Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified. Last date for submitting the applications is December 21, 2024.

Well, that is the number of seats to be reserved for women in Lok Sabha in the first round if the women’s reservation bill is passed.  The rules for determining number of seats to be reserved are as follows.

  1. The Bill does not reserve one-third of seats on an All-India basis.  It reserves “as nearly as possible, one-third” of seats in each state.
  2. Also, it reserves “as nearly as possible, one-third” of seats reserved for Scheduled Castes in any state for women, and similarly for ST women.  If any state/UT has only 1 seat in any of these categories, that seat will be reserved in the first election, and be open to men in the subsequent two elections.  If a state has 2 seats in any category, one of these will be reserved for women in the first election, the other in the second, and neither in the third election.  One of the two seats nominated for Anglo-Indians will be reserved after the first and second elections.
  3. The reservation for general category seats will be done after following Rules 1 and 2 above.  However, if a state has one or two general category seats, they follow rules similar to that for SC and ST seats (cycling through three elections).

Example 1:  Puducherry has one general seat.  This will be reserved for women in the first election and open in second and third elections. Example 2:  Manipur has two seats, of which one is reserved for STs.  Thus, both seats will be reserved in the first election and open in the second and third elections. Example 3:  Delhi has seven seats:  six general and one SC.  In the each election 2 seats (seven divided by three, rounded to nearest integer) will be reserved.  In the first election, one general and one SC seat will be reserved, and in the next two elections, two general seats will be reserved. We compute that this results in 192, 179 and 175 seats (out of 545) being reserved for women in the first three elections. A similar computation shows that 1367, 1365 and 1364 (out of 4090 seats of the legislative assemblies of 28 states and Delhi) will be reserved for women in the first three elections. Excel file with detailed computation is available here.

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.