On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER). During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed. The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region. In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.
A new scheme named PM-DevINE announced to boost infrastructure and social development
In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22. The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme. A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.
One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE). It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region). PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture. The scheme will not replace or subsume existing central sector or centrally sponsored schemes. The Scheme will be given an initial allocation of Rs 1,500 crore.
Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)
Major Heads |
2020-21 Actuals |
2021-22 BE |
2021-22 RE |
2022-23 BE |
% change from 2021-22 RE to 2022-23 BE |
North East Special Infrastructure Development Scheme |
446 |
675 |
674 |
1,419 |
111% |
Schemes of North East Council |
567 |
585 |
585 |
702 |
20% |
North East Road Sector Development Scheme |
416 |
696 |
674 |
496 |
-26% |
Central pool of resources for North East and Sikkim |
342 |
581 |
581 |
- |
- |
Others |
270 |
322 |
344 |
241 |
-30% |
Total |
1,854 |
2,658 |
2,658 |
2,800 |
5% |
Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.
Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS.
Allocation towards capital outlay less than demand
The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore). Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges. The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay. It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.
Underutilisation of funds over the years
Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1). For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure). Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.
Figure 1: Underutilisation of funds by the Ministry since 2011-12
Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
Sources: Union Budget Documents (2011-12 to 2022-23); PRS.
Delay in project completion
The Ministry implements several schemes for infrastructural projects such as roads and bridges. The progress of the certain schemes has been inadequate. The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project. Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.
Need to address declining forest cover
The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover. The Committee took note of the declining forest cover in the North East India. As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km). The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities. The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline. It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.
Key issues raised by Members during discussion in Rajya Sabha
The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022. One of the issues highlighted by members was about the Ministry not having its own line Department. This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects. Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region. The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.
Allocation by Union Ministries to the North East
Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation). The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries. In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region. The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore). In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.
Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)
Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.
As the dust settles around the 16th Lok Sabha, attention must now shift to the state assemblies, some of which have been newly constituted like Rajasthan, Chhattisgarh, Madhya Pradesh, Odisha, Andhra Pradesh and the few that will go into elections in the next few months like Maharashtra and Haryana. There are 30 state legislative assemblies not including the newly formed state of Seemandhara. In our federal structure, laws framed by the state assemblies are no less important and deserve the same diligence and debate as laws made by Parliament. A brief look in to the performance of some of our state assemblies reveals that these institutions which form the cornerstones of our democracy need some serious attention. State Assemblies: business hours The current Haryana Legislative Assembly that comes to the end of its five year term in October this year has held 10 sessions since 2009 till March 2014, meeting for a total of 54 days – an average of 11 days per year. In comparison, the Lok Sabha sat for an average of 69 days each year from 2009 to 2014. Among state assemblies, only Nagaland and Arunachal Pradesh sat for fewer days than Haryana. In the same period the Kerala Assembly sat for an average of 50 days per year, while Tamil Nadu Assembly sat for 44 days. In its previous term, the Gujarat Legislative Assembly sat for a total of 157 days – an average of 31 days each year. Similarly, the current Goa Legislative Assembly sat for 24 days in 2012 and for 39 days in 2013. Over the last 10 years, the Assembly sat for an average of 26 days a year. It recorded the highest number of sitting days in the last 10 years, at 39 days. Law making in the states In most states, Bills are passed with little or no discussion. Most Bills are introduced and passed on the last day of each session, which gives Members hardly any opportunity to examine or discuss legislation in detail. Unlike Parliament, where most Bills are referred to a department related standing committee which studies the Bill in greater detail, in most states such committees are non-existent. The exceptions are Kerala which has constituted subject committees for this purpose and states like Goa and Himachal Pradesh where Select Committees are constituted for important Bills. The current Haryana Assembly has passed 129 Bills, all of which were passed on the same day as they were introduced. Upto 23 Bills were passed on a single day, which left hardly any time for substantial discussion. In the twelfth Gujarat Assembly, over 90% of all Bills were passed on the same day as they were introduced. In the Budget Session of 2011, 31 Bills were passed of which 21 were introduced and passed within three sitting days. Of the 40 Bills passed by the Goa Assembly till May 2013, three Bills were referred to Select Committees. Excluding Appropriation Bills, the Assembly passed 32 Bills, which were taken up together for discussion and passing in five days. Almost all Bills were passed within three days of introduction. On average, each Bill was discussed for four minutes. In 2012, the West Bengal Legislative Assembly passed a total of 39 Bills, including Appropriation Bills. Most Bills were passed on the same day they were introduced in the Assembly. In 2011, a total of 23 Bills were passed. On average, five Members participated in the discussions on each Bill. In 2012, the Delhi Legislative Assembly passed 11 Bills. Only one of the 11 Bills was discussed for more than 10 minutes. The performance of the Chhattisgarh and Bihar Vidhan Sabhas follow the same pattern. Over the last few years, some assemblies such as Andhra Pradesh, Rajasthan and Haryana have taken some positive steps which include setting up subject committees and permitting live telecast of Assembly proceedings. Every legislator- in Parliament and the states - is accountable to his voter. Weak democratic institutions deprive legislators of their right to oversee the government as enshrined in the Constitution. Inadequate number of sitting days, lack of discussion on Bills, and passing of the Budget and demands for grants without discussion are symptoms of institutional ennui and do not do justice to the enormous import of these legislative bodies. Serious thought and public debate is needed to reinvigorate these ‘temples of democracy’ and provide elected representatives with the opportunity to exercise their right to legislative scrutiny, hold government to account, and represent their constituents.