In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.

On October 2, 2021, Swachh Bharat Mission (SBM) celebrates its seventh anniversary.  It was launched on October 2, 2014 to fulfil the vision of a cleaner India by October 2, 2019.  The objective of the Mission was to eliminate open defecation, eradicate manual scavenging, and promote scientific solid waste management.  In this blog post, we discuss the sanitation coverage leading up to the launch of the Swachh Bharat Mission and the progress made under this scheme.

Nation-wide sanitation programmes in past

According to the Census, the rural sanitation coverage in India was only 1% in 1981.  

The first nationwide programme with a focus on sanitation was the Central Rural Sanitation Programme (CRSP), which was started in 1986 to provide sanitation facilities in rural areas.  Later, in 1999, CRSP was restructured and launched as the Total Sanitation Campaign (TSC).  While CRSP was a supply-driven infrastructure-oriented programme based on subsidy, TSC was a demand-driven, community-led, project-based programme organised around the district as the unit.

By 2001, only 22% of the rural families had access to toilets.  It increased further to 32.7% by 2011.  In 2012, TSC was revamped as Nirmal Bharat Abhiyan (NBA) to accelerate the sanitation coverage in rural areas through saturation approach and by enhancing incentives for Individual Household Latrines (IHHL).

In comparison to rural sanitation, fewer programmes were enacted to tackle deficiencies in urban sanitation.  In the 1980s, the Integrated Low-Cost Sanitation Scheme provided subsidies for households to build low-cost toilets.  Additionally, the National Slum Development Project and its replacement programme, the Valmiki Ambedkar Awas Yojana launched in 2001, were programmes that aimed to construct community toilets for slum populations.  In 2008, the National Urban Sanitation Policy (NUSP) was announced to manage human excreta and associated public health and environmental impacts.

On October 2, 2014, the Swachh Bharat Mission was launched with two components: Swachh Bharat Mission (Gramin) and Swachh Bharat Mission (Urban), to focus on rural and urban sanitation, respectively.  While the rural component of the Mission is implemented under the Department of Drinking Water and Sanitation, the urban one is implemented by the Ministry of Housing and Urban Affairs.  In 2015, the Sub-Group of Chief Ministers on Swachh Bharat Abhiyaan under NITI Aayog had observed that the key difference between SBM and previous programmes was in the efforts to attract more partners to supplement public sector investment towards sanitation.

Swachh Bharat Mission – Gramin (SBM-Gramin)

The Sub-Group of Chief Ministers (2015) had noted that more than half of India’s 25 crore households do not have access to toilets close to places where they live.  Notably, during the 2015-19 period, a major portion of expenditure under the Department of Drinking Water and Sanitation was towards SBM-Gramin (see Figure 1).

Figure 1: Expenditure on Swachh Bharat Mission-Gramin during 2014-22


Note: Values for 2020-21 are revised estimates and 2021-22 are budget estimates.  Expenditure before 2019-20 were from the erstwhile Ministry of Drinking Water and Sanitation. 
Sources: Union Budgets 2014-15 to 2021-22; PRS.

The expenditure towards Swachh Bharat – Gramin saw a steady increase from 2014-15 (Rs 2,841 crore) to 2017-18 (Rs 16,888 crore) and a decrease in the subsequent years.  Moreover, during 2015-18, the expenditure of the scheme exceeded the budgeted amount by more than 10%.  However, every year since 2018-19, there has been some under-utilisation of the allocated amount. 

As per the Department of Drinking Water and Sanitation, 43.8% of the rural households had access to toilets in 2014-15, which increased to 100% in 2019-20 (see Figure 2).  However, the 15th Finance Commission (2020) noted that the practice of open defecation is still prevalent, despite access to toilets and highlighted that there is a need to sustain the behavioural change of people for using toilets. The Standing Committee on Rural Development raised a similar concern in 2018, noting that “even a village with 100% household toilets cannot be declared open defecation-free (ODF) till all the inhabitants start using them”.  The Standing Committee also raised questions over the construction quality of toilets and observed that the government is counting non-functional toilets, leading to inflated data.

Figure 2: Toilet coverage for rural households


Sources: Dashboard of SBM (Gramin), Ministry of Jal Shakti; PRS.

The 15th Finance Commission also noted that the scheme only provides financial incentives to construct latrines to households below the poverty line (BPL) and selected households above the poverty line.  It highlighted that there are considerable exclusion errors in finding BPL households and recommended the universalisation of the scheme to achieve 100% ODF status.

In March 2020, the Department of Drinking Water and Sanitation launched Phase II of SBM-Gramin which will focus on ODF Plus, and will be implemented from 2020-21 to 2024-25 with an outlay of Rs 1.41 lakh crore.  ODF Plus includes sustaining the ODF status, and solid and liquid waste management.  Specifically, it will ensure that effective solid and liquid waste management is instituted in every Gram Panchayat of the country.

Swachh Bharat Mission – Urban (SBM-Urban)

SBM-Urban aims at making urban India free from open defecation and achieving 100% scientific management of municipal solid waste in 4,000+ towns in the country.  One of its targets was the construction of 66 lakh individual household toilets (IHHLs) by October 2, 2019.  However, this target was then lowered to 59 lakh IHHLS by 2019.  This target was achieved by 2020 (see Table 1).

Table 1: Toilet construction under Swachh Bharat Mission-Urban (as of December 30, 2020)

Targets

Original Target

Revised Target  
(revised in 2019)

Actual Constructed

Individual Household Latrines

66,42,000

58,99,637

62,60,606

Community and Public Toilets

5,08,000

5,07,587

6,15,864

Sources: Swachh Bharat Mission Urban - Dashboard; PRS.

Figure 3: Expenditure on Swachh Bharat Mission-Urban during 2014-22 (in Rs crore)

Note: Values for 2020-21 are revised estimates and 2021-22 are budget estimates. 
Sources: Union Budget 2014-15 to 2021-22; PRS.

The Standing Committee on Urban Development noted in early 2020 that toilets built under the scheme in areas including East Delhi are of very poor quality, and do not have adequate maintenance.  Further, only 1,276 of the 4,320 cities declared to be open defecation free have toilets with water, maintenance, and hygiene.  Additionally, it also highlighted in September 2020 that uneven release of funds for solid waste management across states/UTs needs to be corrected to ensure fair implementation of the programme. 

The Standing Committee on Urban Development (2021) also expressed concern about the slow pace in achieving targets for source segregation and waste processing.  The completion of their targets stood at 78% and 68% respectively of the goal set under SBM-Urban during 2020-21.  In addition, other targets related to the door-to-door collection of waste also remained unfulfilled (see Table 2).

Table 2: Waste management under Swachh Bharat Mission-Urban (progress as of December 30, 2020)

Targets

Target

Progress
as of March 2020

Progress
as of December 2020

Door to Door Waste Collection (Wards)

86,284

81,535 (96%)

83,435 (97%)

Source Segregation (Wards)

86,284

64,730 (75%)

67,367 (78%)

Waste Processing (in %)

100%

65%

68%

Sources: Standing Committee on Urban Development (2021); PRS.

In February 2021, the Finance Minister announced in her budget speech that the Urban Swachh Bharat Mission 2.0 will be launched.  Urban Swachh Bharat Mission 2.0 will focus on: (i) sludge management, (ii) waste-water treatment, (iii) source segregation of garbage, (iv) reduction in single-use plastics and (v) control of air pollution caused by construction, demolition, and bio-remediation of dumpsites.  On October 1, 2021, the Prime Minister launched SBM-Urban 2.0 with the mission to make all our cities ‘Garbage Free’.