There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

In recent public discourse over lobbying, two issues that have underscored the debate are:

  1. Greater transparency in the policymaking process, and
  2. Equality of access for all stakeholders in engaging with the process.

There is a need to build linkages between citizens and the policy making process, especially by strengthening scrutiny before a Bill is introduced in Parliament. Currently, there is no process established to ensure pre-legislative scrutiny by the citizenry. Other democracies incorporate several measures to enhance public engagement in the pre-legislative process. These include:

  • Making all Bills available in the public domain for a stipulated period before introducing them in the legislature. This includes, publishing these Bills in forms (language, medium etc) that are accessible to the general public.
  • Making a report or Green paper on the legislative priorities addressed by the Bill available for citizens.
  • Forming adhoc committees to scrutinise the Bill before it is piloted in the House.
  • Having Standing Committees examine the Bill before introducing it in the House.
  • Providing a financial memorandum for each Bill, which specifies the budgetary allocation for the process/bodies created by the Bill.
  • Creating online fora for discussion. For the sections of the stakeholders who have limited access to the internet, efforts are made to proactively consult them through other media.
  • Expanding the purview of citizens’ right to petition their representatives with legislative proposals.

There are several instances, in the last few years itself, wherein civil society groups have played an active role in the development of pre-legislative scrutiny in India.

  • Public consultation with cross-section of stakeholders when drafting a Bill: The Right to Information Act is seen as a landmark legislation when highlighting the role of civil society actors in the drafting of a Bill.  It also serves as a prime example for how it the movement mobilised widespread public opinion for the Bill, bringing together different sections of the citizenry.
  • Public feedback on draft Bills: In several cases, after a Bill has been drafted the concerned ministry or public body publishes the Bill, inviting public comments. The Right to Education Bill, the National Identification Authority Bill and the Draft Direct Taxes Code Bill 2009 are recent cases in point. These announcements are made through advertisements published in newspapers and other media. For instance, the government has recently proposed to amend the rules of the RTI and has invited public feedback on the rules by December 27.
  • Engaging with legislators: It is important to expand engagement with lawmakers after the Bill has been introduced in Parliament, as they will determine what the law will finally contain.  This is done by approaching individual legislators or members of the committee which is likely to examine the legislation. Standing Committees invite feedback on the Bill through newspaper advertisements.  For instance, the Standing Committee examining the Civil Nuclear Liability Bill heard testimonies from journalists, civil society groups, thinktanks, public bodies and government departments.

The role of the media and channelising the potential of the internet are other key approaches that need to be explored. Other examples and channels of engagement with the legislative process are illustrated in the PRS Primer on Engaging with Policymakers