There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Recently, there have been multiple Naxal attacks on CRPF personnel in Chhattisgarh.  Parliamentary Committees have previously examined the working of the Central Armed Police Forces (CAPFs).  In this context, we examine issues related to functioning of these Forces and recommendations made to address them.

What is the role of the Central Armed Police Forces (CAPFs)?

Under the Constitution, police and public order are state subjects.  However, the Ministry of Home Affairs (MHA) assists state governments by providing them support of the Central Armed Police Forces.  The Ministry maintains seven CAPFs: (i) the Central Reserve Police Force, which assists in internal security and counterinsurgency, (ii) the Central Industrial Security Force, which protects vital installations (like airports) and public sector undertakings, (iii) the National Security Guards, which is a special counterterrorism force, and (iv) four border guarding forces, which are the Border Security Force, Indo-Tibetan Border Police, Sashastra Seema Bal, and Assam Rifles.

What is the sanctioned strength of CAPFs personnel compared to the actual strength?

As of January 2017, the sanctioned strength of the seven CAPFs was 10,78,514 personnel.  However, 15% of these posts (1,58,591 posts) were lying vacant.  Data from the Bureau of Police Research and Development shows that vacancies in the CAPFs have remained over the years.  Table 1 shows the level of vacancies in the seven CAPFs between 2012 and 2017. Nov 2The level of vacancies is different for various police forces.  For example, in 2017, the Sashastra Seema Bal had the highest level of vacancies at 57%.  On the other hand, the Border Security Force had 2% vacancies.  The Central Reserve Police Force, which account for 30% of the sanctioned strength of the seven CAPFs, had a vacancy of 8%.

How often are CAPFs deployed?

According to the Estimates Committee of Parliament, the number of deployment of CAPFs battalions has increased from 91 in 2012-13 to 119 in 2016-17.  The Committee has noted that there has been heavy dependence by states on central police forces even for day-to-day law and order issues.  This is likely to affect anti-insurgency and border-guarding operations of the Forces, as well as curtail their time for training.  The continuous deployment also leaves less time for rest and recuperation.

The Estimates Committee recommended that states must develop their own systems, and augment their police forces by providing adequate training and equipment.  It further recommended that the central government should supplement the efforts of state governments by providing financial assistance and other help for capacity building of their forces.

What is the financial allocation to CAPFs?

Under the Union Budget 2018-19, an allocation of Rs 62,741 crore was made to the seven CAPFs.  Of this, 32% (Rs 20,268 crore) has been allocated to the Central Reserve Police Forces.  The Estimates Committee has pointed out that most of the expenditure of the CAPFs was on salaries.  According to the Committee, the financial performance in case of outlays allocated for capacity augmentation has been very poor.  For example, under the Modernization Plan-II, Rs 11,009 crore was approved for the period 2012-17.  However, the allocation during the period 2013-16 was Rs 251 crore and the reported expenditure was Rs 198 crore.

What are the working conditions for CAPFs personnel?

The Standing Committee on Home Affairs in the year 2017 had expressed concern over the working conditions of personnel of the border guarding forces (Border Security Force, Assam Rifles, Indo-Tibetan Border Police, and Sashastra Seema Bal).  The Committee observed that they had to work 16-18 hours a day, with little time for rest or sleep.  The personnel were also not satisfied with medical facilities that had been provided at border locations.

In addition, the Standing Committee observed that personnel of the CAPFs have not been treated at par with the Armed Forces, in terms of pay and allowances.  The demand for Paramilitary Service Pay, similar to Military Service Pay, had not been agreed to by the Seventh Central Pay Commission.  Further, the Committee observed that the hard-area allowance for personnel of the border guarding forces was much lower as compared to members of the Armed Forces, despite being posted in areas with difficult terrain and harsh weather.

What is the status of training facilities and infrastructure available to CAPFs?

The Estimates Committee has noted that all CAPFs have set up training institutions to meet their training requirements and impart professional skills on specialised topics.  However, the Committee noted that there is an urgent need to upgrade the curriculum and infrastructure in these training institutes.  It recommended that while purchasing the latest equipment, training needs should also be taken care of, and if required, should be included in the purchase agreement itself.  Further, it recommended that the contents of training should be a mix of conventional matters as well as latest technologies such as IT, and cyber security.

According to the Estimates Committee, the MHA has been making efforts to provide modern arms, ammunition, and vehicles to the CAPFs.  In this regard, the Modernization Plan-II, for the period 2012-17, was approved by the Cabinet Committee on Security.  The Plan aims to provide financial support to CAPFs for modernisation in areas of arms, clothing, and equipment.

However, the Committee observed that the procurement process under the Plan was cumbersome and time consuming.  It recommended that the bottlenecks in procurement should be identified and corrective action should be taken.  It further suggested that the MHA and CAPFs should hold negotiations with ordnance factories and manufacturers in the public or private sector, to ensure an uninterrupted supply of equipment and other infrastructure.