Safety has been one of the biggest concerns in the Indian Railways system.  While the number of accidents have gone down over the last few years, the number still remains over 100 accidents a year.  In light of the recent train accidents in Uttar Pradesh (UP), we present some details around accidents and safety in the Indian Railways.

Causes of rail accidents

The number of rail accidents has declined from 325 in 2003-04 to 106 in 2015-16.[1]  The number of rail accidents as per the cause are shown in the graph below.  In 2015-16, majority of the accidents were caused due to derailments (60%), followed by accidents at level crossings (33%).1  In the last decade, accidents caused due to both these causes have reduced by about half.  According to news reports, the recent railway accidents in UP were caused due to derailment of coaches.

1

Derailments

Between 2003-04 and 2015-16, derailments were the second highest reason for casualties.2  The Standing Committee on Railways, when examining the safety in railways, had noted that one of the reasons for derailments is defect in the track or coaches.  Of the total track length of 1,14,907 kms in the country, 4,500 kms should be renewed annually.2  However, in 2015-16, of the 5,000 km of track length due for renewal, only 2,700 km was targeted to be renewed.2  The Committee had recommended that Indian Railways should switch completely to the Linke Hoffman Busch (LHB) coaches as they do not pile upon each other during derailments and hence cause lesser casualties.2

Un-manned level crossings

Un-manned level crossings (UMLCs) continue to be the biggest cause of casualties in rail accidents.  Currently there are 14,440 UMLCs in the railway network.  In 2014-15, about 40% of the accidents occurred at UMLCs, and in 2015-16, about 28%.2  Between 2010 and 2013, the Ministry fell short of meeting their annual targets to eliminate UMLCs.  Further, the target of eliminating 1,352 UMLCs was reduced by about 50% to 730 in 2014-15, and 820 in 2015-16.2  Implementation of audio-visual warnings at level crossings has been recommended to warn road users about approaching trains.2  These may include Approaching Train Warning Systems, and Train Actuated Warning Systems.2  The Union Budget 2017-18 proposes to eliminate all unmanned level crossings on broad gauge lines by 2020.

Casualties and compensation

In the last few years, Railways has paid an average compensation of Rs 3.03 crore every year for accidents (see figure below).[2]

2

Note: Compensation paid during a year relates to the cases settled and not to accidents/casualties during that year.

Consequential train accidents

Accidents in railways may or may not have a significant impact on the overall system.  Consequential train accidents are those which have serious repercussions in terms of loss of human life or injury, damage to railway property or interruption to rail traffic.  These include collisions, derailments, fire in trains, and similar accidents that have serious repercussions in terms of casualties and damage to property.  These exclude cases of trespassing at unmanned railway crossings.

As seen in the figure below, the share of failure of railways staff is the biggest cause of consequential rail accidents.  The number of rail accidents due to failure of reasons other than the railway staff (sabotage) has increased in the last few years.

3

Accidents due to failure of railway staff

It has been noted that more than half of the accidents are due to lapses on the part of railway staff.2  Such lapses include carelessness in working, poor maintenance, adoption of short-cuts, and non-observance of laid down safety rules and procedures.  To address these issues, conducting a regular refresher course for each category of railway staff has been recommended.2

Accidents due to loco-pilots2,[3]

Accidents also occur due to signalling errors for which loco-pilots (train-operators) are responsible.  With rail traffic increasing, loco-pilots encounter a signal every few kilometres and have to constantly be on high alert.  Further, currently no technological support is available to the loco-pilots and they have to keep a vigilant watch on the signal and control the train accordingly.2 These Loco-pilots are over-worked as they have to be on duty beyond their stipulated working hours.  This work stress and fatigue puts the life of thousands of commuters at risk and affects the safety of train operations.2  It has been recommended that loco-pilots and other related running staff should be provided with sound working conditions, better medical facilities and other amenities to improve their performance.2

Actions taken by Railways with regard to the recent train accident

According to news reports, the recent accident of Utkal Express in UP resulted in 22 casualties and over 150 injuries.[4]  It has also been reported that following this incident, the Railways Ministry initiated action against certain officials (including a senior divisional engineer), and three senior officers (including a General Manager and a Railway Board Member).

The Committee on Restructuring of Railways had noted that currently each Railway zone (headed by a General Manager) is responsible for operation, management, and development of the railway system under its jurisdiction.[5]  However, the power to make financial decisions does not rest with the zones and hence they do not possess enough autonomy to generate their own revenue, or take independent decisions.5

While the zones prepare their annual budget, the Railway Board provides the annual financial budget outlay for each of them.  As a result of such budgetary control, the GM’s powers have been reduced leaving them with little independence in planning their operations.5

The Committee recommended that the General Managers must be fully empowered to take all necessary decisions independent of the Railway Board.5  Zonal Railways should also have full power for expenditure and re-appropriations and sanctions.  This will make each Zonal Railway accountable for its transport output, profitability and safety under its jurisdiction.

Under-investment in railways leading to accidents

In 2012, a Committee headed by Mr. Anil Kakodkar had estimated that the total financial cost of implementing safety measures over the five-year period (2012-17) was likely be around Rs one lakh crore.  In the Union Budget 2017-18, the creation of a Rashtriya Rail Sanraksha Kosh was proposed for passenger safety.  It will have a corpus of Rs one lakh crore, which will be built over a five-year period (Rs 20,000 crore per year).

The Standing Committee on Railways had noted that slow expansion of rail network has put undue burden on the existing infrastructure leading to severe congestion and safety compromises.2  Since independence, while the rail network has increased by 23%, passenger and freight traffic over this network has increased by 1,344% and 1,642% respectively.2  This suggests that railway lines are severely congested.  Further, under-investment in the sector has resulted in congested routes, inability to add new trains, reduction of train speeds, and more rail accidents.2  Therefore, avoiding such accidents in the future would also require significant investments towards capital and maintenance of rail infrastructure.2

Tags: railways, safety, accidents, finances, derailment, casualty, passengers, train

[1] Railways Year Book 2015-16, Ministry of Railways, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/stat_econ/IRSP_2015-16/Year_Book_Eng/8.pdf.

[2] “12th Report: Safety and security in Railways”, Standing Committee on Railways, December 14, 2016, http://164.100.47.193/lsscommittee/Railways/16_Railways_12.pdf.

[3] Report of High Level Safety Review Committee, Ministry of Railways, February 17, 2012.

[4] “Utkal Express derailment: Four railway officials suspended as death toll rises to 22”, The Indian Express, August 20, 2017, http://indianexpress.com/article/india/utkal-express-train-derailment-four-railway-officers-suspended-suresh-prabhu-muzaffarnagar-22-dead-4805532/.

[5] Report of the Committee for Mobilization of Resources for Major Railway Projects and Restructuring of Railway Ministry and Railway Board, Ministry of Railways, June 2015, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/HLSRC/FINAL_FILE_Final.pdf.

The counting of votes for General Election 2019, which concluded on Sunday, will begin tomorrow, i.e., 23rd May at 8 AM.  The election was conducted in 7 phases for 543 constituencies of Lok Sabha.  The Election Commission of India (ECI) uses Electronic Voting Machines (EVM) to conduct elections. Since 2000, ECI has conducted 113 assembly elections and three general elections using EVMs.[1]  Voter Verified Paper Audit Trail (VVPAT) system was added to EVMs in 2013 to increase transparency and improve voter confidence in the system.  The VVPAT system generates a printed paper slip bearing the name and election symbol of the candidate.  On April 8, 2019, Supreme Court instructed the ECI that printed VVPAT slips from randomly selected five polling stations in each assembly segment of a parliamentary constituency should be matched with EVMs.[2]  In this blog, we explain the election counting process in India.

Who is responsible for counting the votes?

The Returning Officer (RO) is responsible for conducting elections in a constituency, which also includes counting of votes.[3] The RO is an officer of the government or a local authority nominated by the ECI for each constituency in consultation with the state government.[4]

Where does the counting take place?

The RO decides the place where the votes will be counted for the parliamentary constituency.  The date and time of counting is fixed by the ECI.  Ideally counting of votes for a constituency should be done at one place, preferably at the Headquarter of the RO in that constituency.  It should be performed under the direct supervision of the RO.  However, each Parliamentary Constituency has multiple assembly segments.  In this situation, counting can take place at different locations for various assembly segments under the direct supervision of an Assistant Returning Officer (ARO).

Layout of the Counting Hall

Page 431, Handbook for Returning Officer Document 23 Edition 1, Election Commission of India

Counting of votes for each assembly segment of a parliamentary constituency is performed in a single hall.  In each round of counting, votes from 14 EVMs are counted.  In case of simultaneous parliamentary and assembly elections, such as Odisha, the first seven tables are used for counting votes for assembly elections, and the rest for parliamentary elections.

In constituencies with a large number of candidates, it may not be possible to count votes for all candidates in a single hall without overcrowding it.  In such a situation, the number of counting halls or tables can be increased with the prior permission of the ECI.  A hall can also be used for counting votes of another assembly segment after the results of the first segment are declared.  However, counting may be done for only one assembly segment in a hall at any point of time.

What is the counting process?

Counting is performed by counting supervisors appointed by the RO.  Counting staff is appointed through a three stage randomisation process to ensure impartiality.  Candidates along with their counting agents and election agents are also present in the counting hall.

Counting of votes begins with Electronically Transmitted Postal Ballots (ETPB) and Postal Ballots (PB). These votes are counted under the direct supervision of the RO. Counting of EVMs can start 30 minutes after the commencement of PB counting, even if all PBs have not been counted.  At the end of each round of counting, the results from 14 EVMs are declared.

What is the process for counting VVPAT slips?

The ECI prescribes the process for randomly selecting one EVM for each assembly segment of a parliamentary constituency for VVPAT matching.  The verification of VVPAT paper slips is conducted inside a secured VVPAT Counting Booth in the counting hall with access to authorised personnel only.  Any counting table in the hall can be converted into VVPAT Counting Booth after completing EVM vote counting.  Parliamentary constituencies generally have between five and ten assembly segments.

The Supreme Court has decided that VVPAT slips of five randomly selected polling stations for each assembly segment shall be matched with the result shown in the respective EVMs.  This implies that VVPAT paper slips need to be matched for about 25-50 machines for each parliamentary constituency.  This process requires personal supervision of RO/ARO.  The ECI has decided that the counting of five VVPATs will be done sequentially.[5]  The RO can declare the final result for the constituency after the VVPAT matching process has been completed.

What happens if there is a discrepancy between the VVPAT count and the EVM results?

In such a case, the printed paper slips count is taken as final. The ECI has not clarified whether there would be any further action (such as counting of all VVPATs in a constituency or assembly segment) if there is a discrepancy in the counts of one of the five VVPATs.

[1] https://www.eci.gov.in/files/file/8756-status-paper-on-evm-edition-3/.

[2] N Chandrababu Naidu and Ors. v. Union of India and Anr WP(C). 273/2019 decided on April 8, 2019.

[3] https://www.eci.gov.in/files/file/9400-hand-book-for-returning-officer-february-2019/.

[4] https://www.eci.gov.in/faqs/elections/election-machinery/faqs-election-machinery-r1/.

[5] https://www.eci.gov.in/files/file/10197-mandatory-verification-of-vvpat-paper-slips-regarding/.