To contain the spread of COVID-19 in India, the central government imposed a nation-wide lockdown on March 24, 2020.  Under the lockdown most economic activities, other than those classified as essential activities, were suspended.  States have noted that this loss of economic activity has resulted in a loss of income for many individuals and businesses.  To allow some economic activities to start, some states have provided relaxations to establishments from their existing labour laws.  This blog explains the manner in which labour is regulated in India, and the various relaxations in labour laws that are being announced by various states. 

How is labour regulated in India?

Labour falls under the Concurrent List of the Constitution.  Therefore, both Parliament and State Legislatures can make laws regulating labour.  Currently, there are over 100 state laws and 40 central laws regulating various aspects of labour such as resolution of industrial disputes, working conditions, social security, and wages.  To improve ease of compliance and ensure uniformity in central level labour laws, the central government is in the process of codifying various labour laws under four Codes on (i) industrial relations, (ii) occupational safety, health and working conditions, (iii) wages, and (iv) social security.  These Codes subsume laws such as the Industrial Disputes Act, 1947, the Factories Act, 1948, and the Payment of Wages Act, 1936.   

How do state governments regulate labour?

A state may regulate labour by: (i) passing its own labour laws, or (ii) amending the central level labour laws, as applicable to the state.   In cases where central and state laws are incompatible, central laws will prevail and the state laws will be void.  However, a state law that is incompatible with central laws may prevail in that state if it has received the assent of the President.  For example: In 2014, Rajasthan amended the Industrial Disputes Act, 1947.  Under the Act, certain special provisions with regard to retrenchment, lay-off and closure of establishments applied to establishments with 100 or more workers.  For example, an employer in an establishment with 100 or more workers required permission from the central or state government prior to retrenchment of workers.  Rajasthan amended the Act to increase the threshold for the application of these special provisions to establishments with 300 workers.  This amendment to the central law prevailed in Rajasthan as it received the assent of the President. 

Which states have passed relaxations to labour laws?

The Uttar Pradesh Cabinet has approved an ordinance, and Madhya Pradesh has promulgated an ordinance, to relax certain aspects of existing labour laws.  Further, Gujarat, Rajasthan, Haryana, Uttarakhand, Himachal Pradesh, Assam, Goa, Uttar Pradesh, and Madhya Pradesh have notified relaxations to labour laws through rules.

Madhya Pradesh:  On May 6, 2020, the Madhya Pradesh government promulgated the Madhya Pradesh Labour Laws (Amendment) Ordinance, 2020.  The Ordinance amends two state laws: the Madhya Pradesh Industrial Employment (Standing Orders) Act, 1961, and the Madhya Pradesh Shram Kalyan Nidhi Adhiniyam, 1982.  The 1961 Act regulates the conditions of employment of workers and applies to all establishments with 50 or more workers.  The Ordinance increases this threshold to 100 or more workers.  Therefore, the Act will no longer apply to establishments with between 50 and 100 workers that were previously regulated.  The 1982 Act provides for the constitution of a Fund that will finance activities related to welfare of labour.  The Ordinance amends the Act to allow the state government to exempt any establishment or class of establishments from the provisions of the Act through a notification.  These provisions include payment of contributions into the Fund by employers at the rate of three rupees every six months. 

Further, the Madhya Pradesh government has exempted all new factories from certain provisions of the Industrial Disputes Act, 1947.  Provisions related to lay-off and retrenchment of workers, and closure of establishments will continue to apply.  However, the other provisions of the Act such as those related to industrial dispute resolution, strikes and lockouts, and trade unions, will not apply.   This exemption will remain in place for the next 1,000 days (33 months).  Note that the Industrial Disputes Act, 1947 allows the state government to exempt certain establishments from the provisions of the Act as long as it is satisfied that a mechanism is in place for the settlement and investigation of industrial disputes.

Uttar Pradesh

The Uttar Pradesh Cabinet has approved the Uttar Pradesh Temporary Exemption from Certain Labour Laws Ordinance, 2020.  According to news reports, the Ordinance seeks to exempt all factories and establishments engaged in manufacturing processes from all labour laws for a period of three years, subject to the fulfilment of certain conditions.  These conditions include:

  • Wages:  The Ordinance specifies that workers cannot be paid below minimum wage.  Further, workers must be paid within the time limit prescribed in the Payment of Wages Act, 1936.  The Act specifies that: (i) establishments with less than 1,000 workers must pay wages before the seventh day after the last day of the wage period and (ii) all other establishments must pay wages before the tenth day after the last day of the wage period.  Wages must be paid into the bank accounts of workers. 

  • Health and safety:   The Ordinance states that provisions of health and safety specified in the Building and Other Construction Workers Act, 1996 and Factories Act, 1948 will continue to apply.  These provisions regulate the usage of dangerous machinery, inspections, and maintenance of factories, amongst others. 

  • Work Hours:  Workers cannot be required to work more than eleven hours a day and the spread of work may not be more than 12 hours a day. 

  • Compensation:  In the case of accidents leading to death or disability, workers will be compensated as per the Employees Compensation Act, 1923. 

  • Bonded Labour: The Bonded Labour System (Abolition) Act, 1976 will continue to remain in force.  It provides for the abolition of the bonded labour system.   Bonded labour refers to the system of forced labour where a debtor enters into an agreement with the creditor under certain conditions such as to repay his or a family members debt, due to his caste or community, or due to a social obligation.  

  • Women and children:  Provisions of labour laws relating to the employment of women and children will continue to apply.  

It is unclear if labour laws providing for social security, industrial dispute resolution, trade unions, strikes, amongst others, will continue to apply to businesses in Uttar Pradesh for the period of three years specified in the Ordinance.  Since the Ordinance is restricting the application of central level labour laws, it requires the assent of the President to come into effect. 

Changes in work hours

The Factories Act, 1948 allows state governments to exempt factories from provisions related to work hours for a period of three months if factories are dealing with an exceptional amount of work.  Further, state governments may exempt factories from all provisions of the Act in the case of public emergencies.  The Gujarat, Himachal Pradesh, Rajasthan, Haryana, Uttar Pradesh, Goa, Assam and Uttarakhand governments passed notifications to increase maximum weekly work hours from 48 hours to 72 hours and daily work hours from 9 hours to 12 hours for certain factories using this provision.  Further, Madhya Pradesh has exempted all factories from the provisions of the Factories Act, 1948 that regulate work hours.  These state governments have noted that an increase in work hours would help address the shortage of workers caused by the lockdown and longer shifts would ensure fewer number of workers in factories allowing for social distancing to be maintained.   Table 1 shows the state-wise increase in maximum work hours. 

Table 1: State-wise changes to work hours

State

Establishments

Maximum weekly work hours

Maximum daily work hours

Overtime Pay (2x ordinary wages)

Time period

Gujarat

All factories

Increased from 48 hours to 72 hours 

Increased from 9 hours to 12 hours 

Not required

Three months

Himachal Pradesh

All factories

Increased from 48 hours to 72 hours 

Increased from 9 hours to 12 hours 

Required

Three months

Rajasthan

All factories distributing essential goods and manufacturing essential goods and food

Increased from 48 hours to 72 hours 

Increased from 9 hours to 12 hours 

Required

Three months

Haryana

All factories

Not specified  

Increased from 9 hours to 12 hours 

Required

Two months

Uttar Pradesh

All factories

Increased from 48 hours to 72 hours 

Increased from 9 hours to 12 hours 

Not required

Three months*

Uttarakhand

All factories and continuous process industries that are allowed to function by government

Maximum 6 days of work a week

Two shifts of 12 hours each.

Required

Three months

Assam

All factories

Not specified

Increased from 9 hours to 12 hours 

Required

Three months

Goa

All factories

Not specified

Increased from 9 hours to 12 hours 

Required

Approximately three months

Madhya Pradesh

All factories

Not specified

Not specified

Not specified

Three months

Note: *The Uttar Pradesh notification was withdrawn

Yesterday, Parliament passed a Bill to increase the number of judges in the Supreme Court from 30 to 33 (excluding the Chief Justice of India).  The Bill was introduced in view of increasing pendency of cases in the Supreme Court.  In 2012, the Supreme Court approved the Scheme of National Court Management System to provide a framework for case management.  The scheme estimated that with an increase in literacy, per capita income, and population, the number of new cases filed each year may go up to 15 crore over the next three decades, which will require at least 75,000 judges.  In this blog, we analyse the pendency of cases at all three levels of courts, i.e. the Supreme Court, the Highs Courts, and the subordinate courts, and discuss the capacity of these courts to dispose of cases.

Pendency in courts has increased over the years; 87% of all pending cases are in subordinate courts

Sources:  Court News, 2006, Supreme Court of India; National Data Judicial Grid accessed on August 7, 2019; PRS.

Overall, the pendency of cases has increased significantly at every level of the judicial hierarchy in the last decade.  Between 2006 and now, there has been an overall increase of 22% (64 lakh cases) in the pendency of cases across all courts.  As of August 2019, there are over 3.5 crore cases pending across the Supreme Court, the High Courts, and the subordinate courts.  Of these, subordinate courts account for over 87.3% pendency of cases, followed by 12.5% pendency before the 24 High Courts.  The remaining 0.2% of cases are pending with the Supreme Court.  The primary reason for growing pendency of cases is that the number of new cases filed every year has outpaced the number of disposed of cases.  This has resulted in a growing backlog of cases.

In High Courts and subordinate courts, over 32 lakh cases pending for over 10 years

 

 

 

 

 

 

 

Sources:  National Data Judicial Grid accessed on August 7, 2019; Court News, 2006-17, Supreme Court of India; PRS.

In the High Courts, over 8.3 lakh cases have been pending for over 10 years.  This constitutes 19% of all pending High Court cases.  Similarly, in the subordinate courts, over 24 lakh cases (8%) have been pending for over 10 years.  Overall, Allahabad High Court had the highest pendency, with over seven lakh cases pending as of 2017.

Despite high pendency, some High Courts have managed to reduce their backlog.  Between 2006 and 2017, pendency of cases reduced the most in Madras High Court at a rate of 26%, followed by Bombay High Court at 24%.  Conversely, during the same period, the pendency of cases doubled in the Andhra Pradesh High Court, and increased by 2.5 times in Karnataka High Court.

As a result of pendency, number of under-trials in prison is more than double that of convicts

Sources:  Prison Statistics in India, 2015, National Crime Record Bureau; PRS.

Over the years, as a result of growing pendency of cases for long periods, the number of undertrials (accused awaiting trial) in prisons has increased.  Prisons are running at an over-capacity of 114%.  As of 2015, there were over four lakh prisoners in jails.  Of these, two-thirds were undertrials (2.8 lakh) and the remaining one-third were convicts. 

The highest proportion of undertrials (where the number of inmates was at least over 1,000) were in J&K (85%), followed by Bihar (82%).  A total of 3,599 undertrials were detained in jails for more than five years.  Uttar Pradesh had the highest number of such undertrials (1,364) followed by West Bengal (294). 

One interesting factor to note is that more criminal cases are filed in subordinate courts than in High Courts and Supreme Court.  Of the cases pending in the subordinate courts (which constitute 87% of all pending cases), 70% of cases were related to criminal matters.  This increase in the pendency of cases for long periods over the years may have directly resulted in an increase in the number of undertrials in prisons.  In a statement last year, the Chief Justice of India commented that the accused in criminal cases are getting heard after serving out their sentence.

Vacancies in High Courts and Subordinate Courts affect the disposal of cases

Sources:  Court News, 2006-17, Supreme Court of India; PRS.

Vacancy of judges across courts in India has affected the functioning of the judiciary, particularly in relation to the disposal of cases.  Between 2006 and 2017, the number of vacancies in the High Courts has increased from 16% to 37%, and in the subordinate courts from 19% to 25%.  As of 2017, High Courts have 403 vacancies against a sanctioned strength of 1,079 judges, and subordinate courts have 5,676 vacancies against a sanctioned strength of 22,704 judges.  As of 2017, among the major High Courts (with sanctioned strength over 10 judges), the highest proportion of vacancies was in Karnataka High Court at 60% (37 vacancies), followed by Calcutta High Court at 54% (39 vacancies).  Similarly, in major subordinate courts (with sanctioned strength over 100 judges), the highest proportion of vacancies was in Bihar High Court at 46% (835 vacancies), followed by Uttar Pradesh High Court at 42% (1,348 vacancies).