On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.

At noon today, the Finance Minister introduced a Bill in Parliament to address the issue of delayed debt recovery.  The Bill  amends four laws including the SARFAESI Act and the DRT Act, which are primarily used for recovery of outstanding loans.  In this context, we examine the rise in NPAs in India and ways in which this may be dealt with.

I. An overview of Non-Performing Assets in India 

Banks give loans and advances to borrowers which may be categorised as: (i) standard asset (any loan which has not defaulted in repayment) or (ii) non-performing asset (NPA), based on their performance.  NPAs are loans and advances given by banks, on which the borrower has ceased to pay interest and principal repayments. Graph for blog In recent years, the gross NPAs of banks have increased from 2.3% of total loans in 2008 to 4.3% in 2015 (see Figure 1 alongside*).  The increase in NPAs may be due to various reasons, including slow growth in domestic market and drop in prices of commodities in the global markets.  In addition, exports of products such as steel, textiles, leather and gems have slowed down.[i] The increase in NPAs affects the credit market in the country.  This is due to the impact that non-repayment of loans has on the cash flow of banks and the availability of funds with them.[ii]  Additionally, a rising trend in NPAs may also make banks unwilling to lend.  This could be because there are lesser chances of debt recovery due to prevailing market conditions.[iii]  For example, banks may be unwilling to lend to the steel sector if companies in this sector are making losses and defaulting on current loans. There are various legislative mechanisms available with banks for debt recovery.  These include: (i) Recovery of Debt Due to Banks and Financial Institutions Act, 1993 (DRT Act) and (ii) Securitisation and Reconstruction of Financial Assets and Security Interest Act, 2002 (SARFAESI Act).  The Debt Recovery Tribunals established under DRT Act allow banks to recover outstanding loans.  The SARFAESI Act allows a secured creditor to enforce his security interest without the intervention of courts or tribunals.  In addition to these, there are voluntary mechanisms such as Corporate Debt Restructuring and Strategic Debt Restructuring, which   These mechanisms allow banks to collectively restructure debt of borrowers (which includes changing repayment schedule of loans) and take over the management of a company.

II. Challenges and recommendations for reform

In recent years, several committees have given recommendations on NPAs. We discuss these below.

Action against defaulters: Wilful default refers to a situation where a borrower defaults on the repayment of a loan, despite having adequate resources. As of December 2015, the public sector banks had 7,686 wilful defaulters, which accounted for Rs 66,000 crore of outstanding loans.[iv]  The Standing Committee of Finance, in February 2016, observed that 21% of the total NPAs of banks were from wilful defaulters.  It recommended that the names of top 30 wilful defaulters of every bank be made public.  It noted that making such information publicly available would act as a deterrent for others.

Asset Reconstruction Companies (ARCs): ARCs purchase stressed assets from banks, and try to recover them. The ARCs buy NPAs from banks at a discount and try to recover the money.  The Standing Committee observed that the prolonged slowdown in the economy had made it difficult for ARCs to absorb NPAs. Therefore, it recommended that the RBI should allow banks to absorb their written-off assets in a staggered manner.  This would help them in gradually restoring their balance sheets to normal health.

Improved recovery: The process of recovering outstanding loans is time consuming. This includes time taken to resolve insolvency, which is a situation where a borrower is unable to repay his outstanding debt.  The inability to resolve insolvency is one of the factors that impacts NPAS, the credit market, and affects the flow of money in the country.[v]  As of 2015, it took over four years to resolve insolvency in India.  This was higher than other countries such as the UK (1 year) and USA (1.5 years).  The Insolvency and Bankruptcy Code seeks to address this situation.  The Code, which was passed by Lok Sabha on May 5, 2016, is currently pending in Rajya Sabha. It provides a 180-day period to resolve insolvency (which includes change in repayment schedule of loans to recover outstanding loans.)  If insolvency is not resolved within this time period, the company will go in for liquidation of its assets, and the creditors will be repaid from these sale proceeds.


  [i] ‘Non-Performing Assets of Financial Institutions’, 27th Report of the Department-related Standing Committee on Finance, http://164.100.47.134/lsscommittee/Finance/16_Finance_27.pdf. [ii] Bankruptcy Law Reforms Committee, November 2015, http://finmin.nic.in/reports/BLRCReportVol1_04112015.pdf. [iii] Volume 2, Economic Survey 2015-16, http://indiabudget.nic.in/es2015-16/echapter-vol2.pdf. [iv] Starred Question No. 17, Rajya Sabha, Answered on April 26, Ministry of Finance. [v] Report of the Bankruptcy Law Reforms Committee, Ministry of Finance, November 2015, http://finmin.nic.in/reports/BLRCReportVol1_04112015.pdf. *Source:  ‘Non-Performing Assets of Financial Institutions’, 27th Report of the Department-related Standing Committee on Finance, http://164.100.47.134/lsscommittee/Finance/16_Finance_27.pdf; PRS.