There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The Gujarat High Court is hearing an important case related to the appointment of the Lokayukta in Gujarat.  The issue is whether the Governor can appoint the Lokayukta at his discretion or whether appointment can be made only upon obtaining the aid and advice of the Council of Ministers led by the Chief Minister. During the period 2006-2010, the Gujarat state government submitted names of two prospective appointees for the post of Lokayukta to the Governor.  But no appointment was made during this period.  On August 26, 2011 the Governor appointed retired judge R.A.Mehta as Lokayukta, whose name was not among those submitted by the state government.  The Gujarat state government moved the High Court to quash the appointment on the ground that the Governor made the appointment without the aid and advice of the Council of Ministers led by the Chief Minister. Section 3 of the Gujarat Lokayukta Act, provides in part that “the Governor shall by warrant under his hand and seal, appoint a person to be known as Lokayukta”.  The Governor acted under this section to make the appointment of Lokayukta.  However, the state government has argued that section 3 has to be understood in light of Article 163(1) of the Constitution.  Article 163(1) provides that the Governor shall be aided and advised in the exercise of his functions by a Council of Ministers with the Chief Minister at the head. Thus, as per this line of argument, the Governor violated the provision of Article 163(1) when she failed to take the aid and advice of the Council of Ministers led by the Chief Minister before exercising the function of appointing the Lokayukta. At the time of writing this post, news reports suggested that the two judges hearing the case are divided over the issue.  It remains to be seen whether this issue will be referred to a larger bench.  The outcome of this case could have wider implications on the constitutional role of governors if it sets guideposts on the extent to which they act independent of the advice of the council of ministers.