There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The President issued the Criminal Law (Amendment) Ordinance on February 3, 2013. This ordinance amends the Indian Penal Code, Criminal Procedure Code and the Indian Evidence Act. Here we explain what an ordinance is, how it is made and with what frequency it is used. This article was first published on Rediff and can be accessed here. What is an ordinance and who makes it? Under the Constitution, the power to make laws rests with the legislature. However, in cases when Parliament is not in session, and ‘immediate action’ is needed, the President can issue an ordinance. An ordinance is a law, and could introduce legislative changes. The Supreme Court has clarified that the legislative power to issue ordinances is ‘in the nature of an emergency power’ given to the executive only ‘to meet an emergent situation’. An example of immediacy can be seen in the ordinance passed in 2011 to give IIIT - Kancheepuram the status of an institute of national importance so that students could be awarded their degrees on completion of their course. What will happen to the ordinance when Parliament meets for the Budget session? After the ordinance is notified it is to be laid before Parliament within 6 weeks of its first sitting. The first sitting of Parliament in the Budget session this year will be February 21, 2013. Parliament could either choose to pass the ordinance, disapprove it or it may lapse within the 6 week time frame.  In addition, the President may chose to withdraw the ordinance. Once the ordinance is laid in Parliament, the government introduces a Bill addressing the same issue. This Bill is supposed to highlight the reasons that necessitated the issue of the Ordinance. Thereafter, the Bill follows the regular law making process. An amendment to Criminal Laws addressing similar issues is currently pending in Parliament. How will this play out vis-à-vis the ordinance? The ordinance gives effect to some of the provisions of the Criminal Laws (Amendment) Bill, 2012, with some modifications. In the upcoming Budget session the government may introduce a new Bill replacing both the Ordinance and the Amendment Bill currently pending in Parliament. The parliamentary Standing Committee is currently examining the Amendment Bill and is expected to submit its report by the end of March. How often does the President use this power to make ordinances? Data over the last 60 years indicates that 1993 saw the highest number of ordinances being passed, i.e. 34. In comparison, a fewer number of ordinances are now being issued. For example, in the last 10 years the average number of ordinances issued per year is 6.