Safety has been one of the biggest concerns in the Indian Railways system.  While the number of accidents have gone down over the last few years, the number still remains over 100 accidents a year.  In light of the recent train accidents in Uttar Pradesh (UP), we present some details around accidents and safety in the Indian Railways.

Causes of rail accidents

The number of rail accidents has declined from 325 in 2003-04 to 106 in 2015-16.[1]  The number of rail accidents as per the cause are shown in the graph below.  In 2015-16, majority of the accidents were caused due to derailments (60%), followed by accidents at level crossings (33%).1  In the last decade, accidents caused due to both these causes have reduced by about half.  According to news reports, the recent railway accidents in UP were caused due to derailment of coaches.

1

Derailments

Between 2003-04 and 2015-16, derailments were the second highest reason for casualties.2  The Standing Committee on Railways, when examining the safety in railways, had noted that one of the reasons for derailments is defect in the track or coaches.  Of the total track length of 1,14,907 kms in the country, 4,500 kms should be renewed annually.2  However, in 2015-16, of the 5,000 km of track length due for renewal, only 2,700 km was targeted to be renewed.2  The Committee had recommended that Indian Railways should switch completely to the Linke Hoffman Busch (LHB) coaches as they do not pile upon each other during derailments and hence cause lesser casualties.2

Un-manned level crossings

Un-manned level crossings (UMLCs) continue to be the biggest cause of casualties in rail accidents.  Currently there are 14,440 UMLCs in the railway network.  In 2014-15, about 40% of the accidents occurred at UMLCs, and in 2015-16, about 28%.2  Between 2010 and 2013, the Ministry fell short of meeting their annual targets to eliminate UMLCs.  Further, the target of eliminating 1,352 UMLCs was reduced by about 50% to 730 in 2014-15, and 820 in 2015-16.2  Implementation of audio-visual warnings at level crossings has been recommended to warn road users about approaching trains.2  These may include Approaching Train Warning Systems, and Train Actuated Warning Systems.2  The Union Budget 2017-18 proposes to eliminate all unmanned level crossings on broad gauge lines by 2020.

Casualties and compensation

In the last few years, Railways has paid an average compensation of Rs 3.03 crore every year for accidents (see figure below).[2]

2

Note: Compensation paid during a year relates to the cases settled and not to accidents/casualties during that year.

Consequential train accidents

Accidents in railways may or may not have a significant impact on the overall system.  Consequential train accidents are those which have serious repercussions in terms of loss of human life or injury, damage to railway property or interruption to rail traffic.  These include collisions, derailments, fire in trains, and similar accidents that have serious repercussions in terms of casualties and damage to property.  These exclude cases of trespassing at unmanned railway crossings.

As seen in the figure below, the share of failure of railways staff is the biggest cause of consequential rail accidents.  The number of rail accidents due to failure of reasons other than the railway staff (sabotage) has increased in the last few years.

3

Accidents due to failure of railway staff

It has been noted that more than half of the accidents are due to lapses on the part of railway staff.2  Such lapses include carelessness in working, poor maintenance, adoption of short-cuts, and non-observance of laid down safety rules and procedures.  To address these issues, conducting a regular refresher course for each category of railway staff has been recommended.2

Accidents due to loco-pilots2,[3]

Accidents also occur due to signalling errors for which loco-pilots (train-operators) are responsible.  With rail traffic increasing, loco-pilots encounter a signal every few kilometres and have to constantly be on high alert.  Further, currently no technological support is available to the loco-pilots and they have to keep a vigilant watch on the signal and control the train accordingly.2 These Loco-pilots are over-worked as they have to be on duty beyond their stipulated working hours.  This work stress and fatigue puts the life of thousands of commuters at risk and affects the safety of train operations.2  It has been recommended that loco-pilots and other related running staff should be provided with sound working conditions, better medical facilities and other amenities to improve their performance.2

Actions taken by Railways with regard to the recent train accident

According to news reports, the recent accident of Utkal Express in UP resulted in 22 casualties and over 150 injuries.[4]  It has also been reported that following this incident, the Railways Ministry initiated action against certain officials (including a senior divisional engineer), and three senior officers (including a General Manager and a Railway Board Member).

The Committee on Restructuring of Railways had noted that currently each Railway zone (headed by a General Manager) is responsible for operation, management, and development of the railway system under its jurisdiction.[5]  However, the power to make financial decisions does not rest with the zones and hence they do not possess enough autonomy to generate their own revenue, or take independent decisions.5

While the zones prepare their annual budget, the Railway Board provides the annual financial budget outlay for each of them.  As a result of such budgetary control, the GM’s powers have been reduced leaving them with little independence in planning their operations.5

The Committee recommended that the General Managers must be fully empowered to take all necessary decisions independent of the Railway Board.5  Zonal Railways should also have full power for expenditure and re-appropriations and sanctions.  This will make each Zonal Railway accountable for its transport output, profitability and safety under its jurisdiction.

Under-investment in railways leading to accidents

In 2012, a Committee headed by Mr. Anil Kakodkar had estimated that the total financial cost of implementing safety measures over the five-year period (2012-17) was likely be around Rs one lakh crore.  In the Union Budget 2017-18, the creation of a Rashtriya Rail Sanraksha Kosh was proposed for passenger safety.  It will have a corpus of Rs one lakh crore, which will be built over a five-year period (Rs 20,000 crore per year).

The Standing Committee on Railways had noted that slow expansion of rail network has put undue burden on the existing infrastructure leading to severe congestion and safety compromises.2  Since independence, while the rail network has increased by 23%, passenger and freight traffic over this network has increased by 1,344% and 1,642% respectively.2  This suggests that railway lines are severely congested.  Further, under-investment in the sector has resulted in congested routes, inability to add new trains, reduction of train speeds, and more rail accidents.2  Therefore, avoiding such accidents in the future would also require significant investments towards capital and maintenance of rail infrastructure.2

Tags: railways, safety, accidents, finances, derailment, casualty, passengers, train

[1] Railways Year Book 2015-16, Ministry of Railways, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/stat_econ/IRSP_2015-16/Year_Book_Eng/8.pdf.

[2] “12th Report: Safety and security in Railways”, Standing Committee on Railways, December 14, 2016, http://164.100.47.193/lsscommittee/Railways/16_Railways_12.pdf.

[3] Report of High Level Safety Review Committee, Ministry of Railways, February 17, 2012.

[4] “Utkal Express derailment: Four railway officials suspended as death toll rises to 22”, The Indian Express, August 20, 2017, http://indianexpress.com/article/india/utkal-express-train-derailment-four-railway-officers-suspended-suresh-prabhu-muzaffarnagar-22-dead-4805532/.

[5] Report of the Committee for Mobilization of Resources for Major Railway Projects and Restructuring of Railway Ministry and Railway Board, Ministry of Railways, June 2015, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/HLSRC/FINAL_FILE_Final.pdf.

In an Indian express editorial, Mandira Kala discusses the Bills, addressing corruption and good governance, pending in Parliament.  She discusses what their fate may be given that the Monsoon session is widely being viewed as a make or break session  for the government to get its legislative agenda through Parliament. The monsoon session of Parliament started on a stormy note last week. Question hour was disrupted on most days and only one government bill was passed. There are 11 days left in the session and more than 40 bills pending for parliamentary approval. With the 15th Lok Sabha drawing to an end, this session is being viewed as a "make or break" session for the government to get its legislative agenda through Parliament. Since 2010, there has been much debate in Parliament on corruption and an important part of the government's legislative agenda was the introduction of nine bills in the Lok Sabha to address corruption and improve governance through effective delivery of public services. Three of these bills have been passed by the Lok Sabha and are currently pending before the Rajya Sabha. These include legislation to address corruption in public office, enforce standards and accountability in the judiciary, and protect whistleblowers. The government has proposed amendments to each of these bills that the Rajya Sabha will have to consider and pass. If the Rajya Sabha passes these bills with amendments, they will be sent back to the Lok Sabha for approval. It is difficult to assess in what timeframe these bills will become law, given that both Houses need to agree on the amendments. The Lokpal and Lokayuktas Bill creates a process for receiving and investigating corruption complaints against public officials, including the Prime Minister, Ministers and Members of Parliament, and prosecuting these in a timebound manner. The government amendments include allowing states the flexibility to determine their respective Lokayuktas and giving the Lokpal power of superintendence over the CBI, if the case has been referred by him. A mechanism to protect whistleblowers and create a process for receiving and investigating complaints of corruption or wilful misuse of discretion against a public servant are proposed under the Whistleblowers' Protection Bill, 2010. The amendments proposed by the government prohibit whistleblowing if the disclosure of information affects the sovereignty of the country and its strategic, scientific and economic interest. The Judicial Standards and Accountability Bill requires judges to declare their assets, lays down judicial standards and establishes processes for the removal of judges of the Supreme Court and high courts. The bill is not listed in the government's legislative agenda for the monsoon session and media reports suggest that the government intends to make amendments to it. In the arena of strengthening governance and effective delivery of public services, there are three bills currently pending in Parliament. The Citizens' Charter Bill confers the right to timebound delivery of goods and services on every citizen and creates a mechanism for redressing complaints on such matters. The Electronic Delivery of Services Bill mandates that Central and state governments shall deliver public services electronically no later than eight years from the enactment of the law. The parliamentary standing committee had highlighted that the Citizens' Charter Bill and Electronic Delivery of Services Bill have an inherent overlap, which the government would have to resolve. While the former is listed for passing in this session, the government plans to withdraw the latter and replace it with a new bill. This new bill is not part of the list that is up for consideration and passing this session. To create a reliable method of identifying individuals to facilitate their access to benefits and services the National Identification Authority of India Bill was introduced in Parliament to provide unique identification numbers ("aadhaar") to residents of India. This bill has not been listed for parliamentary approval during this session. Two other pending bills do not find place in the government's legislative agenda for the session either. These include legislation that curbs the holding and transfer of benami property and regulates the procurement process in government departments to ensure transparency, accountability and probity. The Prevention of Bribery of Foreign Public Officials Bill, which imposes penalties on Indian companies and individuals who bribe officials of a foreign government or international agency, is listed for passing this session. Each of these nine bills were introduced in the Lok Sabha. If they are not passed by both Houses before the 15th Lok Sabha is dissolved in 2014, no matter where they are in the legislative process, the bills will lapse. This implies that the entire legislative process will have to start all over again, if and when there is political will to legislate on these issues in the 16th Lok Sabha. The challenges in getting legislation passed by Parliament are many, given that its overall productive time, especially time spent on legislation, is decreasing. Typically, Parliament spends about 25 per cent of its time debating legislation, but in the past few years this average has declined to 15 per cent. While the time lost by the House due to frequent adjournments is difficult to make up, parliamentarians will have to cautious about passing bills without the rigours of parliamentary debate. It is uncertain what the trajectory of the anti-corruption legislation in Parliament will be — enacted as law or resigned to a pool of lapsed legislation.