There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

A change in the Contract Labour (Regulation and Abolition) Act, 1970 may be in the pipeline.  According to news reports, the government may amend the 1970 Act to safeguard the interest of contract workers.  The proposal is to bring parity between permanent and contractual workers in wages and other benefits. The Contract Labour Act, 1970 regulates the employment of contract labour in establishments which employ 20 or more workmen.  It excludes any establishment whose work is intermittent or casual in nature.  The appropriate government may require establishments to provide canteens, rest rooms and first aid facilities to contract labourers.  The contractor shall be responsible for payment of wages to each worker employed by him.  There are penalties listed for contravening the Act. According to the Report of the National Commission on Enterprises in the Unorganised Sector (NCEUS), more than 90% of the workforce is part of the unorganised sector.  Contract labour is found in certain activities in the unorganized sector such as in stone quarrying, beedi rolling, rice shelling and brick kiln.  The Commission recommended some measures to protect the workers in the unorganized sector such as ensuring minimum conditions of work, minimum level of social security and improved credit flow to the non-agricultural sector. The Report of the Working Group on “Labour Laws and other Regulations” for the 12th Five Year Plan, also proposed that the 1970 Act should be amended.  The amendment should ensure that in case of contract labour performing work similar to that performed by permanent workers, they should be entitled to the same wage rates, holidays, hours of work and social security provisions.  Furthermore, whenever a contract worker is engaged through a contractor, the contract agreement between the employer and the contractor should clearly indicate the wages and other benefits to be paid by the contractor. However, other experts such as Bibek Debroy, Kaushik Basu and Rajeev Dehejia have recommended broad reforms in India’s labour laws to allow for more flexibility in the labour market.  According to them, these laws protect only a small portion of workers in the organized sector.