There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The Protection of Women against Sexual Harassment Bill was passed by Rajya Sabha yesterday.  Prior to this, no legislation specifically addressed the issue of sexual harassment at the workplace.  In 1997, the Supreme Court issued directions in Vishakha vs. State of Rajasthan to deal with the issue.  The Supreme Court had also recommended that steps be taken to enact a law on the subject.  The Bill was introduced in Parliament in 2010 and was passed by the Lok Sabha on September 3, 2012.  In order to protect women from harassment, the Bill establishes a mechanism for redressal of complaints related to harassment. Recently, the Verma Committee in its Report on Amendments to Criminal Laws had made recommendations on the Sexual Harassment Bill.  In this blog we discuss some of the key issues raised by the Verma Committee with regard to the issue of sexual harassment at the workplace. Internal Committee:  The Bill requires the establishment of a committee within organisations to inquire into complaints of sexual harassment.  The Committee shall comprise four members: three would be employees of the organisation; and the fourth, a member of an NGO committed to the cause of women.  The Verma Committee was of the opinion that in-house dealing of the complaints would dissuade women from filing complaints.  It recommended that a separate Employment Tribunal outside the organisation be established to receive and address complaints of sexual harassment. Requirement for conciliation:  Once a complaint is made, the Bill requires the complainant to attempt conciliation and settle the matter.  Only in the event a settlement cannot be reached, the internal committee of the organisation would inquire into the matter.  The Verma Committee was of the opinion that this is in violation of the Supreme Court’s judgment.  It noted that in sexual harassment cases, an attempt to conciliate compromises the dignity of the woman. Action during pendency of the case:  As per the Bill, a woman may approach the internal committee to seek a transfer for herself or the respondent or a leave to the complainant.  The Verma Committee had recommended that till the disposal of the case, the complainant and the respondent should not be compelled to work together. False complaints: The Bill allows the employer to penalise false or malicious complaints as per their service rules.  The Committee was of the opinion that this provision was open to abuse. A PRS analysis of the Bill may be accessed here.