There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

TRAI released its recommendations on auction of spectrum on April 23, 2012.   The recommendations are in pursuance of the Supreme Court order cancelling 122 telecom licences.  The cancellation was ordered on grounds of procedural irregularities and arbitrariness in the first-cum-first-serve policy for allocation of spectrum.   The recommendations, if adopted by the Department of Telecommunications, would change various aspects of the present telecom policy, including (a) relationship between a telecom licence and spectrum; (b) procedure for allocation of spectrum; (c) pricing of spectrum; (d)  limits on spectrum allocation; and (e) use of spectrum. Relationship between telecom licences and spectrum Previously, under the Telecom Policy 1994 (updated in 1999), spectrum was tied in with telecom licences.  Since 2003, licence conditions provided for award of two blocks of 6.2 MHz of spectrum for GSM technology and two blocks of 5 MHz for CDMA technology.  As per the government’s decision of January 17, 2008 (as explained in TRAI's consultation paper, see page 3 paragraph 7) additional spectrum would be awarded on the basis of increment in the number of subscribers.  Service providers had to pay a licence fee (on obtaining the licence), an annual licence fee and a spectrum usage charge determined on the basis of their adjusted gross revenue. TRAI has recommended that telecom licences and spectrum should be de-linked.  The service provider would thus pay separately for the value of the licence and the spectrum.  With this formulation an entity that does not hold a licence, but is eligible to secure one, may also procure spectrum.  This would help in avoiding situations where licence holders have to wait to secure spectrum or offer wire line services in the absence of spectrum. Procedure for allocation of spectrum TRAI has recommended that spectrum be auctioned by means of a simultaneous multiple round ascending auction (SMRA).  This means that the service providers would bid for spectrum in different blocks simultaneously.  In the first round of auction a reserve price (base price) set by the government is used. Reserve price for auction and payment mechanism A reserve price indicates the minimum amount the bidder must pay to win the object.  In case it is too low, it may reduce the gains made by the seller and lead to a sub-optimal sale.  If it is too high, it may reduce the number of bidders and the probability of the good not being sold. Various countries have adopted a reserve price of 0.5 times the final price.  TRAI has recommended that the reserve price should be 0.8 times the expected winning bid.  It has also recommended that telecom companies pay 67% to 75% of the final price in installments over 10 years, depending on the spectrum band. TRAI has reasoned that a higher price would reduce the possibility of further sales upon bidders securing spectrum.  However, this may lead to fewer bidders and ultimately fewer service providers.  It is argued in news reports that this may increase investments to be made by the service providers and eventually an increase in tariffs. Spectrum blocks and caps TRAI has recommended that the spectrum cap should be determined on the basis of market share.  A service provider can now secure a maximum of 50% of spectrum assigned in each band in each service area.  However, a service provider cannot hold more than 25% of the total spectrum assigned in all the bands across the country. As per the January 2008 decision, additional spectrum could be awarded to telecom companies when they reached incremental slabs of subscribers.  This could extend to two blocks of 1 MHz for GSM technology, and two blocks of 1.25 MHz for CDMA, for each slab of subscribers. TRAI has recommended that spectrum should be auctioned in blocks of 1.25 MHz.  Each auction would at least offer 5 MHz of spectrum at a time.  Smaller blocks would ensure that service providers who are nearing the spectrum cap may secure spectrum without exceeding the cap.  However, experts have argued that 1.25 MHz block may be too limited for launching services.  Also, TRAI in the recommendation has noted that a minimum of 5 MHz of contiguous spectrum is required to launch efficient services with new technologies. Use of spectrum TRAI has recommended that the use of spectrum should be liberalised.  This implies that spectrum should be technology neutral.  Telecom companies would now be free to launch services with any technology of their choice.