There have been articles in the media on the future passage of the Women's Reservation Bill stating that the Bill will have to be ratified by state legislatures before it is signed into law by the President. Our analysis indicates that ratification by state legislatures is not required. We state the reasons below: This Bill amends the Constitution. It (a) amends Article 239AA, Article 331, and Article 333, and (b) inserts Article 330A, Article 332A, and Article 334A. In doing so the Bill:
Article 368 regulates the procedure for amending the Constitution. It states that the ratification of the state legislatures to a constitutional amendment is required in the following cases: a. If there is a change in the provisions regarding elections to the post of the President of India. b. If there is a change in the extent of the executive power of the centre or the state governments. c. If there is any change in the provisions regarding the Union judiciary or the High Courts. d. If the distribution of legislative powers between the centre and the states is affected. e. If any of the Lists in the Seventh Schedule is affected. f. If the representation of the states in the Rajya Sabha is changed. g. Lastly, if Article 368 itself is amended. None of these provisions are attracted in the case of the Women's Reservation Bill. The Parliament recently extended the reservation of seats for SCs, STs and Anglo-Indians in Lok Sabha and Legislative Assemblies by another ten years. Article 334 was amended to state that such reservation "will cease to have effect on the expiration of a period of seventy years from the commencement of the Constitution." The 109th Amendment Bill was passed by both Houses of Parliament and did not require the ratification of the states before being signed into law by the President. It follows that if Bills amending provisions for reserving seats for SCs and STs don't need ratification by state legislatures, a bill reserving seats for women does not need ratification either. Thus Article 368 very clearly lays down situations in which state legislatures have to ratify a piece of legislation before it can receive the assent of the President.
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.