There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

 The last few months saw a number of allegations of corruption in issues such as contracts for the Commonwealth Games, allocation of  2G Spectrum, and the building of the Adarsh housing society.  Professor Kaushik Basu, the Chief Economic Adviser to the Ministry of Finance, has proposed a modification in order to make the anti-corruption law in the country more effective.  The Prevention of Corruption Act, 1988 penalizes both bribe giving and taking.  Bribe giving is punishable under the Act with imprisonment ranging between six months to five years.  He argues that bribe giving should be legalized. Professor Basu distinguishes “harassment bribes”, which he defines as “bribes that people often have to give to get what they are legally entitled to” from the remaining, “Non-Harassment Bribes” which would involve illegal benefits accruing to the bribe giver at a potential cost to the public interest.  He argues that legalization of harassment bribes would reduce the nexus between the giver (victim) and the taker of a bribe. Giving complete immunity to the bribe-giver would ensure higher reporting and co-operation of the giver in bringing to justice the bribe taker. The present law acts as a deterrent to reporting of bribery. Courts have also highlighted this issue. The High Court of Delhi in the Bharadwaaj Media Case (2007) observed that a “bribe giver is normally on the mercy of the officials and babus who compel him to pay bribe even for lawful work.The Court further observed that “Instead of expressing gratefulness to the persons who expose corruption, if the institutions start taking action against those who expose corruption, corruption is bound to progress day and night.”  It can be inferred from the judgement that steps ought to be taken to provide protection to those exposing bribery. The proposed legalization of bribe-giving may result in increased reporting of bribery and co-operation of the victim during prosecution. The fear that a bribe giver may report the public official could reduce corruption, at least in terms of harassment bribes. However, this proposal may reduce the stigma attached to bribe-giving and result in corrosion of morality. Much of the recent debate around corruption and the Lok Pal Bill revolve around effective prosecution. This paper looks at the incentive structure for reporting bribe-giving, and merits public debate.