Applications for the LAMP Fellowship 2025-26 will open soon. Sign up here to be notified when the dates are announced.

On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.

Recently, the Karnataka legislature passed the Bruhat Bengaluru Mahanagara Palike (BBMP) Bill, 2020.  BBMP is the municipal corporation of the Greater Bengaluru metropolitan area.  The BBMP Act, 2020 seeks to improve decentralisation, ensure public participation, and address certain administrative and structural concerns in Bengaluru.  In this blog, we discuss some common issues in urban local governance in India, in the context of Bengaluru’s municipal administration.

The Constitution (74th Amendment) Act, 1992 provided for the establishment of urban local bodies (ULBs) (including municipal corporations) as institutions of local self-government.  It also empowered state governments to devolve certain functions, authority, and power to collect revenue to these bodies, and made periodic elections for them compulsory. 

Urban governance is part of the state list under the Constitution.  Thus, the administrative framework and regulation of ULBs varies across states.  However, experts have highlighted that ULBs across India face similar challenges.  For instance, ULBs across the country lack autonomy in city management and several city-level functions are managed by parastatals (managed by and accountable to the state).  Several taxation powers have also not been devolved to these bodies, leading to stressed municipal finances.  These challenges have led to poor service delivery in cities and also created administrative and governance challenges at the municipal level.

BBMP was established under the Karnataka Municipal Corporation Act, 1976 (KMC Act).  The BBMP Act, 2020 replaces provisions of the KMC Act, 1976 in its application to Bengaluru.  It adds a new level of zonal committees to the existing three-tier municipal structure in the city, and also gives the Corporation some more taxation powers.  Certain common issues in urban local governance in India, with provisions related to them in the BBMP Act, 2020 are given below.

Functional overlap with parastatals for key functions

The Constitution (74th Amendment) Act, 1992 empowered states to devolve the responsibility of 18 functions including urban planning, regulation of land use, water supply, and slum upgradation to ULBs.  However, in most Indian cities including Bengaluru, a majority of these functions are carried out by parastatals.  For example, in Bengaluru, the Bengaluru Development Authority is responsible for land regulation and the Karnataka Slum Clearance Board is responsible for slum rehabilitation. 

The BBMP Act, 2020 provides the Corporation with the power and responsibility to prepare and implement schemes for the 18 functions provided for in the Constitution (74th Amendment) Act, 1992.  However, it does not provide clarity if new bodies at the municipal level will be created, or the existing parastatals will continue to perform these functions and if so, whether their accountability will shift from the state to the municipal corporation. 

This could create a two-fold challenge in administration.  First, if there are multiple agencies performing similar functions, it could lead to a functional overlap, ambiguity, and wastage of resources.  Second, and more importantly, the presence of parastatals that are managed by and accountable to the state government leads to an erosion of the ULB’s autonomy.  Several experts have highlighted that this lack of autonomy faced by municipal corporations in most Indian cities leads to a challenge in governance, effective service delivery, and development of urban areas.

An Expert Committee on Urban Infrastructure (2011) had recommended that activity mapping should be done for the 18 functions.  Under this, functions in the exclusive domain of municipalities and those which need to be shared with the state and the central government must be specified.  Experts have also recommended that the municipality should be responsible for providing civic amenities in its jurisdiction and if a parastatal exercises a civic function, it should be accountable to the municipality.

Stressed municipal finances

Indian ULBs are amongst the weakest in the world in terms of fiscal autonomy and have limited effective devolution of revenue.  They also have limited capacity to raise resources through their own sources of revenue such as property tax.  Municipal revenue in India accounts for only one percent of the GDP (2017-18).  This leads to a dependence on transfers by the state and central government.

ULBs in states like Uttar Pradesh, Uttarakhand, Bihar, Jharkhand, Rajasthan, and Haryana are in poor financial condition.  This has been attributed to limited powers to raise revenue and levy taxes, and problems in the management of existing resources.  For instance, the finances of Bihar’s ULBs were assessed to be poor because of: (i) delays in release of grants, (ii) inadequate devolution of funds, and (iii) delays in revision of tax rates and assessments of landholdings.

In comparison, Karnataka ranks high among Indian states in key indicators for fiscal capacity like collection of property taxes, grants from Central Finance Commissions, and state government transfers.  The BBMP Act, 2020 further increases the taxation powers of the Corporation, by allowing it to impose taxes on professions and entertainment.  

Experts have recommended that the central government and the respective state government should provide additional funds and facilitate additional funding mechanisms for ULBs to strengthen their finances.  The revenue of ULBs can be augmented through measures including assignment of greater powers of taxation to the ULBs by the state government, reforms in land and property-based taxes (such as the use of technology to cover more properties), and issuing of municipal bonds (debt instruments issued by ULBs to finance development projects). 

Powers of elected municipal officials

The executive power with state-appointed municipal Commissioners and elected municipal officers differs across states.  States like Tamil Nadu and Gujarat, and cities like Chennai and Hyderabad vest the executive power in the Commissioner.  In contrast, the executive power of the Corporation is exercised by a Mayor-in council (consisting of the Mayor and up to 10 elected members of the Corporation) in Kolkata and Madhya Pradesh.  This is unlike large metropolitan cities in other countries like New York and London, where elected Mayors are designated as executive heads.  Experts have noted that charging Commissioners with executive power diluted the role of the Mayor and violated the spirit of self-governance.

Under the BBMP Act, 2020, both the elected Mayor and the state-appointed Chief Commissioner exercise several executive functions.  The Mayor is responsible for approving contracts and preparing the budget estimate for the Corporation.  He is also required to discharge all functions assigned to him by the Corporation.  On the other hand, executive functions of the Chief Commissioner include: (i) selling or leasing properties owned by the Corporation, and (ii) regulating and issuing instructions regarding public streets. 

The Expert Committee on Urban Infrastructure (2011) has recommended that the Commissioner should act as a city manager and should be recruited through a transparent search-cum-selection process led by the Mayor.  A Model Municipal law, released by the Urban Development Ministry in 2003, provided that the executive power should be exercised by an Empowered Standing Committee consisting of the Mayor, Deputy Mayor, and seven elected councillors.  

Management of staff and human resources

Experts have noted that municipal administration in India suffers from staffing issues which leads to a failure in delivering basic urban services.  These include overstaffing of untrained manpower, shortage of qualified technical staff and managerial supervisors, and unwillingness to innovate in methods for service delivery. 

The BBMP Act, 2020 provides that the Corporation may make bye-laws for the due performance of duties by its employees.  However, it does not mention other aspects of human resource management such as recruitment and promotion.  A CAG report (2020) looking at the implementation of the Constitution (74th Amendment) Act, 1992 in Karnataka has observed that the power to assess municipal staff requirements, recruiting such staff, and determining their pay, transfer and promotion vests with the state government.  This is in contrast with the recommendations of several experts who have suggested that municipalities should appoint their personnel to ensure accountability, adequate recruitment, and proper management of staff.

Other states including Kerala, Maharashtra and Tamil Nadu also allow the state governments to regulate recruitment and staffing for ULBs.  In cities like Mumbai, and Coimbatore, and some states like Gujarat and Madhya Pradesh, while the recruitment process is conducted by the respective municipal corporations, the final sanction for hiring staff lies with the state government.