There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The Lok Pal (anti-corruption body) Bill has generated widespread interest in the past few days.

The Bill is an attempt by the government, under massive pressure due to corruption charges, to gain some of its lost ground. However, civil rights activists, including Anna Hazare, Swami Agnivesh, Kiran Bedi and Arvind Kejriwal, have termed the draft legislation as weak and demanded that fifty per cent of the members in the committee drafting the bill should be from the public.

But the common man appears to be in the dark about the scope of the proposed bill.

Here's an FAQ on the controversial bill.

What is the controversy between the government and Anna Hazare about?

Anna Hazare and other civil society activists have proposed a draft Lok Pal Bill to tackle the menace of corruption. The Prime Minister formed a sub-committee of the Group of Ministers to discuss the issue with these activists. However, these two groups were unable to reach an agreement on the provisions of the Lok Pal Bill. According to the government, the activists demanded that the government should accept the Bill drafted by them without any changes.

What steps has the government taken to enact the Lok Pal Bill?

In January 2011, the government has formed a Group of Ministers chaired by Shri Pranab Mukherjee to suggest measures to tackle corruption, including examination of the proposal of a Lok Pal Bill.

What is the purpose of the office of Lok Pal?

The office of the Lok Pal is the Indian version of the office of an Ombudsman who is appointed to inquire into complaints made by citizens against public officials. The Lok Pal is a forum where the citizen can send a complaint against a public official, which would then be inquired into and the citizen would be provided some redressal.

What are issues that have generated debate on the Lok Pal Bill?

There are diverging views on issues such as the inclusion of the office of the Prime Minister, Ministers and Members of Parliament, inclusion of judges, and powers of the Lok Pal. Some experts contend that all public officials should be accountable while others feel that the autonomy and privilege of Parliament require the Prime Minister, Ministers, and Members of Parliament to be accountable only to Parliament.

Have there been other attempts to establish the institution of Lok Pal at the central level?

Yes. The Lok Pal Bill has been introduced eight times in the Lok Sabha (1968, 1971, 1977, 1985, 1989, 1996, 1998 and 2001). However, each time the Lok Sabha was dissolved before the Bill could be passed, except in 1985 when it was withdrawn.

Have any expert commissions made recommendations on the office of Lok Pal?

Yes, a number of commissions have made various recommendations regarding the necessity of the office of the Lok Pal, its composition, powers and functions, and jurisdiction. The commissions, which dealt with the Lok Pal include the First Administrative Reforms Commission of 1966, the National Commission to Review the Working of the Constitution of 2002 and the Second Administrative Reforms Commission of 2007. The Lok Pal Bills that were introduced were referred to various Parliamentary committees (the last three Bills were referred to the Standing Committee on Home Affairs).

What are the present laws that deal with corruption of public officials in India?

Public servants (such as government employees, judges, armed forces, and Members of Parliament) can be prosecuted for corruption under the Indian Penal Code, 1860 and the Prevention of Corruption Act, 1988. However, the Code of Criminal Procedure and the 1988 Act require the investigating agency (such as the CBI) to get prior sanction of the central or state government before it can initiate the prosecution process in a court.

Have the state governments been more successful in setting up bodies to redress public grievances against administrative acts?

So far 18 state governments have enacted legislation to set up the office of Lokayukta and Uplokayukta (deputy Lokayukta). The 18 states are: Andhra Pradesh, Assam, Bihar, Chhattisgarh, Delhi, Gujarat, Jharkhand, Haryana, Himachal Pradesh, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Orissa, Punjab, Rajasthan, Uttarakhand, and Uttar Pradesh.

Which other countries have the office of the Ombudsman for grievances?
Sweden, Finland, Denmark, the Netherlands, Austria, Portugal, Spain, New Zealand, Burkina Faso and the United Kingdom are some of the countries which have the office of an Ombudsman.

The article was published on rediff.com on April 5, 2011