There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.