Reports suggest that the first reactor of the Kudankulam power plant is close to operational. With state discoms struggling, advocates of nuclear power see Kudankulam as a necessary boost to India’s struggling power sector. The Kudankulam power plant will have two reactors. At full capacity, the plant would produce 2 GW of energy, making it India’s largest nuclear plant, and significantly increasing India’s nuclear capacity (currently at 4.8 GW or 2.3% of total capacity). Internationally, nuclear power plants contributed 12.3 % of the world's electricity production in 2011. In terms of number of nuclear reactors, India ranks 6th in the world with 20 nuclear reactors (in seven power stations across five states: Rajasthan, Uttar Pradesh, Gujarat, Karnataka and Tamil Nadu). The Kudankulam power station would be Tamil Nadu’s second power station after the Madras Atomic Power Station (MAPS). Tamil Nadu is struggling to meet electricity demand, recently moved the Supreme Court, asking the Centre for more power. Peak demand deficit (the difference between electricity supply and demand at peak periods) in the state was 17.5% in 2011-12. The per capita consumption of electricity in the state was 1,132 kWh in 2009-10, significantly greater than the India average of 779 kWh. Currently, electricity in Tamil Nadu is fueled by a mixture of coal (35% of capacity), renewable sources (42%) and hydro sources (12%). A fully operational Kudankulam reactor would boost Tamil Nadu’s capacity by 6% (including state, private and centrally owned generating entities). The interactive table below provides a state-level breakdown of key power sector indicators. To view data in ascending or descending order, simply click the relevant column heading. (For a detailed overview of the power sector and even more state-wise statistics, see here.) [table id=4 /] Source: Central Electricity Authority; Planning Commission; PRS. Note: capacity for states includes allocated shares in joint and central sector utilities. T&D (transmission and distribution) losses refer to losses in electricity in the process of delivery
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.