Safety has been one of the biggest concerns in the Indian Railways system.  While the number of accidents have gone down over the last few years, the number still remains over 100 accidents a year.  In light of the recent train accidents in Uttar Pradesh (UP), we present some details around accidents and safety in the Indian Railways.

Causes of rail accidents

The number of rail accidents has declined from 325 in 2003-04 to 106 in 2015-16.[1]  The number of rail accidents as per the cause are shown in the graph below.  In 2015-16, majority of the accidents were caused due to derailments (60%), followed by accidents at level crossings (33%).1  In the last decade, accidents caused due to both these causes have reduced by about half.  According to news reports, the recent railway accidents in UP were caused due to derailment of coaches.

1

Derailments

Between 2003-04 and 2015-16, derailments were the second highest reason for casualties.2  The Standing Committee on Railways, when examining the safety in railways, had noted that one of the reasons for derailments is defect in the track or coaches.  Of the total track length of 1,14,907 kms in the country, 4,500 kms should be renewed annually.2  However, in 2015-16, of the 5,000 km of track length due for renewal, only 2,700 km was targeted to be renewed.2  The Committee had recommended that Indian Railways should switch completely to the Linke Hoffman Busch (LHB) coaches as they do not pile upon each other during derailments and hence cause lesser casualties.2

Un-manned level crossings

Un-manned level crossings (UMLCs) continue to be the biggest cause of casualties in rail accidents.  Currently there are 14,440 UMLCs in the railway network.  In 2014-15, about 40% of the accidents occurred at UMLCs, and in 2015-16, about 28%.2  Between 2010 and 2013, the Ministry fell short of meeting their annual targets to eliminate UMLCs.  Further, the target of eliminating 1,352 UMLCs was reduced by about 50% to 730 in 2014-15, and 820 in 2015-16.2  Implementation of audio-visual warnings at level crossings has been recommended to warn road users about approaching trains.2  These may include Approaching Train Warning Systems, and Train Actuated Warning Systems.2  The Union Budget 2017-18 proposes to eliminate all unmanned level crossings on broad gauge lines by 2020.

Casualties and compensation

In the last few years, Railways has paid an average compensation of Rs 3.03 crore every year for accidents (see figure below).[2]

2

Note: Compensation paid during a year relates to the cases settled and not to accidents/casualties during that year.

Consequential train accidents

Accidents in railways may or may not have a significant impact on the overall system.  Consequential train accidents are those which have serious repercussions in terms of loss of human life or injury, damage to railway property or interruption to rail traffic.  These include collisions, derailments, fire in trains, and similar accidents that have serious repercussions in terms of casualties and damage to property.  These exclude cases of trespassing at unmanned railway crossings.

As seen in the figure below, the share of failure of railways staff is the biggest cause of consequential rail accidents.  The number of rail accidents due to failure of reasons other than the railway staff (sabotage) has increased in the last few years.

3

Accidents due to failure of railway staff

It has been noted that more than half of the accidents are due to lapses on the part of railway staff.2  Such lapses include carelessness in working, poor maintenance, adoption of short-cuts, and non-observance of laid down safety rules and procedures.  To address these issues, conducting a regular refresher course for each category of railway staff has been recommended.2

Accidents due to loco-pilots2,[3]

Accidents also occur due to signalling errors for which loco-pilots (train-operators) are responsible.  With rail traffic increasing, loco-pilots encounter a signal every few kilometres and have to constantly be on high alert.  Further, currently no technological support is available to the loco-pilots and they have to keep a vigilant watch on the signal and control the train accordingly.2 These Loco-pilots are over-worked as they have to be on duty beyond their stipulated working hours.  This work stress and fatigue puts the life of thousands of commuters at risk and affects the safety of train operations.2  It has been recommended that loco-pilots and other related running staff should be provided with sound working conditions, better medical facilities and other amenities to improve their performance.2

Actions taken by Railways with regard to the recent train accident

According to news reports, the recent accident of Utkal Express in UP resulted in 22 casualties and over 150 injuries.[4]  It has also been reported that following this incident, the Railways Ministry initiated action against certain officials (including a senior divisional engineer), and three senior officers (including a General Manager and a Railway Board Member).

The Committee on Restructuring of Railways had noted that currently each Railway zone (headed by a General Manager) is responsible for operation, management, and development of the railway system under its jurisdiction.[5]  However, the power to make financial decisions does not rest with the zones and hence they do not possess enough autonomy to generate their own revenue, or take independent decisions.5

While the zones prepare their annual budget, the Railway Board provides the annual financial budget outlay for each of them.  As a result of such budgetary control, the GM’s powers have been reduced leaving them with little independence in planning their operations.5

The Committee recommended that the General Managers must be fully empowered to take all necessary decisions independent of the Railway Board.5  Zonal Railways should also have full power for expenditure and re-appropriations and sanctions.  This will make each Zonal Railway accountable for its transport output, profitability and safety under its jurisdiction.

Under-investment in railways leading to accidents

In 2012, a Committee headed by Mr. Anil Kakodkar had estimated that the total financial cost of implementing safety measures over the five-year period (2012-17) was likely be around Rs one lakh crore.  In the Union Budget 2017-18, the creation of a Rashtriya Rail Sanraksha Kosh was proposed for passenger safety.  It will have a corpus of Rs one lakh crore, which will be built over a five-year period (Rs 20,000 crore per year).

The Standing Committee on Railways had noted that slow expansion of rail network has put undue burden on the existing infrastructure leading to severe congestion and safety compromises.2  Since independence, while the rail network has increased by 23%, passenger and freight traffic over this network has increased by 1,344% and 1,642% respectively.2  This suggests that railway lines are severely congested.  Further, under-investment in the sector has resulted in congested routes, inability to add new trains, reduction of train speeds, and more rail accidents.2  Therefore, avoiding such accidents in the future would also require significant investments towards capital and maintenance of rail infrastructure.2

Tags: railways, safety, accidents, finances, derailment, casualty, passengers, train

[1] Railways Year Book 2015-16, Ministry of Railways, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/stat_econ/IRSP_2015-16/Year_Book_Eng/8.pdf.

[2] “12th Report: Safety and security in Railways”, Standing Committee on Railways, December 14, 2016, http://164.100.47.193/lsscommittee/Railways/16_Railways_12.pdf.

[3] Report of High Level Safety Review Committee, Ministry of Railways, February 17, 2012.

[4] “Utkal Express derailment: Four railway officials suspended as death toll rises to 22”, The Indian Express, August 20, 2017, http://indianexpress.com/article/india/utkal-express-train-derailment-four-railway-officers-suspended-suresh-prabhu-muzaffarnagar-22-dead-4805532/.

[5] Report of the Committee for Mobilization of Resources for Major Railway Projects and Restructuring of Railway Ministry and Railway Board, Ministry of Railways, June 2015, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/HLSRC/FINAL_FILE_Final.pdf.

As the dust settles around the 16th Lok Sabha, attention must now shift to the state assemblies, some of which have been newly constituted like Rajasthan, Chhattisgarh, Madhya Pradesh, Odisha, Andhra Pradesh and the few that will go into elections in the next few months like Maharashtra and Haryana. There are 30 state legislative assemblies not including the newly formed state of Seemandhara. In our federal structure, laws framed by the state assemblies are no less important and deserve the same diligence and debate as laws made by Parliament. A brief look in to the performance of some of our state assemblies reveals that these institutions which form the cornerstones of our democracy need some serious attention. State Assemblies: business hours The current Haryana Legislative Assembly that comes to the end of its five year term in October this year has held 10 sessions since 2009 till March 2014, meeting for a total of 54 days – an average of 11 days per year. In comparison, the Lok Sabha sat for an average of 69 days each year from 2009 to 2014. Among state assemblies, only Nagaland and Arunachal Pradesh sat for fewer days than Haryana. In the same period the Kerala Assembly sat for an average of 50 days per year, while Tamil Nadu Assembly sat for 44 days. In its previous term, the Gujarat Legislative Assembly sat for a total of 157 days – an average of 31 days each year. Similarly, the current Goa Legislative Assembly sat for 24 days in 2012 and for 39 days in 2013. Over the last 10 years, the Assembly sat for an average of 26 days a year.  It recorded the highest number of sitting days in the last 10 years, at 39 days. Law making in the states In most states, Bills are passed with little or no discussion. Most Bills are introduced and passed on the last day of each session, which gives Members hardly any opportunity to examine or discuss legislation in detail. Unlike Parliament, where most Bills are referred to a department related standing committee which studies the Bill in greater detail, in most states such committees are non-existent.  The exceptions are Kerala which has constituted subject committees for this purpose and states like Goa and Himachal Pradesh where Select Committees are constituted for important Bills. The current Haryana Assembly has passed 129 Bills, all of which were passed on the same day as they were introduced. Upto 23 Bills were passed on a single day, which left hardly any time for substantial discussion. In the twelfth Gujarat Assembly, over 90% of all Bills were passed on the same day as they were introduced. In the Budget Session of 2011, 31 Bills were passed of which 21 were introduced and passed within three sitting days. Of the 40 Bills passed by the Goa Assembly till May 2013, three Bills were referred to Select Committees. Excluding Appropriation Bills, the Assembly passed 32 Bills, which were taken up together for discussion and passing in five days. Almost all Bills were passed within three days of introduction. On average, each Bill was discussed for four minutes. In 2012, the West Bengal Legislative Assembly passed a total of 39 Bills, including Appropriation Bills.  Most Bills were passed on the same day they were introduced in the Assembly.  In 2011, a total of 23 Bills were passed. On average, five Members participated in the discussions on each Bill. In 2012, the Delhi Legislative Assembly passed 11 Bills. Only one of the 11 Bills was discussed for more than 10 minutes. The performance of the Chhattisgarh and Bihar Vidhan Sabhas follow the same pattern. Over the last few years, some assemblies such as Andhra Pradesh, Rajasthan and Haryana have taken some positive steps which include setting up subject committees and permitting live telecast of Assembly proceedings. Every legislator- in Parliament and the states - is accountable to his voter. Weak democratic institutions deprive legislators of their right to oversee the government as enshrined in the Constitution. Inadequate number of sitting days, lack of discussion on Bills, and passing of the Budget and demands for grants without discussion are symptoms of institutional ennui and do not do justice to the enormous import of these legislative bodies. Serious thought and public debate is needed to reinvigorate these ‘temples of democracy’ and provide elected representatives with the opportunity to exercise their right to legislative scrutiny, hold government to account, and represent their constituents.