There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Report on Khap Panchayats The Law Commission has drafted a consultation paper on caste panchayats.    A draft legislation titled “The Prohibition of Unlawful Assembly (Interference with the Freedom of Matrimonial Alliances) Bill, 2011” has been attached to the consultation paper. The Bill prohibits people from congregating together to condemn a legal marriage on the ground that the said marriage has brought dishonour to the caste or community.     Every member of such a group shall be punished with imprisonment of a minimum term of 6 months and a maximum term of 1 year.   The member may also be liable to a fine of up to Rs 10,000. Under our criminal justice system, the presumption is that the accused person is innocent until proven guilty.   This Bill reverses this presumption.   It provides that if an accused person participated in an unlawful assembly, then it will be presumed that the accused intended to commit an offence under the Bill. The Commission has invited public comments on the consultation paper within 4 weeks.   The comments can be sent by post or email to lci-dla@nic.in.    A copy of the consultation paper is available at http://lawcommissionofindia.nic.in/reports/cp-Honour%20Killing.pdf. Report on compounding of offences including Sec 498A of IPC (harassment for dowry) The Law Commission has also submitted its report on ‘Compounding of (IPC) Offences.    Compoundable offences are offences which allow the parties to enter into a private compromise.   The Supreme Court in some recent cases had asked the Law Commission to identify more offences which could be treated as compoundable.   Section 320 of the Code of Criminal Procedure lists the offences which are compoundable.  Currently under the section there are 56 compoundable offences.   Certain offences can be compounded only with the prior permission of the court. The Commission has recommended that Section 498A of the IPC (cruelty against a married woman by her husband or relatives) should be made compoundable with the permission of the Court.   It has recommended that the magistrate should give a hearing to the woman and then permit or refuse the compounding of the offence.  This has been recommended to ensure that woman is not coerced into compounding the offence. The other IPC offences that the Commission has recommended should be made compoundable include (a) Section 324 (simple hurt); (b) Section 147 (rioting); (c) Section 380 (theft in dwelling house); (d) Section 384 (extortion) and  (e) Section 385 (extortion by threat  to person). A copy of the report is available at http://lawcommissionofindia.nic.in/reports/report237.pdf