There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

At an event organised by the Hansard Society, a UK based political research and education charity, MPs spoke about what their role entails and the challenges the face in fulfilling their role.  It is striking to note the similarity between what our Parliamentarians have to share about the challenges they face in their roles as representative of the people and what the UK MPs have shared.

  • Management of their diary i.e. Time Management and prioritizing issues are important to the MP being able to do justice to his various roles
  • The MPs stated that the constituency expects action from them on issues which fall within the purview of the local Government and should have been taken up with the councillor. These could be issues related to public works, schools and the like.
  • Quite often the local councillor is unknown to the population and since the MP is easily recognizable, local issues are taken up with him. The MP is obliged to take up the issue because he cannot be seen to turn anyone away.
  • People assume that if you are not seen on the streets you aren't doing your job. Therefore constituency visits are deemed important and end up taking quite a bit of time, which could have been otherwise devoted to legislative work.
  • MPs with a thin majority tend to focus more on local issues for fear of not being able to retain their seat. They tend to try that much harder to address local issues, even with the knowledge that it is not their primary responsibility.
  • Some MPs felt that the committee work should be of foremost priority instead of just an additional responsibility for the MP, as it is at the committee level that all aspects of the legislation can be examined and worked on in detail.
  • MPs should be encouraged to specialize in subjects so that they develop their knowledge in there area of interest.

In general, there are three views the MP has to balance: The Party's, The Constituency's and his or her Personal views. For example the debate on Wind Farms for renewable energy which spoil the landscape, or immigration. These are subjects where the three views may be vary greatly from each other and the MP has to balance each of these. Ultimately, loyalty to party is a must, since the MP won on the party’s ticket, so the MP owes his/her allegiance to the Party and should endorse the Party’s views.