There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Elections to the 13th Legislative Assembly of Gujarat are scheduled to be held in two phases on the 13th and 17th of December.  The BJP has been the dominant majority party in the Assembly since 1995.  The 2002 elections saw the largest victory for the party, winning 127 seats. The Congress last held power in Gujarat in 1985.  In the Assembly elections held for the the seventh Assembly, the Congress had a clear majority of 149 seats.  In 1990, the Janata Dal emerged as the largest party with 70 seats.  The BJP registered major gains in 1990, improving their tally of 11 seats in 1985 to 67 seats.  The Congress came third with 33 seats. The electoral trends over the last 22 years may be viewed here. In the current Assembly, 117 of the 182 seats are held by the BJP.  It is useful to look at the work done by the 12th Gujarat Assembly during its term from 2008 to 2012.  Here we look at key metrics like the number of days the assembly was in session, members’ attendance, and legislative business. Performance of the Assembly During its five year term, the assembly sat for a total of 157 days – an average of 31 days each year.  In comparison, the Lok Sabha sat for an average of 66 days each year during the period 2008 to 2011.  In the same period the Kerala Assembly sat for an average of 50 days – highest among states - followed by Maharashtra (44).  However, the Gujarat Assembly sat for more number of days than the Haryana Assembly which sat for an average of 13 days and Rajasthan (24). The average attendance among Gujarat MLAs stood at 83% for the whole term, with two members registering 100% attendance. 87 Bills were passed by the Assembly since the beginning of its term in 2008 till September 2011.  Of these, 80 Bills i.e. over 90% of all Bills were passed on the same day as they were introduced.  None of the Bills were referred to any Committee.  In the Budget Session of 2011, 31 Bills were passed of which 21 were introduced and passed within three sitting days Amendments sought by the President and the Governor One of the significant laws passed by the 12th Assembly was the Gujarat Control of Terrorism and Organised Crime Bill, 2003 which was introduced and passed in July 2009.  However the Bill did not receive the Presidents Assent and was sent back to the Gujarat Assembly for amendments. In December 2009, the assembly passed the Gujarat Local Authorities Laws (Amendment) Bill 2009 which sought to make voting compulsory in elections to local self-government bodies like municipal corporations and Panchayats.  The Gujarat governor returned the Bill for reconsideration in 2010.  It was re-introduced in the house in September 2010 without changes. Another Bill that was returned by the Governor was the Gujarat Regularisation of Unauthorised Development Bill which sought to regularise unauthorised construction on payment of an Impact Fee.  The Bill was passed by the Assembly in March 2011.  The Governor returned the Bill with a suggestion to include a provision to bar the regularisation of unauthorised construction beyond a specified date.  The Bill was re-introduced and passed with amendments by the Assembly in September 2011.