The Finance Bill, 2017 is being discussed in Lok Sabha today.  Generally, the Finance Bill is passed as a Money Bill since it gives effect to tax changes proposed in the Union Budget.  A Money Bill is defined in Article 110 of the Constitution as one which only contains provisions related to taxation, borrowings by the government, or expenditure from Consolidated Fund of India.  A Money Bill only needs the approval of Lok Sabha, and is sent to Rajya Sabha for its recommendations.  It is deemed to be passed by Rajya Sabha if it does not pass the Bill within 14 calendar days.

In addition to tax changes, the Finance Bill, 2017 proposes to amend several laws such the Securities Exchange Board of India Act, 1992 and the Payment and Settlements Act, 2007 to make structural changes such as creating a payments regulator and changing the composition of the Securities Appellate Tribunal.  This week, some amendments to the Finance Bill were circulated.  We discuss the provisions of the Bill, and the proposed amendments.

Certain Tribunals to be replaced

Amendments to the Finance Bill seek to replace certain Tribunals and transfer their functions to existing Tribunals.  The rationale behind replacing these Tribunals is unclear.  For example, the Telecom Disputes Settlement and Appellate Tribunal (TDSAT) will replace the Airports Economic Regulatory Authority Appellate Tribunal.  It is unclear if TDSAT, which primarily deals with issues related to telecom disputes, will have the expertise to adjudicate matters related to the pricing of airport services.  Similarly, it is unclear if the National Company Law Appellate Tribunal, which will replace the Competition Appellate Tribunal, will have the expertise to deal with matters related to anti-competitive practices.

Terms of service of Tribunal members to be determined by central government

The amendments propose that the central government may make rules to provide for the terms of service including appointments, term of office, salaries and allowances, and removal for Chairpersons and other members of Tribunals, Appellate Tribunals and other authorities.  The amendments also cap the age of retirement for Chairpersons and Vice-Chairpersons.  Currently, these terms are specified in the laws establishing these Tribunals.

One may argue that allowing the government to determine the appointment, reappointment and removal of members could affect the independent functioning of the Tribunals.  There could be conflict of interest if the government were to be a litigant before a Tribunal as well as determine the appointment of its members and presiding officers.

The Supreme Court in 2014, while examining a case related to the National Tax Tribunal, had held that Appellate Tribunals have similar powers and functions as that of High Courts, and hence matters related to their members’ appointment and reappointment must be free from executive involvement.[i]  The list of Tribunals under this amendment includes several Tribunals before which the central government could be a party to disputes, such as those related to income tax, railways, administrative matters, and the armed forces Tribunal.

Note that a Bill to establish uniform conditions of service for the chairpersons and members of some Tribunals has been pending in Parliament since 2014.

Inclusion of technical members in the Securities Appellate Tribunal 

The composition of the Securities Appellate Tribunal established under the SEBI Act is being changed by the Finance Bill.  Currently, the Tribunal consists of a Presiding Officer and two other members appointed by the central government.  This composition is to be changed to: a Presiding Officer, and a number of judicial and technical members, as notified by the central government.

Creation of a Payments Regulatory Board

Recently, the Ratan Watal Committee under the Finance Ministry had recommended creating a statutory Payments Regulatory Board to oversee the payments systems in light of increase in digital payments.  The Finance Bill, 2017 seeks to give effect to this recommendation by creating a Payments Regulatory Board chaired by the RBI Governor and including members nominated by the central government.  This Board will replace the existing Board for Regulation and Supervision of Payment and Settlement Systems.

Political funding

The Finance Bill, 2017 proposes to make changes related to how donations may be made to political parties, and maintaining the anonymity of donors.

Currently, for donations below Rs 20,000, details of donors do not have to be disclosed by political parties.  Further, there are no restrictions on the amount of cash donations that may be received by political parties from a person.  The Finance Bill has proposed to set this limit at Rs 2,000.  The Bill also introduces a new mode of donating to political parties, i.e. through electoral bonds.  These bonds will be issued by banks, which may be bought through cheque or electronic means.  The only difference between cheque payment (above Rs 20,000) and electoral bonds may be that the identity of the donor will be anonymous in the case of electoral bonds.

Regarding donations by companies to political parties, the proposed amendments to the Finance Bill remove the: (i) existing limit of contributions that a company may make to political parties which currently is 7.5% of net profit of the last three financial years, (ii) requirement of a company to disclose the name of the parties to which a contribution has been made.  In addition, the Bill also proposes that contributions to parties will have to be made only through a cheque, bank draft, electronic means, or any other instrument notified by the central government.

Aadhaar mandatory for PAN and Income Tax

Amendments to the Finance Bill, 2017 make it mandatory for every person to quote their Aadhaar number after July 1, 2017 when: (i) applying for a Permanent Account Number (PAN), or (ii) filing their Income Tax returns.  Persons who do not have an Aadhaar will be required to quote their Aadhaar enrolment number indicating that an application to obtain Aadhaar has been filed.

Every person holding a PAN on July 1, 2017 will be required to provide the authorities with his Aadhaar number by a date and in a manner notified by the central government.  Failure to provide this number would result in the PAN being invalidated.

The Finance Bill, 2017 is making structural changes to some laws.  Parliamentary committees allow for a forum for detailed scrutiny, deliberations and public consultation on proposed laws.  The opportunity to build rigour into the law-making process is lost if such legislative changes are not examined by committees

[i] Madras Bar Association vs. Union of India, Transfer Case No. 150 of 2006, Supreme Court of India, September 25, 2014 (para 89).

In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.