There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

We wrote an FAQ on the Lok Pal Bill for Rediff.  http://www.rediff.com/news/special/special-parliamentary-committee-cannot-study-lokpal-bill-in-10-days/20110822.htm The Lok Pal Bill has been referred to the Standing Committee of Parliament on Personnel, Public Grievances, Law and Justice.  In this FAQ, we explain the process of these Committees. What is the role of such standing committees? The system of departmentally related standing committees was instituted by Parliament in 1993.  Currently, there are 24 such committees, organised on the lines of departments and ministries.  For example, there are committees on finance, on home affairs, on defence etc.  These standing committees examine Bills that are referred to them.  They also examine the expenditure plans of ministries in the Union Budget.  In addition, they may examine the working of the departments and various schemes of the government. How is the membership of these committees decided? Each committee has 31 members: 21 from Lok Sabha and 10 from Rajya Sabha.  Parties are allocated seats based on their strength in Parliament.  The final membership is decided based on the MP’s area of interest as well as their party’s decision on allocating the seats. Who chairs the committees? Of the 24 committees, 16 are administered by Lok Sabha and eight by Rajya Sabha.  The Chairperson is from the respective House.  Political parties are allocated the chairs based on their strength in Parliament.  Some committees such as home affairs, finance and external affairs are customarily chaired by a senior member of an opposition party. What will the Standing Committee do with the Lok Pal Bill? The Committee has invited comments and suggestions from the public on the Bill.  Comments can be sent to Mr. KP Singh, Director, Rajya Sabha Secretariat, 201, Second Floor, Parliament House Annexe, New Delhi -110001.  These may also be emailed to kpsingh@sansad.nic.in or rs-cpers@sansad.nic.in.  The Committee will examine the written memoranda.  They will also invite some experts and stakeholders for oral evidence.  Based on its examination, the committee will prepare a report with its recommendations on the various provisions of the Bill.  This report will be tabled in Parliament. Is the report decided by voting? No.  The committee tries to form a consensus while preparing the report.  However, if some members do not agree on any point, they may add a dissent note.  For example, the committee on the Civil Liability for Nuclear Damages Bill had dissent notes written by MPs from the left parties.  The Women’s Reservation Bill also had dissent notes from a couple of members. Are the committee’s recommendations binding? No.  The Committee system was formed recognising that Parliament does not have the time for detailed examination and public feedback on all bills.  Parliament, therefore, delegates this task to the committee which reports back with its recommendations.  It is the role of all MPs in each House of Parliament to examine the recommendations and move suitable amendments.  Following this, Parliament can vote on these amendments, and finalise the Bill. Can you give examples when the Committee’s work has resulted in significant changes? There are many such instances.  For example, the standing committee on science and technology examined the Civil Liability for Nuclear Damages Bill.  The committee made several recommendations, some of which increased the potential liability of suppliers of nuclear equipment in case of an accident.  All the recommendations were accepted.  Similarly, the Seeds Bill, which is currently pending in Rajya Sabha has seen several major recommendations by the Committee on Agriculture.  The government has agreed to move amendments that accept many of these recommendations. Are all Bills referred to Standing Committees? Most Bills are referred to such committees but this is not a mandatory requirement before passing a Bill.  In some cases, if a Bill is not referred to a committee and passed by one House, the other House may constitute a select committee for detailed examination.  Some recent examples include such select committees formed by the Rajya Sabha on the Prevention of Torture Bill, the Wakf Amendment Bill, and the Commercial Divisions of High Courts Bill.  There are also some instances when a Bill may be passed without the committee process. Is it a good idea to bypass the committee process? In general, this process provides a platform for various stakeholders to provide their inputs.  In the Lok Pal case, a few influential groups such as the India Against Corruption (IAC) and the National Campaign for People’s Right to Information (NCPRI) have voiced their views.  However, there may be other points of views of persons who do not have similar access to the media.  The Standing Committee provides equal opportunity to everyone to write in their memoranda.  It also allows parliamentarians to devote a significant amount of time to understand the nuances of a Bill and make suitable modifications.  Thus, the standing committee system is an opportunity to strengthen legislation in an informed and participatory manner. Is it feasible to compress this process within 10 days and get the Lok Pal Bill passed within the current session of Parliament? There should be sufficient time for citizens to provide inputs to the committee.  The committee has to examine the different points of view and find suitable provisions to achieve the final objectives.  For example, there are divergent views on the role of Lok Pal, its constitution, its jurisdiction etc.  The Committee has to understand the implications of the various proposals and then make its recommendations.  It has been given three months to do so.  Typically, most committees ask for an extension and take six to eight months.  It is not practical to expect this process to be over within 10 days. Should civil society demand that the government issue a whip and pass the Jan Lok Pal Bill? Everyone has the right to make any demand.  However, the government is duty bound to follow the Constitution.  Our Constitution has envisaged a Parliamentary system.  Each MP is expected to make up their minds on each proposal based on their perception of national interest and people’s will.  Indeed, one may say that the best way to ensure a representative system is to remove the anti-defection law, minimise the use of whips, and let MPs vote their conscience.  That may give us a more accountable government.