There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

In India, children between the age group of 6 and 14 years have the fundamental right to free and compulsory education.  This right is implemented through the Right of Children to Free and Compulsory Education Act, 2009 (RTE Act).  The Act is applicable to all categories of schools (government and private). According to recent media reports (see here and here), many schools (including government schools) are flouting norms laid down in the RTE Act.  Unaided schools have criticised state government over norms related to religious and linguistic status of minority schools (see here and here).  The government has also faced flak over unclear norms on neighbourhood schools and reimbursement of money to private schools (see here, here and here). Most Acts ‘delegate’ the power to make rules and regulations for operationalising the law to the executive (Ministry).   We provide an overview of the Rules notified by the state governments. The central government notified the RTE Rules 2010 on April 9, 2010, which are applicable to all schools under the central government, and in the five Union Territories without legislatures.  Most of the states have notified similar Rules with a few variations. The Rules define the limits of a neighbourhood and make it mandatory for the local authority to maintain list of children within its jurisdiction.  They also prescribe the composition of the School Management Committee to be formed in government schools.  Private schools shall reserve 25% of the seats for disadvantaged children.  These schools shall be reimbursed for either their tuition charge or the per-student expenditure in government schools, whichever is lower.  All private schools have to be recognised before they can start operation.  Recognition is contingent upon meeting the minimum standard laid down in the Act    Existing private schools have to meet the norms within three years of commencement of the Act.  If they are not compliant after three years, they shall cease to function.  Government schools under the central government have to meet only two conditions: the minimum qualification for teachers and the student-teacher ratio. For all state government schools and un-adided schools, the power to make rules is delegated to the state government.  The central government circulated Model Rules for the RTE Act to the states.  All state governments, except Goa, have notified the state RTE Rules.  Delhi and Puducherry have also notified them.  Most of the states have notified similar Rules with a few variations.  We list some of the variations. Andhra Pradesh: The break-up of the 25% quota among the various disadvantaged groups have been included in the Rules.  Scheduled Castes: 10%; Scheduled Tribes: 4%; Orphans, disabled and HIV affected: 5% and children with parents whose annual income is lower than Rs 60,000: 6%. Rajasthan: Private schools either have to be affiliated with a university or recognised by any officer authorised by the state government.     Karnataka: In addition to the minimum norms under RTE Act, private schools have to comply with the Karnataka Education Act, 1983. Gujarat: If an existing recognised school is unable to meet the infrastructure norms it may be given the option of demonstrating that it achieved certain learning outcomes, both in terms of absolute levels and as improvement from previous years. Uttar Pradesh: The government shall pay per child reimbursement to the school after it gives a list of children with their Unique Identity Number and other details. Kerala:  The local authority has to maintain a record of all the children (0-14 years) within its jurisdiction.  It shall also maintain the Unique Identity Number of every child, as and when issued by the competent authority, to monitor his enrolment, attendance and learning achievements. Haryana:  Defines textbooks, uniform and writing material.  It states that Hindi is to be the preferred medium of instruction in all schools. For using other language, permission of Director, Elementary Education Dept is required (to be given within 45 days or deemed to be granted). West Bengal: The Rules give detailed definition of the appropriate age for each class.  They require schools to be set up in a relatively noise-free and pollution-free area with adequate supply of drinking water and electricity.  Existing schools (which are already recognised or affiliated with a Board) may get the local municipal authorities to provide infrastructural support including relaxation of building rules to comply with the requirements of the Act. Additional sources

  1. PRS Brief on Right of Children to Free and Compulsory Education Bill, 2008.
  2. PRS Bill Summary on Right of Children to Free and Compulsory Education (Amendment) Bill, 2010.
  3. Accountability Initiative’s Policy Brief on 25% Reservation under the RTE.