAC will be the CJI, the next two judges of the Supreme Court in terms of seniority, the law minister and two eminent persons.  These two eminent persons will be selected by a collegium consisting of the CJI, the prime minister and the leader of opposition in the Lok Sabha.  In case of High Court Judges, the JAC will consult with the chief minister, the governor of the state and the Chief Justice of the High Court. The new system is widening the selection committee.  It includes representatives of the executive and senior judiciary, as well as two persons who are jointly selected by the executive (PM), judiciary (CJI), and the legislature (leader of opposition). However, it may be diluting some of the safeguards in the Constitution.  At a later date, the composition of the JAC can be amended by ordinary majority in Parliament.  [For example, they can drop the judicial members.]  This is a significantly lower bar than the current system which requires a change to the Constitution, i.e., have the support of two thirds of members of each House of Parliament, and half the state assemblies. The 120th Constitution Amendment Bill and the JAC Bill are listed for consideration and passing in Rajya Sabha today.  Given that these Bills propose fundamental changes to the process of appointments to key constitutional bodies, it is important that there be a wide debate.  The Rajya Sabha must refer these Bills to the Standing Committee for careful examination of various issues. I have written a piece on this issue in the Indian Express today.