There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

A recent news report has discussed the methods by which states such as Chattisgarh have attempted to reform the Public Distribution System (PDS).  Chattisgarh has computerised its PDS supply chain and introduced smart cards as part of a slew of measures to plug pilferage and weed out corruption in the system.  In an effort to create a national computerised database for PDS, the Ministry of Consumer Affairs has launched an online National Transparency Portal for the Public Distribution System.  The portal aims to provide end-to-end computerisation of PDS; it is a single platform in the public domain for all PDS related information. The PDS is a centrally sponsored scheme that entitles beneficiaries to subsidised foodgrains every month.  Currently, beneficiaries are divided into the following groups: Below Poverty Line (BPL), Above Poverty Line and Antodaya Anna Yojana.  As such, several challenges have been identified in the implementation of PDS.  Some of them are as follows:

  1. Targeting errors: Separating beneficiaries of the PDS into three categories requires their classification and identification.  Targeting mechanisms, however, have been prone to large inclusion and exclusion errors.  In 2009, an expert group estimated that about 61% of the eligible population was excluded from the BPL list while 25% of non-poor households were included in the BPL list.
  2. Large leakages and diversion of subsidized foodgrain:  Foodgrain is procured by the centre and transported from the central to state godowns.  Last mile delivery from state godowns to the Fair Price Shop (FPS) where beneficiaries can purchase grain with ration cards, is the responsibility of the state government.  Large quantities of foodgrain are leaked and diverted into the open market during this supply chain.

The creation of the e-portal could help track these issues more effectively and increase transparency in the system. The portal contains information relating to FPS and ration cards attached to the FPS.  It is likely that this will help weed out bogus ration cards and improve targeting of subsidies.  The portal also has information on capacity utilization of Food Corporation of India, state storage godowns, and data on central pool stocks.  This helps track storage supplies of grains at each level and aims to prevent leakage of grain. With respect to data on PDS in states, the portal hosts information such as the central orders on monthly allocation of foodgrain to states, state-specific commodity sale prices, lifting position of states, etc. for public view.  All states and union territories will be required to maintain and update the data on the portal. The reforms come at a time when the National Food Security Bill, 2011 is pending in Parliament.  The Bill aims to deliver foodgrain entitlements through Targeted PDS to 75% of the rural and 50% of the urban population.  The Bill is currently under examination by the Standing Committee of Food, Consumer Affairs and Public Distribution.  It proposes reforms to the TPDS, which include the application of information and communication technology, including end-to-end computerisation.  These reforms seek to ensure full transparency of records in the PDS and prevent diversion of foodgrains.  The creation of the e-portal might be a step towards reforming the PDS. For an analysis of the National Food Security Bill, see here.