There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Elections to the 14th Legislative Assembly of Karnataka are scheduled to be held on May 5, 2013. Of the 224 assembly constituencies that will go into polls, 36 are reserved for Scheduled Castes and 15 for Scheduled Tribes. Voting will take place in 50,446 polling stations across Karnataka [1.  Election Commission India]. In this blog, we analyse electoral trends between 1989 and 2008 and the performance of the current Karnataka Assembly.

Figure 1: Electoral trends since 1989, source: Election Commission of India, PRS.

 

In the last elections, held in 2008, the Bharatiya Janata Party (BJP) formed the government, winning 110 of the 226 seats in the Assembly. The BJP has steadily increased its seat share since 1989: it won four seats in 1989, 44 in 1999 and 79 in 2004. The Indian National Congress (INC) had a 179 seat majority in 1989 (79% of the assembly) which fell to 34 seats in 1994. The INC subsequently increased their tally from 65 seats in 2004 to 80 seats in 2008. However, the INC continued to have the highest share of votes polled (except in 1994) even as its share of seats decreased. The 1990s also saw the emergence of the Janata Dal (S) who won the 1994 elections with 115 seats. Janata Dal’s emergence is part of a broader theme of increased participation by regional parties in Karnataka. In 1989, 20 parties contested the elections, seven of which were national parties but in 2008, 30 parties contested, of which only five were national parties. Performance of the current Assembly As we approach the end of the term of the current Assembly, a brief look at its work from 2008 to 2013:

  • During its five-year-term, the Assembly sat for a total of 144 days, an average of 31 days each year. In comparison, the Lok Sabha in its current term sat for an average of 68 days per year. Among states, the Kerala Assembly sat for an average of 50 days, Haryana for 13 days and Rajasthan for 24 days, each year. Figure 2: Days of sitting - Karnataka assembly, source: RTI, PRS.

     

  •  Members of the Karnataka Assembly recorded an average attendance of 81 per cent for the whole term, broadly in line with the Lok Sabha attendance of 77 per cent. Nearly one in five members registered more than 90 per cent attendance. In comparison, members of the 11th Himachal Pradesh Assembly recorded an attendance of 95 per cent, while the attendance of the 12th Gujarat Assembly stood at 83 per cent.
  • Some of the significant Bills passed by the 14th Karnataka Assembly include the Karnataka Guarantee of Services to Citizens Bill and the Karnataka Ground Water (Regulation and Control of Development and Management) Bill.  In 2012, the Assembly also passed the Karnataka Prevention of Cow Slaughter and Preservation Bill.