Miscellaneous

RTI rejections

Sachin - November 1, 2011

The Right to Information Act, 2005, contains several exemptions which enable public authorities to deny requests for information. RTI Annual Return Reports for 2005-2010 give detailed information on use of these exemptions to reject RTI requests. Exemptions to requests for information under the Act are primarily embodied in three sections – section 8, section 11, and section 24. Section 8 lists nine specific exemptions ranging from sovereignty of India to trade secrets. Sec 11 provides protection to confidential third party information. Sec 24 exempts certain security and intelligence organizations from the purview of the Act. Of these, sections 8(1)(j), 8(1)(d) and 8(1)(e) are respectively the three most frequently invoked exemptions for the period 2005-2010, cumulatively amounting to almost three-fourths of all exemptions invoked.   orange Section 8(1)(j) provides protection to personal information of individuals from disclosure in the absence of larger public interest. This exemption was invoked over 30,000 times during 2005-2010, which amounts to almost 40% of all invocations of exemptions. Among ministries, the Finance Ministry has invoked this sub-section the most, followed by the Ministry of Communications and Information Technology. Section 8(1)(d) provides protection to trade secrets and intellectual property from disclosure in the absence of larger public interest. This exemption was invoked almost 15,000 times during 2005-2010, which constitutes 18% of all invocations of exemptions. As with sec 8(1)(j), the Finance Ministry has utilized this exemption the most, followed by the Ministry of Petroleum and Natural Gas. Section 8(1)(e) provides protection to information available to a person in his fiduciary relationship from disclosure in the absence of larger public interest. This exemption was invoked 11,639 times during 2005-2010, which accounts for almost 15% of all invocations of exemptions. The Finance Ministry has invoked this exemption more than any other ministry, both overall and for each individual year during 2005-2010. The Finance Ministry accounts for more than 50% of all invocations of this exemption, having invoked it over 6000 times. The Ministry of Petroleum and Natural Gas is second, with a little over 1000 invocations of this exemption. Ministry-wise Rejections As discussed above, Finance Ministry has a large number of rejections, perhaps because of the larger number of requests that it receives.  It is also possible that the Finance Ministry receives a larger number of requests related to private and confidential information (such as Income Tax returns) as well as those which are held in a fiduciary capacity (such as details of accounts in nationalised banks).  Adjusted for the number of requests received, the Finance Ministry tops the rejection rate at 24%, followed by the Prime Minister's Office (12%) and the Ministry of Petroleum and Natural Gas (11%). blue

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.