There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Bihar became the first state to scrap the MLA Local Area Development Fund scheme (MLALAD).  According to news reports, Nitish Kumar, Bihar’s Chief Minister, is planning to replace it with the CM Area Development Programme, which would be implemented at the District level.  The schemes would be selected by a district selection committee headed by the minister-in-charge and MLAs and MLCs of that district as members.  The implementation shall rest with a body of engineers, headed by Engineer-in-chief.  The district magistrates would only monitor implementation and contractors would be chosen through open tendering in which a representative of the Comptroller and Auditor General of India (CAG) would be present.  The state government would allocate funds as per requirement. The MPLAD and MLALAD scheme was introduced in December 1993 by former Prime Minister, P.V. Narasimha Rao to enable legislators to execute small works of a local nature to meet the urgent needs of their constituents.  Under the scheme, each legislator may identify projects and sanction upto Rs 2 crore per year for public works in their constituencies.  The scheme was mooted after MPs demanded that they should be able to recommend certain development projects in their constituencies.  The projects include assets building such as drinking water facilities, primary education, public health sanitation and roads.  The initial amount allocated was Rs 5 lakh per year to each MP. It has however not been smooth sailing for the scheme.  Besides the many implementation lapses (as pointed out by the Standing Committee on Finance in 1998-1199, the CAG and the Planning Commission), the constitutionality of the scheme has been questioned by various scholars and experts. In 2002, the National Commission to Review the Working of the Constitution recommended immediate discontinuation of the MPLAD scheme on the ground that it was inconsistent with the spirit of federalism and distribution of powers between the centre and the state.  Former MP, Era Sezhiyan in a booklet titled ‘MPLADS – Concept, Confusion and Contradictions’ also opposed the scheme and recommended that it be scrapped since it ran contrary to the Constitutional provisions which envisaged separate roles for the Executive and Legislature.  However, the Committee on MPLADS in its 13th Report and its 15th Report stated that there was nothing wrong with the scheme per se except some procedural infirmities and recommended among other things a change of nomenclature to the Scheme for Local Area Development.  The debate continued with the 2nd Administrative Reforms Commission’s report on “Ethics in Governance” taking a firm stand against the scheme arguing that it seriously erodes the notion of separation of powers, as the legislator directly becomes the executive.  However, in response to a Writ Petition that challenged the constitutionality of the MPLAD scheme as ultra vires of the Constitution of India, in May 2010, a five-judge bench of the Supreme Court ruled that there was no violation of the concept of separation of powers because the role of an MP in this case is recommendatory and the actual work is carried out by the Panchayats and Municipalities which belong to the executive organ.  There are checks and balances in place through the guidelines which have to be adhered to and the fact that each MP is ultimately responsible to the Parliament. Meanwhile, some MPs are pushing for hiking the amount allocated under the scheme to Rs 5 crore.  However, no decision has been reached yet.  The Ministry of Statistics and Programme Implementation has suggested that a single parliamentary committee be formed comprising of members of both Houses of Parliament to monitor MPLAD schemes. While the question of constitutionality of the MPLAD scheme may have been put to rest by the Supreme Court ruling, other issues related to implementation of the scheme still remain.  Unless problems such as poor utilisation of funds, irregular sanction of works, delay in completion of works are tackled in an efficient manner, the efficacy of the scheme will remain in doubt.