There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

In the aftermath of the nuclear leaks in Japan, there have been concerns regarding the safety of nuclear power plants around the world. There are some proposals to change the regulatory framework in India to ensure the safety of these plants. We examine some of the issues in the current structure.   Which body looks at safety issues regarding nuclear power plants in the country?   The apex institution tasked to look at issues regarding nuclear safety is the Atomic Energy Regulatory Board. The AERB was set up in 1983 to carry out regulatory and safety functions regarding nuclear and radiation facilities. The agency has to give clearances for establishing nuclear power plants and facilities.   It issues clearances for nuclear power projects in stages after safety reviews. The safety of setting up a nuclear plant in any given area is also assessed by the AERB. For example, it would have looked into the safety of setting up a nuclear power project in Jaitapur in Maharashtra.   AERB also reviews the safety mechanisms within existing nuclear plants and facilities. To do this, it requires nuclear facilities to report their compliance with safety regulations, and also makes periodic inspections.   Under the recently passed Civil Liability for Nuclear Damage Act, 2010 the AERB is also the authority responsible for notifying when a nuclear incident takes place. Mechanisms for assessing and claiming compensation by victims will be initiated only after the nuclear incident is notified.   Why is the Atomic Energy Regulatory Board in the news?   Prime Minister Manmohan Singh announced on March 29, 2011, "We will strengthen the Atomic Energy Regulatory Board and make it a truly autonomous and independent regulatory authority."   This announcement came in the backdrop of the continuing crisis and high radiation levels at the Fukusima nuclear plant in Japan.   News reports opined that the lack of proper autonomy of Japan's nuclear regulator curbed its effectiveness. Japan's ministry of economy, trade and industry regulates the nuclear power industry, and also promotes nuclear technology. These two aims work at cross-purposes. India's regulatory structure is similar to Japan in some respects.   What measures has the AERB taken post the Fukushima nuclear incident in Japan?   Following the nuclear incident in Japan, a high-level committee under the chairmanship of a former AERB chairman has been set up to review the safety of Indian nuclear power plants.   The committee shall assess the capability of Indian nuclear power plants to withstand earthquakes, tsunamis, cyclones, floods, etc. The committee will review the adequacy of provisions for ensuring safety in case of such events.   Is there any issue in the current regulatory structure?   The AERB is a regulatory body, which derives administrative and financial support from the Department of Atomic Energy. It reports to the secreatry, DAE.   The DAE is also involved in the promotion of nuclear energy, and is also responsible for the functioning of the Nuclear Power Corporation of India Limited, which operates most nuclear power plants in the country.     The DAE is thus responsible both for nuclear safety (through the AERB), as well as the operation of nuclear power plants (through NPCIL). This could be seen as a conflict of interest.   How does the system of independent regulators differ from this?   The telecom sector provides an example of an independent regulator.   The Telecom Regulatory Authority of India does not report to the Department of Telecommunications. The DoT is responsible for policy matters related to telecommunications, promoting private investment in telecom, and also has a stake in BSNL. Had TRAI reported to the DoT, there would have been a conflict of interest within the DoT.   What will the proposed legislation change?   Recent news reports have stated that a bill to create an independent regulatory body will be introduced in Parliament soon.   Though there is no draft bill available publicly, news reports state that an independent Nuclear Regulatory Authority of India will be created by the bill, and the authority will subsume the AERB within it.   This post first appeared as an article on rediff.com and can be accessed here.