Reports suggest that the first reactor of the Kudankulam power plant is close to operational. With state discoms struggling, advocates of nuclear power see Kudankulam as a necessary boost to India’s struggling power sector.  The Kudankulam power plant will have two reactors.  At full capacity, the plant would produce 2 GW of energy, making it India’s largest nuclear plant, and significantly increasing India’s nuclear capacity (currently at 4.8 GW or 2.3% of  total capacity). Internationally, nuclear power plants contributed 12.3 % of the world's electricity production in 2011.  In terms of number of nuclear reactors, India ranks 6th in the world with 20 nuclear reactors (in seven power stations across five states: Rajasthan, Uttar Pradesh, Gujarat, Karnataka and Tamil Nadu).  The Kudankulam power station would be Tamil Nadu’s second power station after the Madras Atomic Power Station (MAPS). Tamil Nadu is struggling to meet electricity demand, recently moved the Supreme Court, asking the Centre for more power. Peak demand deficit (the difference between electricity supply and demand at peak periods) in the state was 17.5% in 2011-12.  The per capita consumption of electricity in the state was 1,132 kWh in 2009-10, significantly greater than the India average of 779 kWh.  Currently, electricity in Tamil Nadu is fueled by a mixture of coal (35% of capacity), renewable sources (42%) and hydro sources (12%).  A fully operational Kudankulam reactor would boost Tamil Nadu’s capacity by 6% (including state, private and centrally owned generating entities). The interactive table below provides a state-level breakdown of key power sector indicators.  To view data in ascending or descending order, simply click the relevant column heading.  (For a detailed overview of the power sector and even more state-wise statistics, see here.) [table id=4 /]   Source: Central Electricity Authority; Planning Commission; PRS. Note: capacity for states includes allocated shares in joint and central sector utilities. T&D (transmission and distribution) losses refer to losses in electricity in the process of delivery  

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.