On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER). During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed. The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region. In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.
A new scheme named PM-DevINE announced to boost infrastructure and social development
In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22. The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme. A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.
One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE). It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region). PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture. The scheme will not replace or subsume existing central sector or centrally sponsored schemes. The Scheme will be given an initial allocation of Rs 1,500 crore.
Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)
Major Heads |
2020-21 Actuals |
2021-22 BE |
2021-22 RE |
2022-23 BE |
% change from 2021-22 RE to 2022-23 BE |
North East Special Infrastructure Development Scheme |
446 |
675 |
674 |
1,419 |
111% |
Schemes of North East Council |
567 |
585 |
585 |
702 |
20% |
North East Road Sector Development Scheme |
416 |
696 |
674 |
496 |
-26% |
Central pool of resources for North East and Sikkim |
342 |
581 |
581 |
- |
- |
Others |
270 |
322 |
344 |
241 |
-30% |
Total |
1,854 |
2,658 |
2,658 |
2,800 |
5% |
Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.
Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS.
Allocation towards capital outlay less than demand
The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore). Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges. The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay. It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.
Underutilisation of funds over the years
Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1). For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure). Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.
Figure 1: Underutilisation of funds by the Ministry since 2011-12
Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
Sources: Union Budget Documents (2011-12 to 2022-23); PRS.
Delay in project completion
The Ministry implements several schemes for infrastructural projects such as roads and bridges. The progress of the certain schemes has been inadequate. The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project. Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.
Need to address declining forest cover
The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover. The Committee took note of the declining forest cover in the North East India. As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km). The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities. The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline. It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.
Key issues raised by Members during discussion in Rajya Sabha
The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022. One of the issues highlighted by members was about the Ministry not having its own line Department. This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects. Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region. The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.
Allocation by Union Ministries to the North East
Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation). The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries. In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region. The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore). In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.
Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)
Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.
‘Ease of doing business’ refers to the regulatory environment in a country to set up and operate a business. Every year, the World Bank compares the business environment in 190 countries in its Ease of Doing Business Report. In its report released yesterday, India’s rank improved to 100 out of 190 countries in 2017, from its rank of 130 in the previous year.[1],[2] In this context, we explain the parameters on which each country is ranked, what has led to India’s improvement in rankings, and some recommendations made by committees to further improve the business environment in the country.
What parameters is a country ranked on?
The ease of doing business rankings are based on a country’s performance on 10 parameters such as enforcing contracts and starting a business. In India, these rankings are based on the business environment in Mumbai and Delhi. A lower rank indicates better performance on that parameter, whereas a higher rank indicates worse performance on the indicator. India’s ranking improved in six out of the 10 parameters over the previous year, while it remained the same or fell in the remaining four (see Table 1).
Note that these parameters are regulated by different agencies across the three tiers of government (i.e. central, state and municipal). For example, for starting a business, registration and other clearances are granted by central ministries such as Finance and Corporate Affairs. Electricity and water connections for a business are granted by the state electricity and water boards. The municipal corporations grant building permits and various other no objection certificates to businesses.
What has led to an improvement in India’s ease of doing business rankings?
According to the 2017 report, India introduced changes in some of these parameters, which helped in improving its ranking.1 Some of these changes include:
What are some of the other recommendations to improve the business environment in India?
Over the last few years various committees, such as an Expert Committee constituted by the Department of Industrial Policy and Promotion and the Standing Committee of Commerce, have studied the the regulatory requirements for starting a business in India and the made recommendations on the ease of doing business.[7],[8],[9] Some of the issues and recommendations made by these committees are discussed below.
Starting a business: The Standing Committee observed that regulations and procedures for starting a business are time-consuming.8 The Committee observed that as a consequence, a large number of start-ups are moving out of India and setting base in countries like Singapore where such procedures are easier. It emphasised on the need to streamline regulations to give businesses in India a boost. Note that the government announced the ‘Start-up India Action Plan in January 2016.[10] The 19-point plan identified steps to simplify the process for registering and operating start-ups. It also proposed to grant tax exemptions to these businesses.
The Committee had suggested that the procedures and time period for registration of companies should be reduced. In addition, a unique business ID should be created to integrate all information related to a debtor. This ID should be used as sole reference for the business.
Acquiring land, registering property: Under the current legal framework there are delays in acquiring land and getting necessary permissions to use it. These delays are on account of multiple reasons including the availability of suitable land and disputes related to land titles. It has been noted that land titles in India are unclear due to various reasons including legacy of the zamindari system, gaps in the legal framework and poor administration of land records.[11]
The Standing Committee observed that the process of updating and digitising land records has been going on for three decades. It recommended that this process should be completed at the earliest. The digitised records would assist in removing ambiguity in land titles and help in its smooth transfer. It also suggested that land ownership may be ascertained by integrating space technology and identification documents such as Aadhaar. Note that as of September 2017, land records had been linked with Aadhaar in 4% of the villages across the country.[11]
Several states have taken steps to improve regulations related to land and transfer of property.8 These steps include integration of land records and land registration by Andhra Pradesh and Gujarat, and the passage of a law to certify land titles in urban areas by Rajasthan. The Committee also recommended creating a single window for registration of property, to reduce delays.8
Construction permits: In India, obtaining construction permits involves multiple procedures and is time consuming. The Standing Committee had observed that it took 33 procedures (such as getting no objection certificates from individual departments) over 192 days to obtain a construction permit in India.8 On the other hand, obtaining a similar permit in Singapore involved 10 procedures and took 26 days.
Taxation: The Standing Committee had noted that the tax administration in India was complex, and arbitration proceedings were time-consuming. It observed that the controversies on the Minimum Alternate Tax on capital gains and the tax disputes with companies like Vodafone and Shell had harmed India’s image on taxation matters. Such policy uncertainty and tax disputes have made foreign companies hesitant to do business in India.8
The Committee observed that for ‘Make in India’ to succeed, there is a need for a fair, judicious and stable tax administration in the country. Further, it suggested that to reduce harassment of tax payers, an electronic tax administration system should be created.8 Such a system would reduce human interface during dispute resolution. Note that the Goods and Services Tax (GST) was introduced across the country from July 1, 2017. The GST framework allows for electronic filling of tax returns, among other measures.[12]
Enforcing contracts: Enforcing contracts requires the involvement of the judicial system. The time taken to enforce contracts in India is long. For instance, the Standing Committee noted that it took close to four years in India for enforcing contracts. On the other hand, it took less than six months for contract enforcement in Singapore. This may be due to various reasons including complex litigation procedures, confusion related to jurisdiction of courts and high existing pendency of cases.8
The Standing Committee recommended that an alternative dispute resolution mechanism and fast track courts should be set up to expedite disposal of contract enforcement cases. It suggested that efforts should be made to limit adjournments to exceptional circumstances only. It also recommended that certified practitioners should be created, to assist dispute resolution.8
[1] ‘Doing Business 2018’, World Bank, http://www.doingbusiness.org/~/media/WBG/DoingBusiness/Documents/Annual-Reports/English/DB2018-Full-Report.pdf.
[2] ‘Doing Business 2017’, World Bank, http://www.doingbusiness.org/~/media/WBG/DoingBusiness/Documents/Annual-Reports/English/DB17-Full-Report.pdf.
[3] Insolvency and Bankruptcy Code, 2016, http://www.prsindia.org/billtrack/the-insolvency-and-bankruptcy-bill-2015-4100/.
[4] G.S.R. 436 (E), G.S.R. 437 (E) and G.S.R. 438 (E), Gazette of India, Ministry of Labour and Employment, May 4, 2017, http://labour.gov.in/sites/default/files/Notifications%20for%20amendment%20under%20EPF%2C%20EPS%20and%20EDLI%20Schemes%20for%20e-Payment_0.pdf.
[5] Finance Bill, 2017, http://www.prsindia.org/billtrack/the-finance-bill-2017-4681/; Memorandum explaining the provisions of the Finance Bill, 2017, http://unionbudget.nic.in/ub2017-18/memo/memo.pdf.
[6] National Judicial Data Grid, http://njdg.ecourts.gov.in/njdg_public/index.php.
[7] Report of the Expert Committee on Prior Permissions and Regulatory Mechanism, Department of Industrial Policy Promotion, February 27, 2016.
[8] ‘Ease of Doing Business’, 122nd Report of the Department Related Standing Committee on Commerce, December 21, 2015, http://164.100.47.5/newcommittee/reports/EnglishCommittees/Committee%20on%20Commerce/122.pdf.
[9] Ease of Doing Business: An Enterprise of Survey of Indian States, NITI Aayog, August 28, 2017, http://niti.gov.in/writereaddata/files/document_publication/EoDB_Single.pdf.
[10] Start Up India Action Plan, January 2016, http://www.startupindia.gov.in/pdffile.php?title=Startup%20India%20Action%20Plan&type=Action&q=Action%20Plan.pdf&content_type=Action&submenupoint=action.
[11] Land Records and Titles in India, September 2017, http://www.prsindia.org/parliamenttrack/analytical-reports/land-records-and-titles-in-india-4941/.
[12] The Central Goods and Services Tax Act, 2017, http://www.prsindia.org/billtrack/the-central-goods-and-services-tax-bill-2017-4697/.