In Budget Session 2018, Rajya Sabha has planned to examine the working of four ministries. The Ministry of Drinking Water and Sanitation is one of the ministries listed for discussion. In this post, we look at the key schemes being implemented by the Ministry and their status.
What are the key functions of the Ministry of Drinking Water and Sanitation?
As per the Constitution, supply of water and sanitation are state subjects which means that states regulate and provide these services. The Ministry of Drinking Water and Sanitation is primarily responsible for policy planning, funding, and coordination of programs for: (i) safe drinking water; and (ii) sanitation, in rural areas. From 1999 till 2011, the Ministry operated as a Department under the Ministry of Rural Development. In 2011, the Department was made an independent Ministry. Presently, the Ministry oversees the implementation of two key schemes of the government: (i) Swachh Bharat Mission-Gramin (SBM-G), and (ii) National Rural Drinking Water Programme (NRDWP).
How have the finances and spending priorities of the Ministry changed over time?
In the Union Budget 2018-19, the Ministry has been allocated Rs 22,357 crore. This is a decrease of Rs 1,654 crore (7%) over the revised expenditure of 2017-18. In 2015-16, the Ministry over-shot its budget by 178%. Consequently, the allocation in 2016-17 was more than doubled (124%) to Rs 14,009 crore.
In recent years, the priorities of the Ministry have seen a shift (see Figure 1). The focus has been on providing sanitation facilities in rural areas, mobilising behavioural change to increase usage of toilets, and consequently eliminating open defecation. However, this has translated into a decrease in the share of allocation towards drinking water (from 87% in 2009-10 to 31% in 2018-19). In the same period, the share of allocation to rural sanitation has increased from 13% to 69%.
What has been the progress under Swacch Bharat Mission- Gramin?
The Swachh Bharat Mission was launched on October 2, 2014 with an aim to achieve universal sanitation coverage, improve cleanliness, and eliminate open defecation in the country by October 2, 2019.
Expenditure on SBM-G: In 2018-19, Rs 15,343 crore has been allocated towards SBM-G. The central government allocation to SBM-G for the five year period from 2014-15 to 2018-19 has been estimated to be Rs 1,00,447 crore. Of this, up to 2018-19, Rs 52,166 crore (52%) has been allocated to the scheme. This implies that 48% of the funds are still left to be released before October 2019.
Construction of Individual Household Latrines (IHHLs): For construction of IHHLs, funds are shared between the centre and states in the 60:40 ratio. Construction of IHHLs account for the largest share of total expenditure under the scheme (97%-98%). Although the number of toilets constructed each year has increased, the pace of annual growth of constructing these toilets has come down. In 2015-16, the number of toilets constructed was 156% higher than the previous year. This could be due to the fact that 2015-16 was the first full year of implementation of the scheme. The growth in construction of new toilets reduced to 74% in 2016-17, and further to 4% in 2017-18.
As of February 2018, 78.8% of households in India had a toilet. This implies that 15 crore toilets have been constructed so far. However, four crore more toilets need to be construced in the next 20 months for the scheme to achieve its target by 2019.
Open Defecation Free (ODF) villages: Under SBM-G, a village is ODF when: (i) there are no visible faeces in the village, and (ii) every household as well as public/community institution uses safe technology options for faecal disposal. After a village declares itself ODF, states are required to carry out verification of the ODF status of such a village. This includes access to a toilet facility and its usage, and safe disposal of faecal matter through septic tanks. So far, out of all villages in the country, 72% have been verified as ODF. This implies that 28% villages are left to be verified as ODF for the scheme to achieve its target by 2019.
Information, Education and Communication (IEC) activities: As per the SBM-G guidelines, 8% of funds earmarked for SBM-G in a year should be utilised for IEC activities. These activities primarily aim to mobilise behavioural change towards the use of toilets among people. However, allocation towards this component has remained in the 1%-4% range. In 2017-18, Rs 229 crore is expected to be spent, amounting to 2% of total expenditure.
What is the implementation status of the National Rural Drinking Water Programme?
The National Rural Drinking Water Programme (NRDWP) aims at assisting states in providing adequate and safe drinking water to the rural population in the country. In 2018-19, the scheme has been allocated Rs 7,000 crore, accounting for 31% of the Ministry’s finances.
Coverage under the scheme: As of August 2017, 96% of rural habitations have access to safe drinking water. In 2011, the Ministry came out with a strategic plan for the period 2011-22. The plan identified certain standards for coverage of habitations with water supply, including targets for per day supply of drinking water. As of February 2018, 74% habitations are fully covered (receiving 55 litres per capita per day), and 22% habitations are partially covered (receiving less than 55 litres per capita per day). The Ministry aims to cover 90% rural households with piped water supply and 80% rural households with tap connections by 2022. The Estimates Committee of Parliament (2015) observed that piped water supply was available to only 47% of rural habitations, out of which only 15% had household tap connections.
Contamination of drinking water: It has been noted that NRDWP is over-dependant on ground water. However, ground water is contaminated in over 20 states. For instance, high arsenic contamination has been found in 68 districts of 10 states. These states are Haryana, Punjab, Uttar Pradesh, Bihar, Jharkhand, Chhattisgarh, West Bengal, Assam, Manipur, and Karnataka.
Chemical contamination of ground water has also been reported due to deeper drilling for drinking water sources. It has been recommended that out of the total funds for NRDWP, allocation for water quality monitoring and surveillance should not be less than 5%. Presently, it is 3% of the total funds. It has also been suggested that water quality laboratories for water testing should be set up throughout the country.
(Authored by Anil Nair) The Maharashtra Legislative Assembly recently passed the Maharashtra Housing (Regulation and Development) Bill. This is the first such Bill to be passed by any state, which sets up a housing regulator to regulate property transactions. The Bill seeks to set up a Housing Regulatory Authority to provide for relief to flat purchasers against sundry abuses, malpractices and difficulties related to the construction, sale, management and transfer of flats. According to news reports, the government felt that existing laws were not effective in protecting the interests of the flat purchasers and allowed the promoters to avoid statutory obligations imposed on them. The Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 1963 did not provide for an effective implementing arm for its various statutory provisions, as the buyers could only approach consumer forum or civil court for acts of omission or commission regarding its provisions. The current Bill passed by the Maharashtra Assembly proposes to repeal the 1963 Act. As per the Statement of Objects and Reasons of the Bill, the Regulatory Authority will strive to encourage growth and promotion of a healthy, transparent, efficient and competitive real estate market. The Bill specifies several conditions to be fulfilled by the developer to further transparency and fairness. All projects proposing to develop more than four flats or of land area exceeding 250 square meters have to submit and update details of the project on the website of the Housing Regulatory Authority. Developers would be required to disclose detailed information regarding the project including:
Failure to give possession of the flat on the agreed date would require repayment of the full amount paid by the buyer with interest. The Authority would also be empowered to penalise the developer up to an amount of one crore rupees for non-compliance with provisions in the Bill. Among other initiatives to assist the real estate industry, the Housing Regulatory Authority would promote rating of projects and of promoters, by the association of promoters, to improve the confidence level of investors and consumers through self-regulation. The full text of the Bill is available on the Government of Maharashtra website.