There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Parliament voted on the Demands for Grants for the Ministry of Home Affairs on May 02, 2012. During the debate, MPs expressed concern over the status of police forces in different States of the country.  They emphasised  the need to augment the capability of police forces. Though ‘Police’ and ‘Public Order’ are State subjects, the union government provides assistance to States for strengthening their forces.  For instance, the Ministry of Home Affairs has been implementing a non-plan scheme for ‘Modernization of Police Forces’ since 1969-70.  Under the scheme assistance is provided in the form of grants-in-aid towards construction of secure police stations, outposts, for purchase of vehicles, equipment etc.  (To know more about the scheme, see an earlier blog post on the issue.) At the all India level, the sanctioned strength of State Police equals 20.6 lakh personnel.  Though there exist wide variations across States, at an average this amounts to 174 police personnel per lakh population.  However, the actual ratio is much lower because of high vacancies in the police forces.  At the aggregate level, 24% positions are vacant. The table below provides data on the strength of state police forces as in Jan, 2011

State Sanctioned strength Sanctioned policemen/ lakh of population Vacancy
Andhra Pradesh 1,31,099 155 31%
Arunachal Pradesh 11,955 966 42%
Assam 62,149 200 12%
Bihar 85,939 88 27%
Chhattisgarh 50,869 207 18%
Goa 6,108 348 16%
Gujarat 87,877 151 27%
Haryana 61,307 248 28%
Himachal Pradesh 17,187 256 22%
Jammu & Kashmir 77,464 575 6%
Jharkhand 73,005 235 30%
Karnataka 91,256 155 10%
Kerala 49,394 141 7%
Madhya Pradesh 83,524 115 9%
Maharashtra 1,53,148 139 10%
Manipur 31,081 1,147 26%
Meghalaya 12,268 469 17%
Mizoram 11,246 1,112 6%
Nagaland 24,226 1,073 0%
Orissa 53,291 130 18%
Punjab 79,565 291 14%
Rajasthan 79,554 118 11%
Sikkim 5,421 886 27%
Tamil Nadu 1,20,441 178 15%
Tripura 44,310 1,224 17%
Uttar Pradesh 3,68,260 184 59%
Uttarakhand 20,775 211 24%
West Bengal 72,998 81 18%
A&N Islands 4,417 1,018 22%
Chandigarh 7,873 695 22%
D&N Haveli 325 114 13%
Daman & Diu 281 140 6%
Delhi 81,467 441 1%
Lakshadweep 349 478 36%
Puducherry 3,941 352 25%
All India 20,64,370 174 24%

Source: Lok Sabha Unstarred Question No. 90, 13th March, 2012  and Lok Sabha Unstarred Question No. 1042, March 20, 2012