There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The recent 2G-controversy and the related debate over the role of the PAC as opposed to the JPC also raises a broader Issue regarding the general scrutiny of government finances by Parliament.  Oversight of the government’s finances involves the scrutiny of the government’s financial proposals and policies.  The Indian Constitution vests this power with the Parliament by providing that (a) taxes cannot be imposed or collected without the authority of law, and (b) expenditure cannot be incurred without the authorisation of the legislature. The Indian Parliament exercises financial oversight over the government budget in two stages: (1) at the time of presentation of the annual budget, and (2) reviewing the government’s budget implementation efforts through the year. The Parliament scrutinises the annual budget (a) on the floor of the House, and (b) by the departmentally related standing committees. Scrutiny on the floor of the House The main scrutiny of the budget in the Lok Sabha takes place through: (a) General discussion and voting: The general discussion on the Budget is held on a day subsequent to the presentation of the Budget by the Finance Minister.  Discussion at this stage is confined to the general examination of the Budget and policies of taxation expressed during the budget speech. (b) Discussion on Demand for Grants: The general discussion is followed by a discussion on the Demand for Grants of different ministries. A certain number of days or hours are allocated for the discussion of all the demands. However, not all the demands are discussed within the allotted number of days. The remaining undiscussed demands are disposed of by the Speaker after the agreement of the House.  This process is known as the ‘Guillotine’.  Figure 1 shows the number of Demands discussed and guillotined over the last five years.  It shows that nearly 90% of the Demands are not discussed every year. Some Important Budget Documents Annual Financial Statement – Statement of the estimated receipts and expenditure of the government. Demand for Grants –Expenditure required to be voted by the Lok Sabha.  A separate Demand is required to be presented for each department of the government. Supplementary Demand for Grants – Presented when (a) authorized amounts are insufficient, or (b) need for additional expenditure has arisen. Finance Bill – Details the imposition of taxes, the rates of taxation, and its regulation. Detailed Demand for Grants – Prepared on the basis of the Demand for Grants.  These show further break-up of objects by expenditure, and also actual expenditure in the previous year. For more details see detailed note on Financial Oversight by Parliament here.